Addendum__1_QA_B2610COC_Lee_Wenner_Day_Docks_FINAL.pdf
PDF 455 KB Posted
- Solicitation number
- B-26-10-COC
- Issued by
- Brevard County, Florida
About this file
This is an Addendum 1 to the Invitation to Bid (ITB B-26-10-COC) issued by the City of Cocoa, Florida, for the Cocoa Waterfront Dock and Breakwater project known as the "Lee Wenner Day Docks." The addendum, dated July 22, 2026, addresses 29 questions and provides clarifications regarding the bidding documents and specifications for this waterfront construction project. The project involves the construction of a new day-slip marina facility at Lee Wenner Park, including permanent concrete docks, finger piers, marine piles, prestressed concrete pile installation, revetment construction, and associated marine components. The addendum clarifies critical technical requirements including pile design and installation criteria, corrugated tube specifications, stone gradation for armor revetment, prestressed concrete pile design responsibilities, utility verification procedures, demolition limits, geotechnical site conditions, pile penetration and refusal criteria, marine access and construction operations, and protection of existing facilities. Contractors are required to establish their own survey control and provide as-built surveys documenting compliance with specified tolerances, and the project is subject to environmental compliance requirements including turbidity monitoring and manatee protection per associated permits.
The addendum specifies that the City of Cocoa is responsible for obtaining Water Management District and USACE permits, while contractors must obtain all other required permits and associated fees. The project is being funded in part by a Florida Inland Navigation District (FIND) grant, with contractors required to comply with all FIND grant requirements including documentation, certified payrolls, schedule updates, inspection coordination, and closeout documentation for grant reimbursement. The addendum clarifies that the Contractor must engage a specialty engineer to design prestressed piles and concrete members, with the Owner and Engineer providing shop drawing reviews within 14 calendar days. Key material specifications are revised through the addendum, including marine mattress thickness (6 inches) with US 670 geotextile underlayment incorporating 2-foot overlap extensions, and armor stone gradation tolerances requiring installation within 6 inches above and no more than 2 inches below the neat line. The Contractor is responsible for all staging, material storage, equipment locations, fuel storage, and employee parking within Owner-approved areas that do not interfere with public operations, including boat ramp operations and public access.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
July 22, 2026
Addendum 1 To the Contract Documents and Specifications:
ITB B-26-10-COC
Cocoa Waterfront Dock and Breakwater “Lee Wenner Day Docks”
To All Plan Holders:
The following addresses and provides clarification of the Bidding Documents and Specifications as fully and completely as if the same were fully set forth therein. Receipt of this addendum must be noted on the Receipt of Addendum(s) and Acknowledgement Form.
A. This addendum includes and addresses the following questions. The questions are listed below numbered 1 through 29 with responses provided in red below the question.
1. On sheet C-11 the Min. Tip Elevation is -45’ and the Pile installation notes (5) give criteria on Allowable Bearing Resistance of the soil. It both are achieved before the full length of the pile is installed then are we allowed to cut off the pile? If so, what will be the purpose of the Corrugated Tube design in section A and B?
Answer: If installed piles reach both the minimum tip elevation and the allowable soil bearing resistance, the Contractor may cut the pile head at the cutoff elevation shown on C-11. Per Detail A on C-11, the corrugated tube must extend to at least the depth shown for dowel installation. To meet this requirement after cutoff, the Contractor may furnish piles with additional corrugated tube length.
2. On sheet C-15 the detail and gradation design could look closer to the following given the diameter of the largest class stone is over 3’. Will this be acceptable?
Finance Department, Purchasing 65 Stone Street • Cocoa, FL 32922
PHONE: (321) 433-8844
www.CocoaFL.gov
2 | P a g e
Answer:
The revetment generally requires 2 stone minimum thickness.
The armor gradation requirement is revised to the following:
3. A 6’&8’ wide prestressed is not common per my supplier. They offer 4’ and 5’. Would it be acceptable to use 2 ea. 4’ for the main dock and a 5’ for the map?
Answer: No.
4. Plan sheet C-11 Pre-Stressed Pile Details, Section B notes: "Fiber Bar Per Prestress Engineer". Is the contractor responsible for designing the pile design?
Answer: For clarification, Section B notes “Framing bars per Prestress Engineer”.
Drawing C-5, Prestressed Concrete Piles and Slabs (Deck), clarifies that the Contractor shall engage a specialty engineer to design the prestressed piles and concrete members.
5. Plan sheet C-11, Section C shows a cylinder in the center of the pile but does not mentioned what it is. What are the details of this cylinder?
Answer: Ignore the cylinder shown in Section C.
3 | P a g e
6. Plan sheet C-11, Section B shows framing bars in the same location where Section C shows (8) 0.60" DIA. Strands. Which detail do we use?
Answer: C-5, Prestressed Concrete Piles and Slabs (Deck), clarifies that the Contractor shall engage a specialty engineer to design the prestressed piles and concrete members. The prestressed engineer must determine the exact prestressing strand pattern and the location relative to the framing bars.
7. Plan sheet C-11 Detail A - Corrugated tube Elevation. Does the corrugated tube have a minimum amendment?
Answer: Per Detail A on C-11, the corrugated tube must extend to at least the depth shown for dowel installation. To meet this requirement after cutoff, the Contractor may furnish piles with additional corrugated tube length at their discretion and judgement.
8. Plan sheet C-11 Pile Design Notes - Note 4, similar to question 1. Does the contractor design the piles?
Answer: Drawing C-5, Prestressed Concrete Piles and Slabs (Deck), clarifies that the Contractor shall engage a specialty engineer to design the prestressed piles and concrete members.
9. What is the engineer's estimate or budget?
Answer: Please refer to the grant agreement for current estimated costs.
10. Existing Utilities and Site Information. The contract drawings identify existing utilities, capped conduits, overhead power, and existing drainage structures within the project limits. Please confirm:
All existing utilities have been verified.
Answer: Contractor is responsible for verifying utilities during construction.
Utility ownership and responsibility.
Answer: Contractor is responsible for verifying utilities during construction.
Utilities to remain in service.
Answer: There are no utilities to remain in service. Conduit penetrations at dock entrance/seawall interface will be capped. See Drawings.
Contractor responsibilities if unforeseen utility conflicts are encountered.
Answer: Notify the Owner.
Availability of any additional as-built utility information not included in the bid documents.
Answer: None available. Contractor is responsible for locating and verifying utilities.
4 | P a g e
11. Existing Structures and Demolition Limits. Please clarify:
Exact limits of demolition.
Answer: See construction drawings.
Removal requirements for piles below mudline.
Answer: The Owner is not currently aware of piles below the mudline.
Disposal requirements for demolished materials.
Answer: Contractor shall dispose of any demolished materials at an appropriate facility in accordance with Florida law.
Ownership of salvaged materials.
Answer: Unless otherwise directed by the Owner, all demolished materials shall become the property of the Contractor and shall be legally disposed of. Any materials identified by the Owner for salvage shall remain the property of the City of Cocoa and shall be delivered to a location designated by the Owner.
Whether abandoned foundations or piles may remain if outside the proposed work limits.
Answer: The Owner is not currently aware of relic piles/foundations in the project footprint. If encountered notify the Owner.
12. Geotechnical Information and Differing Site Conditions. Please confirm:
The provided geotechnical report is representative of all proposed pile locations.
Answer: The Contract Documents provide the geotechnical report for Contractor’s use and planning for pile driving. Contractor to review and bid accordingly.
No additional subsurface investigations are available.
Answer: The historical shallow boring information reports: COC013 Riverfront Universal Geotech Report 01 2019 (Attachment 1) and the COC011 T-Docks Universal Geotech Report 01 2019 (Attachment 2) are included as attachments to this addendum.
The contract includes provisions for differing site conditions should subsurface conditions differ materially from those indicated.
Answer: The Contract includes the differing site conditions provisions contained in the Contract Documents. Any unforeseen conditions shall be handled in accordance with the applicable contract requirements. The Contractor shall promptly notify the Owner before proceeding with work affecting the differing condition.
5 | P a g e
13. Pile Installation Requirements. Please provide clarification regarding:
Minimum pile penetration.
Answer: Drawing C-6, Prestressed Concrete Pile Installation, Note 1 provides the penetration criteria for installing prestressed concrete piles. Drawing C-11, Pile Data Table, provides the minimum tip for lateral stability and the minimum allowable bearing resistance. Drawing C-12 provides the minimum tip elevation for timber fender piles.
Refusal criteria.
Answer: Drawing C-6, Prestressed Concrete Pile Monitoring, Note 2 provides refusal criteria.
Installation tolerances.
Answer: Drawing C-6, Prestressed Concrete Pile Installation, Note 4 provides installation tolerances under the heading Maximum Deviations.
Cutoff elevations.
Answer: Drawing C-11, Pile Data Table, provides the cutoff elevations.
Acceptance criteria.
Answer: Drawing C-11, Pile Data Table, provides the cutoff elevations.
Required pile testing (PDA, dynamic, static, or integrity testing).
Answer: PDA, dynamic, static, or integrity testing is not required by the Contract.
Drawing C-11, Pile Data Table, provides cutoff elevations. Drawing C-6, Prestressed Concrete Pile Installation, Note 7 provides requirements for verifying bearing capacity.
Responsibility for testing costs.
Answer: Drawing C-6, Prestressed Concrete Pile Installation, Note 7 provides requirements for verifying bearing capacity. If the Contractor elects to perform pile testing, incorporate the cost into the bid price.
14. Marine Access and Construction Operations. Please clarify any restrictions associated with:
Barge size and draft.
Answer: Contractor is responsible for providing means and methods to complete project. Contractor shall review Bidding Documents and local, State, Federal requirements for restrictions.
Crane operations.
Answer: Contractor is responsible for providing means and methods to complete project. Contractor shall review Contract Documents and local requirements for restrictions. Contractor is advised overhead powerlines at the project site as indicated on Construction Documents.
6 | P a g e
Navigation restrictions.
Answer: Contractor must orient equipment as to not impact boat ramp operations.
Temporary channel closures.
Answer: Contractor must orient equipment as to not impact boat ramp operations.
Temporary mooring or spud locations.
Answer: Contractor must orient equipment as to not impact boat ramp operations.
15. Revetment Construction. Please clarify:
Measurement and payment quantities.
Answer: Quantiles are provided on Sheet C-15.
Stone gradation tolerances.
Answer: : Armor stone gradation is provided on Sheet C-15. Armor stone revetment shall be installed within 6” above neat line and not more than 2” below neat line.
Inspection requirements.
Answer: See submittal requirements on Drawings. Owner’s representative will inspect the work for compliance with Contractor furnished submittals such as but not limited to as-built survey, armor stone and marine mattress submittal requirements presented on Contract Documents.
Acceptance criteria.
Answer: Armor stone revetment shall be installed within 6” above neat line and not more than 2” below neat line.
**Contractor shall supply as-built survey to document the structures are within compliance of this tolerance and Contract Documents.**
Requirements for the Contractor’s stone placement plan.
Answer: See Sheet C-4 of Drawings.
16. Protection of Existing Facilities. Please identify acceptable methods for protecting:
Existing seawall.
Answer: Contractor to provide means and methods so as to not damage existing structures.
Existing pile-supported platform.
Existing bulkhead.
7 | P a g e
Existing drainage structures.
Adjacent public infrastructure during construction.
17. Public Access and Traffic Maintenance. Please clarify the minimum requirements for maintaining:
Public pedestrian access Boat ramp operations.
Vehicular circulation.
Temporary closures.
Contractor work zones.
Temporary fencing requirements.
Answer: See Section 1.01 of the ITB. The Contractor shall maintain safe public access to the site and adjacent facilities to the maximum extent practicable throughout construction. Temporary closures shall be minimized, coordinated with the Owner in advance, and approved prior to implementation. The Contractor shall provide and maintain all necessary traffic control devices, barriers, fencing, and pedestrian protection in accordance with applicable regulations."
18. Environmental Compliance. Please confirm all environmental requirements including:
Turbidity monitoring.
Answer: See permits and associated conditions within Contract Documents.
Manatee protection.
Answer: See permits and associated conditions within Contract Documents.
Protected species restrictions.
Answer: See permits and associated conditions within Contract Documents.
Seasonal work limitations.
Answer: See permits and associated conditions within Contract Documents.
Environmental reporting responsibilities.
Answer: See permits and associated conditions within Contract Documents.
8 | P a g e
19. FIND Grant Requirements. Please identify all contractor obligations associates with the Florida Inland Navigation District (FIND) grant, including:
Reporting.
Documentation.
Payment procedures.
Inspection requirements.
Closeout documentation.
Any grant-specific contract provisions not contained within the specifications.
Answer: The Contractor shall comply with all applicable requirements contained in the Bidding Documents and provide documentation reasonably requested by the Owner to support grant administration, including certified payrolls (if applicable), schedule updates, inspection coordination, payment documentation, material certifications, and closeout documentation necessary for grant reimbursement.
20. Survey Control. Please provide:
Horizontal control.
Answer: Contractor to establish their own survey control.
Vertical control.
Answer: Contractor to establish their own survey control.
Benchmark information
Answer: Contractor to establish their own survey control. Tolerances for various proposed construction features provided on Contract Documents.
Construction survey tolerances.
Answer: Contractor to establish their own survey control. Tolerances for various proposed construction features provided on Contract Documents.
As-built survey requirements.
Answer: See Sheet C-3
21. Contractor Staging and Site Logistics. Please identify approved locations for:
Equipment staging.
Material storage.
Crane assembly.
Fuel storage.
Temporary laydown areas.
Employee parking.
Answer: : See Section 1.01 of the ITB. All staging , material storage, equipment locations, fuel storage, and employee parking areas shall remain within areas approved by the Owner and shall not interfere with public operations.
9 | P a g e
22. Shop Drawings and Long-Lead Materials. Please clarify:
Anticipated shop drawing review durations.
Answer: The Owner and Engineer will review and provide shop drawing response no later than 14 calendar days.
Long-lead materials identified by the Engineer or Owner.
Answer: This is responsibility of the Contractor.
Procurement priorities that may impact the project schedule.
Answer: We currently do not have any procurement issues.
23. Weather Delays and Contract Time. Please clarify the contract provisions regarding:
Weather delays.
Names tropical storm or hurricane impacts.
Excusable delays.
Extension of contract time.
Answer: Weather delays, named storm impacts, excusable delays, and requests for extensions of contract time shall be administered in accordance with the Contract Documents. Any request for additional contract time shall be submitted in writing with supporting documentation for Owner review.
24. Bid Quantities and Bid Alternate. Please confirm:
Measurement and payment methodology.
Answer: See Sheet C-3/C-4 of Drawings.
Adjustment procedures for estimated quantities.
Answer: Refer to 4.24 of General Terms and Conditions regarding work quantities.
Award methodology for the Bid Alternate.
Answer: The Bidding Documents identify the work to be bid. The City reserves the right to evaluate all bids and make an award in accordance with the ITB, and applicable procurement requirements.
Whether the Alternate will be considered when determining the lowest responsive and responsible bidder.
Answer: The Bidding Documents identify the work to be bid. The City reserves the right to evaluate all bids and make an award in accordance with the ITB, and applicable procurement requirements.
25. General Contract Clarifications: Please confirm whether any additional addenda are anticipated addressing:
Technical revisions.
Answer: Not at this time other than clarification through official bid addenda.
10 | P a g e
Specification updates.
Answer: Not at this time other than clarification through official bid addenda.
Drawing revision.
Answer: Not at this time other than clarification through official bid addenda.
Permit conditions.
Answer: Available permits in Contract Documents are not anticipated to be changed.
Permits for the Bid Alternate – West Revetment has yet to be issued.
Utility Coordination.
Answer:
It is the Contractor’s responsibility to complete utility locates and associated coordination as required to complete work.
Environmental agency comments received after issuance of the bid documents.
Answer: This is unknown and out of the Owners control. It is not currently anticipated.
26. Is Builder’s Risk required?
Answer: Please refer to the bid documents.
27. In the Invitation to Bid, Attachment “E” Bid Price Schedule, the description for Item 34 is 5” Marine Mattress. The drawings indicate 6” Marine Mattress. Please clarify which thickness is required?
Answer: 6” marine mattress.
28. For the Revetment, is there a geotextile underlayment required under the marine mattress? If so, what are specifications/details?
Answer: Yes. The marine mattress structure shall incorporate and include US 670 fabric on the underside of mattress including 2-ft overlap extensions. See attached example detail figure to support bid development.
29. Is the owner or contractor responsible for handling the permitting process and fee?
Answer: Owner is obtaining the Water Management District and USACE permit. All other permits are to be obtained by the Contractor.
All other Bidding/Contract Documents and Specifications remain unchanged.
Should there be additional questions or clarification needed please contact the Purchasing and Contracts Division at purchasing@cocoafl.org.
Brian Dale, Procurement and Budget Manger
City of Cocoa mailto:purchasing@cocoafl.org