Siphons Phase 2 Presentation Slides.pdf

PDF 3 MB Posted

Attached to
WRC: Walnut Lake No. 2 Conveyance CAP Phase II
Solicitation number
Oak-0000000922
Issued by
Michigan

About this file

The document is a presentation slide deck for the Walnut Lake #1 Pump Station Corrective Action Plan Phase #2 project, prepared by the Water Resources Commissioner (WRC) of Oakland County, Michigan. The presentation outlines a complex sewer infrastructure rehabilitation project involving the Great Lakes Water Authority (GLWA) and Detroit Water and Sewerage Department (DWSD). The project involves hand-mining horseshoe tunnels to install new sewer lines with varying diameters (54-inch, 78-inch, and 96-inch), replacing existing sewer infrastructure, and modifying several critical chambers including the Junction Chamber, Meter Chamber, and Riser Chamber.

The project scope includes detailed technical processes such as debris removal, temporary sewer lining, tunneling operations, installing new steel gates, and abandoning existing sewer lines by grouting. The tunneling will be performed using hand-mining techniques above existing sewer lines, with tunnel diameters ranging from 8.5 to 10 feet depending on the pipe size. The project involves precise engineering modifications, including structural, electrical, and telemetry component updates across multiple chambers and manholes. The work is scheduled for June 2025 and represents a significant infrastructure improvement for the Walnut Lake area, focusing on enhancing sewer system reliability and capacity.

View the file

Other files

File Type Posted
19880901_PCI-41 EF Relief Outlet Sewer Section II - Complete Set.pdf PDF
Addendum 3 attachments (1).pdf PDF
EQP1451-Equivalency-Projects-Contract-Boilerplate-Language.pdf PDF
OCWRC_Walnut 1 CAP_EFSD Outlet Siphon Phase 2_IFB Plans (1) (1).pdf PDF
OCWRC_Walnut CAP1 EFSD 21 inch Sewer Abandonment_FKE Geotech Data Report_24-162_04-27-2025.pdf PDF
PCI-41 EF Relief Outlet Sewer Section II - Complete Set Final Connection (1).pdf PDF
SAN-1233EV-RD-CO-CONT3.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT2OF17.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT3OF17.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT4OF17.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT7OF17.TIF TIF image
SAN-1233EV-RD-SD-CONT3-SHTA.TIF TIF image
SAN-1600EV-CP-PP-SHT1321.TIF TIF image
SAN-1600EV-CP-PP-SHT1326.TIF TIF image
SAN-1600EV-CP-SD-SHT1335.TIF TIF image
01 22 00 - measurement and payment.pdf PDF
DC-117.pdf PDF
FLow Control Pages from OCWRC_Walnut 1 CAP_EFSD Outlet Siphon Phase 2_IFB Specifications_ASI.pdf PDF
OCWRC_Walnut CAP1 EFSD Siphon Removal_FKE Geotech Inv Report_24-162_04-27-2025.pdf PDF
SAN-1233EV-RD-PP-CONT3-SHT10OF17.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT5OF17.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT6OF17.TIF TIF image
SAN-1233EV-RD-SD-CONT3-SHT12OF17.TIF TIF image
SAN-1600EV-CP-PP-SHT1322.TIF TIF image
SAN-1600EV-CP-PP-SHT1324.TIF TIF image
SAN-1600EV-CP-PP-SHT1327.TIF TIF image
SAN-1600EV-CP-PP-SHT1329.TIF TIF image
Updated Davis Bacon.pdf PDF
VIDEO Help.pdf PDF
VR-14 and EFSD Outlet Schematics (1).pdf PDF
33 40 00 - Temporary Flow Diversion and Bypass Pumping (1).pdf PDF
ADDENDUM #3 922.pdf PDF
Addendum #1.pdf PDF
DC-116.pdf PDF
DC-123 (1).pdf PDF
DC-675.pdf PDF
EQP1451-Equivalency-Projects-Contract-Boilerplate-Language Project.pdf PDF
PC-637 (1).pdf PDF
SAN-1233EV-RD-PP-CONT3-SHT11OF17.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT16OF17.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT17OF17.TIF TIF image
SAN-1233EV-RD-PP-CONT3-SHT8OF17.TIF TIF image
SAN-1233EV-RD-SD-CONT3-SHT12AOF17.TIF TIF image
SAN-1233EV-RD-SD-CONT3-SHT13OF17.TIF TIF image
Walnut Lake No.1 Conveyance CAP Phase II Specs 5-21-2025 (1).pdf PDF
24-162 Pre-bid meeting sign in.pdf PDF
24-162 Pre-bid meeting sign in.xlsx XLSX spreadsheet
DC-123.pdf PDF
OCWRC Walnut 1 CAP EFSD Outlet Siphon Phase 2 IFB Plans_Addendum 3.pdf PDF
SAN-1233EV-RD-MI-CONT3-SHT14AOF17.TIF TIF image
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WALNUT LAKE #1

PUMP STATION

CORRECTIVE ACTION

PLAN PHASE #2

FKE HRC ASI

June 2025

1. Location

2. Southfield Highway TERS and Drop Connection

3. Investigation and Demolition of Existing Structures

4. Debris Removal and Temporary Sewer Lining

5. Tunneling and New Sewer Line

6. Meter Chamber Gate

7. Abandon Existing Sewer Lines

Topics

Location

Southfield Highway TERS and Drop Connection

TERS

Drop Connection

Investigation and Demolition of Existing Structures

Junction Chamber

Meter Chamber

MH

SOT140007 MH

SOT140002

Riser

Chamber

• To accommodate tunneling, existing structures except SOT140002 are to have all equipment, walls, floors, and roofs removed (SOT140002 equipment will remain until the new sewer is put into service).

• Following demolition, steel bracing is to be installed in all existing structures prior to tunneling.

• An investigation into what backfill is outside of structures to take place prior to tunneling.

Debris Removal and Temporary Sewer Lining

Debris Removal

Temporary Sewer Lining

• After debris removal, sewer to be temporarily lined with 54” FRPMP or braced with steel box beams within C-channels mounted to the pipe at springline. FRPMP to be pulled or carried in. No jacking of pipe to be allowed.

• Following temporary sewer work, the existing structures are to have concrete working platforms poured to assist with tunneling operations.

Tunneling and New Sewer Line

Tunnel Reaches

• Horseshoe tunnels for new sewers are to be hand-mined above the existing sewers connecting existing structures MH SOT140007, Junction Chamber, Meter Chamber, Riser Chamber, and MH SOT140002.

• 8.5-foot diameter horseshoe tunnels will be mined for 54-inch I.D. and 78-inch I.D. pipe installation, and 10-foot diameter horseshoe tunnels will be mined for 96-inch I.D. pipe installation.

Permanent Sewer Line Following hand-mining operations, FRPMP is to be grouted into place within the tunnels to complete the permanent sewer installation.

Linings to be pulled or carried in. No jacking of pipe to be allowed.

Meter Chamber Gate

Meter Chamber Gate

The Meter Chamber is to have a new steel gate installed following tunneling operations.

Abandon Existing Sewer Lines

Abandonment Existing sewers highlighted will be abandoned with grout after completion of drop connection and new sewer line.

Questions?