ADDENDA #2
430 KB Posted
- Solicitation number
- 22-106-WBS
- Issued by
- Bibb County, Georgia
About this file
This addendum document issued by the Macon Water Authority details the preproposal conference held on January 12, 2022, for the Request for Proposals regarding AMR Meter Replacement and MIU Installation Services. The project involves the replacement of approximately 41,000 Neptune T10 5/8" and 1" water meters located in meter pits and installation of Meter Interface Units (MIUs) with AMR (Automated Meter Reading) capabilities. The project is structured in three phases: a start-up phase, a 100-day test phase, and a 24-month installation phase. The RFP was released on December 15, 2021, with a preproposal conference conducted on January 12, 2022. Proposers were required to submit questions and clarifications by January 19, 2022, with sealed proposals due February 2, 2022, at 2:00 p.m. EST. Presentations and interviews were scheduled for February 21-24, 2022, with board recommendation of award on March 3, 2022, and anticipated notice of award on March 4, 2022.
Installation services required include field supervision, water meter and AMR radio transmitter installation, service line analysis on both sides of the meter, AMR drive-by reading tests for all MIUs, assessment of non-reporting MIUs, CIS integration and data management, and a one-year installation warranty. Proposers must meet minimum requirements including documentation of at least five AMR/AMI installations of similar size within the past eight years, evidence that the project manager oversaw at least five successful AMR/AMI projects, and proof that the contractor has been in business for at least ten years. The procurement includes Disadvantaged Business Enterprise (DBE) goals of 10% minority participation and 10% female participation annually, in accordance with Georgia's State Revolving Loan Fund requirements. Evaluation will be based on technical proposals scored up to 1,000 points with a 600-point minimum threshold, with the preferred proposer selected based on the lowest cost per technical point calculation. The addendum lists thirteen firms and individuals who attended the preproposal conference, including representatives from Concord, Envocore, Metals & Materials Engineers LLC, Olameter, PMI, and Vanguard Utility Services Inc.
Text of this file
BOARD MEMBERS
Samuel F. Hart, Sr.
Chairman
Frank Patterson
Vice-Chairman
Dr. Anissa Jones
Desmond D. Brown
Dwight Jones
Valerie Wynn
Bill Howell
Joey Leverette
Executive Director and President
790 Second Street
P.0.Box 108
Macon, GA 31202
(478) 464-5600 Fax: (478) 750-2007
MaconWater.org
ADDENDA #2
JANUARY 14, 2022
To: ALL POTENTIAL PROPOSERS
Re: PREPROPOSAL CONFERENCE FOR THE REQUEST FOR
PROPOSALS FOR AMR METER REPLACEMENT AND MIU
INSTALLATION SERVICES
A preproposal conference was held on January 12, 2022 at 2:00 PM EST. This addenda lists the potential Proposer attendees and includes the presentation given to the attendees.
Proposers shall acknowledge receipt of, and compliance with, this addenda by signing below and returning it with a Proposal submission as Part K.
Sincerely, Barry Smallwood Barry Smallwood
Purchasing Specialist
We hereby acknowledge receipt of, and compliance with, this addenda in conjunction with the above Request for Proposal.
Signature Firm Name
Addenda #2
Full Name Company
Doug Oberheu Concord
Joe Ogg Concord
Jordan Bell Concord
Levi Capaci Concord
Brian King Envocore
Ryan Smith Envocore
Sandra Pierre Metals & Materials Engineers, LLC
Seana Brooks Metals & Materials Engineers, LLC
Justin McCloud Olameter
Stephen Clemens Olameter
Don Shuler PMI
Alicia Lawrence Vanguard Utility Services, Inc
Kathy Kolter Vanguard Utility Services, Inc
AMR METER REPLACEMENT AND
MIU INSTALLATION SERVICES
Preproposal Conference January 12, 2022
Proposal Due 2:00 PM EST February 2, 2022
Agenda
1. Introductions
2. Overview of the Project
3. Procurement Award Timeline
4. Point of Contact
5. DBE Goals
6. Minimum Requirements
7. Proposal Elements & Forms
8. Evaluation Process
9. Questions
Overview of the Project
• Meter replacements and MIU installations for AMR
• Neptune T10 5/8” and 1” Meters
• ~ 41,000 meters in meter pits
• Project Phases − Start-up Phase
− Test Phase (100 days)
− Installation Phase (24 months)
Overview of the Project
Procurement Award Timeline
Event Date
RFP Release December 15, 2021
Preproposal Conference January 12, 2022
Deadline for Questions & Clarifications by
Proposers
January 19, 2022
Proposal Closing Date (sealed bid opening) February 2, 2022, 2:00PM
Presentations and Interviews February 21-24, 2022
Recommendation of Award to the Board March 3, 2022
Anticipated Notice of Award Date March 4, 2022
Point of Contact
Contact: Harold Blevins, Director of Information Technology
Address: 790 Second Street Macon, GA 31202-0108
E-mail: hblevins@maconwater.org
Phone: 478-464-5625
Proposers shall not contact MWA staff, Board members, or consultants in relation to this procurement, potential disqualification.
Responses to questions will be posted to the Georgia Procurement
Registry website and the Macon Water Authority website as
Addenda.
mailto:hblevins@maconwater.org
Description of Services
• Installation services including:
− Field supervision
− Water meter and AMR radio transmitters
− Analyze service line type (both sides of the meter)
• Test AMR drive-by reading for all MIUs − Assess non-reporting MIUs
− Report all MIUs that cannot be read by AMR drive-by for Authority resolution
− All meter and MIU installations shall pass the RSR
• CIS integration and data management
• One (1) year installation warranty
• Public outreach implementation
DBE Goals and Forms
• Georgia’s State Revolving Loan Fund (SRF) Good Faith Efforts (RFP Section B.19.2)
• Additional information in the SWRCB's "Guidelines for Clean Water State Revolving Fund (CWSRF) Program Disadvantage Business Enterprise Requirements” available at:
https://gefa.georgia.gov/water-resources/loan-documents
TIME- TABLES
GOALS FOR MINORITY
PARTICIPATION FOR EACH TRADE
GOALS FOR FEMALE
PARTICIPATION IN EACH TRADE
Annual 10% 10% https://gefa.georgia.gov/water-resources/loan-documents
Minimum Requirements
1. Provide documentation of the completion of least five (5) AMR/AMI installations of similar size within the past eight (8) years.
2. Provide documentation of the Project Manager having direct oversight of the successful implementation of at least five (5) AMR/AMI projects.
3. Produce documentation of the contractor being in business for at least ten (10) years.
Part B.12 Proposal Elements and Forms Volume I: Technical Proposal
• Letter of Introduction
• Section 1: Project Overview
• Section 2: Installation Services
• Section 3: Data Management
• Section 4: Mandatory Technical Proposal Forms
C.1.1 Proposal Execution Form (Inclusive of sections C.1.1- C.1.8)
C.1.9 Proposer’s Statement of Financial Information Form
C.1.10 Use of American Iron and Steel Form
C.1.11 Minimum Requirements Form
C.1.12 DBE Reporting Forms
C.1.13 Contractor’s Written Oath
Appendices: 1. Preliminary Project Schedule
2. Resumes of key project team members
Part B.12 Proposal Elements and Forms
Volume II: Financial Proposal
• Section 1: J.1 Payment Item Schedule
• Section 2: Bid Forms Part C 2.1 Bid Security Form
Part C 2.2 Bidder’s Bond Form
Evaluation Process
• Volume I: Technical Proposal
• Proposal format must comply with Section B.12 Proposal Elements and Forms
• Section H includes instructions for proposal elements and a list of questions whose responses must be included in the proposal
• 1000 = Available technical points
• 600 = Minimum technical point threshold for short-listing and presentation
• Technical scores will be adjusted following presentations
• Proposals with adjusted technical scores of at least 600 will continue to be evaluated
Evaluation Process
• Volume II: Financial Proposal
• Each qualifying proposal will be evaluated by calculating the cost per technical point (i.e., Total Project Cost / Total Technical Points)
• The Proposer with the lowest cost per technical point will become the preferred proposer with whom the Authority may enter into negotiations.
Questions?
Event Date
RFP Release December 15, 2021
Preproposal Conference January 12, 2022
Deadline for Questions & Clarifications by
Proposers
January 19, 2022
Proposal Closing Date (sealed bid opening) February 2, 2022, 2:00PM
Presentations and Interviews February 21-24, 2022
Recommendation of Award to the Board March 3, 2022
Anticipated Notice of Award Date March 4, 2022
| MWA Addenda #2.pdf |
| MWA Addenda #2.pdf |
| MWA Addenda #2.pdf |
| MWA Addenda #3.pdf |
| MWA Addenda #3-Original.pdf |
| MWA - Preproposal Conference.pdf |
Other files
| File | Type | Posted |
|---|---|---|
| Award Information | — | |
| ADDENDA #3 | — | |
| LIST OF PROPOSALS RECEIVED | — | |
| RFP DOCUMENT | — | |
| ADDENDA #1 | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .