Addendum #1 Narrative 152732.00 .pdf

PDF 97 KB Posted

Attached to
Rifle Vets Living Center-Resident Safety&Accessibility Impro
Solicitation number
IFB1 IHKA 2017000258 4
Issued by
Garfield County, Colorado

About this file

This is an Addendum #1 document issued by Boulder Associates Architects on May 11, 2017, modifying the original contract documents for the Veterans Community Living Center at Rifle State Project 2016-032P15, which involves Resident Safety and Accessibility Improvements. The addendum provides clarifications regarding project execution and work specifications. Key operational requirements include maintaining building access during construction at the main entrance and north parking lot through either safe pedestrian access or phased work scheduling. The facility will remain operational during construction with capacity to vacate one corridor side for 7-hour shifts or up to 4 resident rooms at one time. Work hours are limited to Monday through Friday, 8 AM to 6 PM. Contractors must identify their proposed project completion timeline on the bid form, with the anticipated timeframe provided as an estimate only and not a maximum calendar day limit. The contract contains no liquidated damages provisions.

The addendum clarifies that Davis Bacon wages do not apply to this project. For electrical systems, General Conditions Article 42 supersedes specification section 260500.2.6 regarding warranty length. All existing exit lights must remain in place and be reinstalled in the new ceiling tile at the same location per keynote 5. The addendum also includes minor drawing sheet modifications to sheets A1.1 and L1.0 for clarification purposes, removing incidental linework and clarifying the scope of integral color concrete to align with architectural and civil drawings.

View the file

Other files

File Type Posted
Drawings - 5p12-15.pdf PDF
Addendum #1 - A1.1.pdf PDF
Drawings - 3p5-8.pdf PDF
Drawings - 7p20-23.pdf PDF
Part 1 - Project Manual .pdf PDF
Drawings - 6p16-19.pdf PDF
Part 3 - Project Manual.pdf PDF
Drawings - 4p9-11.pdf PDF
Drawings - Electrical E1.1.pdf PDF
Mandatory Walkthrough List- Rifle.pdf PDF
Addendum #1 -170512_Addendum1_LandscapeDwg_L1.0.pdf PDF
Drawings - Electrical E0 E.2.pdf PDF
Advertisement for Bid-Rifle 2017-04-26.docx DOCX document
Part 4 - Project Manual.pdf PDF
Drawings - 1p1.pdf PDF
Drawings - Electrical E1.0.pdf PDF
Part 2 - Project Manual.pdf PDF
Drawings - Electrical E2.1 E2.2 E3.1.pdf PDF
Drawings - 2p2-4.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Boulder Associates, Inc.

1426 Pearl Street | Suite 300 | Boulder, Colorado 80302 | 303.499.7795 | www.boulderassociates.com

BOULDER ■ SACRAMENTO ■ ORANGE COUNTY ■ SAN FRANCISCO ■ DALLAS

ADDENDUM #1

May 11, 2017

Veterans Community Living Center at Rifle

State Project: 2016-032P15 – Resident Safety and Accessibility Improvements

Boulder Associates Project No. 152732.00

Issued To: All Plan Holders

By: Boulder Associates Architects

This addendum forms part of the Contract Documents and modifies the original documents dated February 1, 2017.

Modification to the documents include, but are not limited to:

Clarifications:

- For work at the building main entrance and north parking lot off 5th Street, contractor to maintain building access by one of the following methods:

o Provide safe pedestrian access from 5th Street to the main entrance (automatic sliding door) throughout the course of the project, or o Phase work so when the porte cochere / main entrance is inaccessible the north parking lot and side entrance are completely open and when the north parking lot and side entrance are closed, the main entrance is free and clear to the street.

- For work in the corridors, common areas, and at the windows, the facility will remain operational during construction. The facility has the capacity to vacate one side of a given corridor for 7-hour shifts or vacate up to

4 resident rooms at one time.

- Work hours are Monday – Friday, 8AM – 6PM.

- Davis Bacon wages do not apply.

- Contractor is to identify the number of days to complete the project on the bid form. The anticipated time frame listed in the advertisement for bids is an estimate and not a maximum number of calendar days to complete the project.

- There are no liquidated damages on this project.

- For electrical systems, the General Conditions, article 42 supersede specification section 260500, 2.6 on length of warranty for electrical systems.

- All existing exit lights are to remain. Where they are located in the new ceiling tile, they are to be reinstalled in same location in the new tile per keynote 5.

Drawing Sheets Modified:

A1.1 – Porte Cochere – Enlarged Plan

- Removed incidental linework from above for clarity.

L1.0 – Landscape Plan

- Clarified scope of integral color concrete to match architectural and civil drawings.

END OF ADDENDUM #1