This is a Bid Schedule template for a five-year requirements contract for boring and erosion control services at Malmstrom Air Force Base in Montana. The contract covers work for the 10th, 12th, and 490th Missile Squadrons across the Malmstrom AFB Missile Field and will be awarded to a single offeror. The schedule is structured as a unit-price contract organized by year (Year 1 through Year 5) with estimated quantities provided for bidding purposes only, with actual quantities to be determined at task order issuance.
The bid schedule includes 24 line items (Sub-CLINs AA through BC) covering bore rig mobilization, erosion control mobilization, 4-inch and 6-inch conduit installation across various soil conditions (clay, cobble, rock, and shale), directional boring services, three classes of rip rap material (Class I, II, and III), rip rap hauling, fill dirt, top soil, erosion repair, straw wattle, and bonding. Quantities vary by line item; for example, 4-inch conduit under 500 feet is estimated at 550 linear feet annually, directional bore work ranges from 10 to 225 linear feet depending on soil type and conduit size, and rip rap quantities range from 60 to 160 cubic yards annually. Contractors must provide unit prices for each line item across all five years, with total extended amounts calculated based on estimated quantities. The Government notes that estimated quantities are historical usage estimates for bidding purposes only and actual quantities may differ.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A4a_Bid Schedule Extended.pdf | ||
| A2_SOW_TO1.pdf | ||
| A8_Subcontractor Consent.docx | DOCX document | |
| A6_Section L and M.pdf | ||
| A3_Submittal Schedule.pdf | ||
| A2b_Location Map_TO1.pdf | ||
| A2a_Erosion Photo_TO1.pdf | ||
| A2c_Location Map Close_TO1.pdf | ||
| A1_SOW_Combined Specs.pdf | ||
| Solicitation - FA462626R0019.pdf | ||
| A9_CEAL_Blank.xlsx | XLSX spreadsheet | |
| A7_Past Performance Reference Sheet.docx | DOCX document | |
| A5_Combined Wage Determinations_18May26.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Schedule
| BID SCHEDULE | ||||
| YEAR 1 | ||||
| CLIN | SUB CLIN | DESCRIPTION | EST. | |
| QTY* | UNIT OF MEASURE | UNIT PRICE | EST. |
EXTENDED AMOUNT
| 1 | AA | Bore Rig Mobilization | 5 | Each | $ - 0 | |
| 1 | AB | Erosion Control Mobilization | 5 | Each | $ - 0 | |
| 1 | AC | 4” Conduit | 550 | Linear Foot | $ - 0 | |
| 1 | AD | 4” Conduit over 500 Feet | 65 | Linear Foot | $ - 0 | |
| 1 | AE | 6” Conduit | 40 | Linear Foot | $ - 0 | |
| 1 | AF | Directional Bore Clay 4” Conduit | 70 | Linear Foot | $ - 0 | |
| 1 | AG | Directional Bore Clay 6”Conduit | 40 | Linear Foot | $ - 0 | |
| 1 | AH | Directional Bore Clay 4”Conduit over 500 feet | 10 | Linear Foot | $ - 0 | |
| 1 | AJ | Directional Bore Cobble 4” Conduit | 225 | Linear Foot | $ - 0 | |
| 1 | AK | Directional Bore Cobble 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 1 | AL | Directional Bore Cobble 4” Conduit Over 500 Feet | 125 | Linear Foot | $ - 0 | |
| 1 | AM | Directional Bore Rock 4” Conduit | 80 | Linear Foot | $ - 0 | |
| 1 | AN | Directional Bore Rock 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 1 | AP | Directional Bore Rock 4” Conduit over 500 Feet | 102 | Linear Foot | $ - 0 | |
| 1 | AQ | Directional Bore Shale 4” Conduit | 55 | Linear Foot | $ - 0 | |
| 1 | AR | Directional Bore Shale 4” Conduit Over 500 Feet | 10 | Linear Foot | $ - 0 | |
| 1 | AS | Directional Bore Shale 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 1 | AT | Class III Rip Rap | 160 | Cubic Yard | $ - 0 | |
| 1 | AU | Class II Rip Rap | 130 | Cubic Yard | $ - 0 | |
| 1 | AV | Class I Rip Rap | 60 | Cubic Yard | $ - 0 | |
| 1 | AW | Rip Rap Hauling | 720 | Ton/Mile | $ - 0 | |
| 1 | AX | Fill Dirt | 75 | Cubic Yard | $ - 0 | |
| 1 | AY | Top Soil | 50 | Cubic Yard | $ - 0 | |
| 1 | AZ | Erosion Repair under 50 CY | 1 | Each | $ - 0 | |
| 1 | BA | Erosion Repair Over 50 Cubic Yards | 10 | Cubic Yard | $ - 0 | |
| 1 | BB | Straw Wattle | 1 | Each | $ - 0 | |
| 1 | BC | Bonding | 1 | Each | $ - 0 | |
| TOTAL EST. EXTENDED AMOUNT - YEAR 1 | $ - 0 | |||||
| YEAR 2 | ||||||
| ITEM | SUB CLIN | DESCRIPTION | EST. | |||
| QTY* | UNIT OF MEASURE | UNIT PRICE | EST. |
EXTENDED AMOUNT
| 1001 | AA | Bore Rig Mobilization | 5 | Each | $ - 0 | |
| 1001 | AB | Erosion Control Mobilization | 5 | Each | $ - 0 | |
| 1001 | AC | 4” Conduit | 550 | Linear Foot | $ - 0 | |
| 1001 | AD | 4” Conduit over 500 Feet | 65 | Linear Foot | $ - 0 | |
| 1001 | AE | 6” Conduit | 40 | Linear Foot | $ - 0 | |
| 1001 | AF | Directional Bore Clay 4” Conduit | 70 | Linear Foot | $ - 0 | |
| 1001 | AG | Directional Bore Clay 6”Conduit | 40 | Linear Foot | $ - 0 | |
| 1001 | AH | Directional Bore Clay 4”Conduit over 500 feet | 10 | Linear Foot | $ - 0 | |
| 1001 | AJ | Directional Bore Cobble 4” Conduit | 225 | Linear Foot | $ - 0 | |
| 1001 | AK | Directional Bore Cobble 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 1001 | AL | Directional Bore Cobble 4” Conduit Over 500 Feet | 125 | Linear Foot | $ - 0 | |
| 1001 | AM | Directional Bore Rock 4” Conduit | 80 | Linear Foot | $ - 0 | |
| 1001 | AN | Directional Bore Rock 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 1001 | AP | Directional Bore Rock 4” Conduit over 500 Feet | 102 | Linear Foot | $ - 0 | |
| 1001 | AQ | Directional Bore Shale 4” Conduit | 55 | Linear Foot | $ - 0 | |
| 1001 | AR | Directional Bore Shale 4” Conduit Over 500 Feet | 10 | Linear Foot | $ - 0 | |
| 1001 | AS | Directional Bore Shale 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 1001 | AT | Class III Rip Rap | 160 | Cubic Yard | $ - 0 | |
| 1001 | AU | Class II Rip Rap | 130 | Cubic Yard | $ - 0 | |
| 1001 | AV | Class I Rip Rap | 60 | Cubic Yard | $ - 0 | |
| 1001 | AW | Rip Rap Hauling | 720 | Ton/Mile | $ - 0 | |
| 1001 | AX | Fill Dirt | 75 | Cubic Yard | $ - 0 | |
| 1001 | AY | Top Soil | 50 | Cubic Yard | $ - 0 | |
| 1001 | AZ | Erosion Repair under 50 CY | 1 | Each | $ - 0 | |
| 1001 | BA | Erosion Repair Over 50 Cubic Yards | 10 | Cubic Yard | $ - 0 | |
| 1001 | BB | Straw Wattle | 1 | Each | $ - 0 | |
| 1001 | BC | Bonding | 1 | Each | $ - 0 | |
| TOTAL EST. EXTENDED AMOUNT - YEAR 2 | $ - 0 | |||||
| YEAR 3 | ||||||
| ITEM | SUB CLIN | DESCRIPTION | EST. | |||
| QTY* | UNIT OF MEASURE | UNIT PRICE | EST. |
EXTENDED AMOUNT
| 2001 | AA | Bore Rig Mobilization | 5 | Each | $ - 0 | |
| 2001 | AB | Erosion Control Mobilization | 5 | Each | $ - 0 | |
| 2001 | AC | 4” Conduit | 550 | Linear Foot | $ - 0 | |
| 2001 | AD | 4” Conduit over 500 Feet | 65 | Linear Foot | $ - 0 | |
| 2001 | AE | 6” Conduit | 40 | Linear Foot | $ - 0 | |
| 2001 | AF | Directional Bore Clay 4” Conduit | 70 | Linear Foot | $ - 0 | |
| 2001 | AG | Directional Bore Clay 6”Conduit | 40 | Linear Foot | $ - 0 | |
| 2001 | AH | Directional Bore Clay 4”Conduit over 500 feet | 10 | Linear Foot | $ - 0 | |
| 2001 | AJ | Directional Bore Cobble 4” Conduit | 225 | Linear Foot | $ - 0 | |
| 2001 | AK | Directional Bore Cobble 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 2001 | AL | Directional Bore Cobble 4” Conduit Over 500 Feet | 125 | Linear Foot | $ - 0 | |
| 2001 | AM | Directional Bore Rock 4” Conduit | 80 | Linear Foot | $ - 0 | |
| 2001 | AN | Directional Bore Rock 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 2001 | AP | Directional Bore Rock 4” Conduit over 500 Feet | 102 | Linear Foot | $ - 0 | |
| 2001 | AQ | Directional Bore Shale 4” Conduit | 55 | Linear Foot | $ - 0 | |
| 2001 | AR | Directional Bore Shale 4” Conduit Over 500 Feet | 10 | Linear Foot | $ - 0 | |
| 2001 | AS | Directional Bore Shale 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 2001 | AT | Class III Rip Rap | 160 | Cubic Yard | $ - 0 | |
| 2001 | AU | Class II Rip Rap | 130 | Cubic Yard | $ - 0 | |
| 2001 | AV | Class I Rip Rap | 60 | Cubic Yard | $ - 0 | |
| 2001 | AW | Rip Rap Hauling | 720 | Ton/Mile | $ - 0 | |
| 2001 | AX | Fill Dirt | 75 | Cubic Yard | $ - 0 | |
| 2001 | AY | Top Soil | 50 | Cubic Yard | $ - 0 | |
| 2001 | AZ | Erosion Repair under 50 CY | 1 | Each | $ - 0 | |
| 2001 | BA | Erosion Repair Over 50 Cubic Yards | 10 | Cubic Yard | $ - 0 | |
| 2001 | BB | Straw Wattle | 1 | Each | $ - 0 | |
| 2001 | BC | Bonding | 1 | Each | $ - 0 | |
| TOTAL EST. EXTENDED AMOUNT - YEAR 3 | $ - 0 | |||||
| YEAR 4 | ||||||
| ITEM | SUB CLIN | DESCRIPTION | EST. | |||
| QTY* | UNIT OF MEASURE | UNIT PRICE | EST. |
EXTENDED AMOUNT
| 3001 | AA | Bore Rig Mobilization | 5 | Each | $ - 0 | |
| 3001 | AB | Erosion Control Mobilization | 5 | Each | $ - 0 | |
| 3001 | AC | 4” Conduit | 550 | Linear Foot | $ - 0 | |
| 3001 | AD | 4” Conduit over 500 Feet | 65 | Linear Foot | $ - 0 | |
| 3001 | AE | 6” Conduit | 40 | Linear Foot | $ - 0 | |
| 3001 | AF | Directional Bore Clay 4” Conduit | 70 | Linear Foot | $ - 0 | |
| 3001 | AG | Directional Bore Clay 6”Conduit | 40 | Linear Foot | $ - 0 | |
| 3001 | AH | Directional Bore Clay 4”Conduit over 500 feet | 10 | Linear Foot | $ - 0 | |
| 3001 | AJ | Directional Bore Cobble 4” Conduit | 225 | Linear Foot | $ - 0 | |
| 3001 | AK | Directional Bore Cobble 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 3001 | AL | Directional Bore Cobble 4” Conduit Over 500 Feet | 125 | Linear Foot | $ - 0 | |
| 3001 | AM | Directional Bore Rock 4” Conduit | 80 | Linear Foot | $ - 0 | |
| 3001 | AN | Directional Bore Rock 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 3001 | AP | Directional Bore Rock 4” Conduit over 500 Feet | 102 | Linear Foot | $ - 0 | |
| 3001 | AQ | Directional Bore Shale 4” Conduit | 55 | Linear Foot | $ - 0 | |
| 3001 | AR | Directional Bore Shale 4” Conduit Over 500 Feet | 10 | Linear Foot | $ - 0 | |
| 3001 | AS | Directional Bore Shale 6” Conduit | 10 | Linear Foot | $ - 0 | |
| 3001 | AT | Class III Rip Rap | 160 | Cubic Yard | $ - 0 | |
| 3001 | AU | Class II Rip Rap | 130 | Cubic Yard | $ - 0 | |
| 3001 | AV | Class I Rip Rap | 60 | Cubic Yard | $ - 0 | |
| 3001 | AW | Rip Rap Hauling | 720 | Ton/Mile | $ - 0 | |
| 3001 | AX | Fill Dirt | 75 | Cubic Yard | $ - 0 | |
| 3001 | AY | Top Soil | 50 | Cubic Yard | $ - 0 | |
| 3001 | AZ | Erosion Repair under 50 CY | 1 | Each | $ - 0 | |
| 3001 | BA | Erosion Repair Over 50 Cubic Yards | 10 | Cubic Yard | $ - 0 | |
| 3001 | BB | Straw Wattle | 1 | Each | $ - 0 | |
| 3001 | BC | Bonding | 1 | Each | $ - 0 | |
| TOTAL EST. EXTENDED AMOUNT - YEAR 4 | $ - 0 | |||||
| YEAR 5 | ||||||
| ITEM | SUB CLIN | DESCRIPTION | EST. | |||
| QTY* | UNIT OF MEASURE | UNIT PRICE | EST. |
EXTENDED AMOUNT
| 4001 | AA | Bore Rig Mobilization | 5 | Each | $ - 0 |
| 4001 | AB | Erosion Control Mobilization | 5 | Each | $ - 0 |
| 4001 | AC | 4” Conduit | 550 | Linear Foot | $ - 0 |
| 4001 | AD | 4” Conduit over 500 Feet | 65 | Linear Foot | $ - 0 |
| 4001 | AE | 6” Conduit | 40 | Linear Foot | $ - 0 |
| 4001 | AF | Directional Bore Clay 4” Conduit | 70 | Linear Foot | $ - 0 |
| 4001 | AG | Directional Bore Clay 6”Conduit | 40 | Linear Foot | $ - 0 |
| 4001 | AH | Directional Bore Clay 4”Conduit over 500 feet | 10 | Linear Foot | $ - 0 |
| 4001 | AJ | Directional Bore Cobble 4” Conduit | 225 | Linear Foot | $ - 0 |
| 4001 | AK | Directional Bore Cobble 6” Conduit | 10 | Linear Foot | $ - 0 |
| 4001 | AL | Directional Bore Cobble 4” Conduit Over 500 Feet | 125 | Linear Foot | $ - 0 |
| 4001 | AM | Directional Bore Rock 4” Conduit | 80 | Linear Foot | $ - 0 |
| 4001 | AN | Directional Bore Rock 6” Conduit | 10 | Linear Foot | $ - 0 |
| 4001 | AP | Directional Bore Rock 4” Conduit over 500 Feet | 102 | Linear Foot | $ - 0 |
| 4001 | AQ | Directional Bore Shale 4” Conduit | 55 | Linear Foot | $ - 0 |
| 4001 | AR | Directional Bore Shale 4” Conduit Over 500 Feet | 10 | Linear Foot | $ - 0 |
| 4001 | AS | Directional Bore Shale 6” Conduit | 10 | Linear Foot | $ - 0 |
| 4001 | AT | Class III Rip Rap | 160 | Cubic Yard | $ - 0 |
| 4001 | AU | Class II Rip Rap | 130 | Cubic Yard | $ - 0 |
| 4001 | AV | Class I Rip Rap | 60 | Cubic Yard | $ - 0 |
| 4001 | AW | Rip Rap Hauling | 720 | Ton/Mile | $ - 0 |
| 4001 | AX | Fill Dirt | 75 | Cubic Yard | $ - 0 |
| 4001 | AY | Top Soil | 50 | Cubic Yard | $ - 0 |
| 4001 | AZ | Erosion Repair under 50 CY | 1 | Each | $ - 0 |
| 4001 | BA | Erosion Repair Over 50 Cubic Yards | 10 | Cubic Yard | $ - 0 |
| 4001 | BB | Straw Wattle | 1 | Each | $ - 0 |
| 4001 | BC | Bonding | 1 | Each | $ - 0 |
| TOTAL EST. EXTENDED AMOUNT - YEAR 5 | $ - 0 | ||||
| TOTAL EST. EXTENDED AMOUNT (5 YEAR ORDERING PERIOD) | $ - 0 | ||||
| * NOTE: ESTIMATED QUANTITIES ARE HISTORICAL USAGE ESTIMATES AND ARE FOR BIDDING PURPOSES ONLY. THE ACTUAL QUANTITIES ORDERED ON THIS CONTRACT MAY DIFFER. THE UNIT PRICES PROVIDED BY CONTRACTORS WILL BE USED TO ESTABLISH PRICES FOR EACH TASK ORDER BASED ON ACTUAL QUANTITIES. |
Page &P of &N
File details come from the government source that posted it. Updated .