About this file

This document is Addendum #1 issued by the Oakland County Water Resources Commissioner for the Walnut Lake No. 1 Pump Station Conveyance Correction Action Plan Phase 2 project located in Southfield, Michigan, dated June 2, 2025. The addendum modifies several key aspects of the original bidding documents, including extending the deadline for bidder questions to 3:00 pm on Monday, June 16, 2025, and adding geotechnical and historical reference documents to the Supplementary Conditions. The addendum also changes the Bid Form, specifically replacing the "Access Shaft Chemical Grouting" line item with "Access Shaft Exterior Soil Stabilization" and expanding the scope of investigation for access structures to include two 4-inch diameter concrete cores at each proposed penetration.

The addendum updates the measurement and payment section to reflect the changes in the bid items, with the new Bid Item 5B allowance to be used for soil stabilization activities identified during the investigation efforts. Additionally, the document includes updates to state requirements in Appendix A and B, replacing sections related to domestic preference, telecommunications equipment prohibitions, Davis-Bacon wages, labor standards, Disadvantaged Business Enterprise requirements, and certification regarding debarment with updated documents from the Michigan Department of Environment, Great Lakes, and Energy (EGLE). The modifications aim to provide more detailed information and clarify the project requirements for potential bidders.

View the file

Other files

File Type Posted
SAN-1600EV-CP-PP-SHT1327.TIF TIF image
DC-117.pdf PDF
DC-123 (1).pdf PDF
SAN-1233EV-RD-PP-CONT3-SHT17OF17.TIF TIF image
EQP1451-Equivalency-Projects-Contract-Boilerplate-Language.pdf PDF
SAN-1233EV-RD-CO-CONT3.TIF TIF image
19880901_PCI-41 EF Relief Outlet Sewer Section II - Complete Set.pdf PDF
SAN-1600EV-CP-SD-SHT1335.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT2OF17.TIF TIF image
Addendum 3 attachments (1).pdf PDF
SAN-1600EV-CP-PP-SHT1321.TIF TIF image
SAN-1600EV-CP-PP-SHT1326.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT9OF17.TIF TIF image
SAN-1600EV-CP-PP-SHT1323.TIF TIF image
SAN-1233EV-RD-MI-CONT3-SHT14OF17.TIF TIF image
SAN-1233EV-RD-SD-CONT3-SHT13AOF17.TIF TIF image
01 22 00 - measurement and payment.pdf PDF
SAN-1600EV-CP-PP-SHT1322.TIF TIF image
SAN-1233EV-RD-MI-CONT3-SHT14AOF17.TIF TIF image
SAN-1600EV-CP-PP-SHT1328.TIF TIF image
SAN-1600EV-CP-PP-SHT1325.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT4OF17.TIF TIF image
PCI-41 EF Relief Outlet Sewer Section II - Complete Set Final Connection (1).pdf PDF
VIDEO Help.pdf PDF
SAN-1233EV-RD-PP-CONT3-SHT7OF17.TIF TIF image
OCWRC_Walnut CAP1 EFSD 21 inch Sewer Abandonment_FKE Geotech Data Report_24-162_04-27-2025.pdf PDF
VR-14 and EFSD Outlet Schematics (1).pdf PDF
SAN-1600EV-CP-PP-SHT1320.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT1OF17.TIF TIF image
DC-123.pdf PDF
SAN-1600EV-CP-PP-SHT1319.TIF TIF image
24-162 Pre-bid meeting sign in.xlsx XLSX spreadsheet
24-162 Pre-bid meeting sign in.pdf PDF
SAN-1233EV-RD-PP-CONT3-SHT6OF17.TIF TIF image
SAN-1600EV-CP-SD-SHT1334.TIF TIF image
Updated Davis Bacon.pdf PDF
SAN-1233EV-RD-PP-CONT3-SHT10OF17.TIF TIF image
SAN-1233EV-RD-SD-CONT3-SHT12OF17.TIF TIF image
SAN-1600EV-CP-PP-SHT1329.TIF TIF image
OCWRC_Walnut CAP1 EFSD Siphon Removal_FKE Geotech Inv Report_24-162_04-27-2025.pdf PDF
FLow Control Pages from OCWRC_Walnut 1 CAP_EFSD Outlet Siphon Phase 2_IFB Specifications_ASI.pdf PDF
SAN-1600EV-CP-PP-SHT1324.TIF TIF image
OCWRC_Walnut 1 CAP_EFSD Outlet Siphon Phase 2_IFB Plans (1) (1).pdf PDF
SAN-1233EV-RD-PP-CONT3-SHT3OF17.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT5OF17.TIF TIF image
SAN-1233EV-RD-MI-CONT3-SHT15OFR17.TIF TIF image
OCWRC Walnut 1 CAP EFSD Outlet Siphon Phase 2 IFB Plans_Addendum 3.pdf PDF
SAN-1233EV-RD-SD-CONT3-SHTA.TIF TIF image
DC-675.pdf PDF
Siphons Phase 2 Presentation Slides.pdf PDF
Show 40 more

Latest 50 of 61 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OAKLAND COUNTY WATER RESOURCES COMMISSIONER

Page A1-1 of A1-3 06/02/2025

ADDENDUM #1

Oakland County Water Resources Commissioner

Walnut Lake No. 1 Pump Station Conveyance Correction Action Plan Phase 2

Southfield, Michigan

Addendum #1

June 2, 2025

To all bidders: On behalf of the OWNER, this ADDENDUM to the Bidding Documents is issued to you by the Engineer for the Project described above.

The following changes and/or clarifications shall be incorporated in the Bidding Documents of the Project and the cost, all inclusive, thereof shall be included in the associated amount shown on each Bidder's Proposal:

Item 1 – Refer to 00 11 13 WRC DC-116 Advertisement to Bid.

1.1 REPLACE. Replace the paragraph in the Advertisement to Bid:

Questions, comments, or concerns of any Bidder regarding the Bidding Documents or the project, must be submitted in writing via the BidNet Direct website by 3:00 pm on Monday, June 9, 2025. No questions received after this time will be given consideration. Questions will be reviewed, and formal responses will be disseminated via addenda on BidNet Direct.

With the following paragraph:

Questions, comments, or concerns of any Bidder regarding the Bidding Documents or the project, must be submitted in writing via the BidNet Direct website by 3:00 pm on Monday, June 16, 2025. No questions received after this time will be given consideration. Questions will be reviewed, and formal responses will be disseminated via addenda on BidNet Direct.

Item 2 – Refer to 00 73 00 WRC DC-675 Supplementary Conditions.

1.1 REVISION. Added the following documents to the Supplementary Conditions:

1.1.01 Added Section L, which states:

Geotechnical Information

Added the following geotechnical reports for reference:

“Geotechnical Investigation Report Walnut Lake Pump Station No. 1 Corrective Action Plan EFSD Siphon Removal” by FK Engineering dated April 27, 2025

Page A1-2 of A1-3

“Geotechnical Investigation Report Walnut Lake Pump Station No. 1 Corrective Action Plan 21-inch Sewer Abandonment” by FK Engineering dated April 27, 2025

Documents are available on request.

1.1.02 Added Section M, which states:

Historical Information

Added the following historical documents for reference:

VR-14 and EFSD Outlet Schematics

DWSD PCI-41 EF Relief Outlet Sewer Section II Plan Set

DWSD PC-637 Plan Set

MDOT Job No. 76902A (1600 EV) Plan Set

OCWRC Eight Mile Road Interceptor Sanitary Relief Sewer Contract No. 3 Plan Set

Documents are available on request.

Item 3 – Refer to 00 41 00 WRC DC-123 Bid Form.

1.1 REPLACE. Replace Bid Sheet Item No. 5B:

5B Access Shaft Chemical Grouting 25000 DLR 1 $25000

With the following Bid Sheet Item No. 5B:

5B Access Shaft Exterior Soil Stabilization 250000 DLR 1 $250000

Item 4 – Refer to 01 22 00 Measurement And Payment.

1.1 REPLACE. Replace the paragraph 1.6.06:

Bid Items 5A and 5B: Investigation of Access Structures (exterior) and Access Shaft Chemical Grouting. The lump sum price for Bid Item 5A shall constitute full compensation for all labor, supervision, tools, and all other work as noted in the Bid Documents and as specified herein to allow CONTRACTOR to investigate the conditions/nature of temporary earth retention systems used to facilitate construction of the existing access structures as shown on the project Bid Documents. The Bid Item 5B allowance is to be used to address chemical grouting activities as identified during Bid Item 5A efforts.

Page A1-3 of A1-3

With the following paragraph 1.6.06:

Bid Items 5A and 5B: Investigation of Access Structures (exterior) and Access Shaft Exterior Soil Stabilization. The lump sum price for Bid Item 5A shall constitute full compensation for all labor, supervision, tools, and all other work as noted in the Bid Documents and as specified herein to allow CONTRACTOR to investigate the conditions/nature of temporary earth retention systems and associated backfill used to facilitate construction of the existing access structures as shown on the project Bid Documents. Investigation to consist, at a minimum, (2) two 4-inch diameter concrete cores at each proposed penetration in the existing access structures (16 total). The Bid Item 5B allowance is to be used to address soil stabilization activities as identified during Bid Item 5A efforts.

Item 5 – Updated State Requirements in Appendix A and B.

1.1 REPLACE. Replace the following sections with updated documents from Michigan Department of Environment, Great Lakes, And Energy (EGLE):

• Domestic Preference Requirements

• Prohibition on Certain Telecommunications and Video Surveillance Services or Equipment

• Davis-Bacon and Related Acts/Prevailing Federal Wages

• Labor Standards Provisions for Federally Assisted Projects

• Disadvantaged Business Enterprise (DBE) Requirements

• Good Faith Efforts (GFE) Worksheet*

• Certification Regarding Debarment, Suspension, and Other Responsibility Matters

END OF SECTION