This document is a Schedule of Items for the Lake Winfield Scott Campground Reconstruction - Phase 1 project by the USDA Forest Service's Chattahoochee-Oconee National Forest. The comprehensive bid schedule includes a base bid and three optional bid items covering various construction elements. The base bid encompasses administration, site preparation, North Loop Bathhouse construction, water line installation, and sanitary sewer work, with detailed line items for specific infrastructure components like PVC piping, gate valves, pavement, grading, and utility installations.

The optional bid items include a South Loop Bathhouse (Option 1), an Entrance/Dump Station (Option 2), and a Guard Shack (Option 3), each with granular breakdowns of construction activities such as site work, demolition, concrete, masonry, plumbing, electrical, and HVAC. While the unit prices are not filled in, the document provides estimated quantities for each line item, ranging from linear feet of piping to lump sum allocations for general conditions and specialized construction tasks. The final section includes a summary table for calculating the total project cost, incorporating the base bid and all optional items.

View the file

Other files

File Type Posted
Amendment 4- 12445226Q0003.pdf PDF
A1- rev3 RFQ T and C.docx DOCX document
Amendment 3- 12445226Q0003.pdf PDF
Amend3 LWS Campground Recon.xlsx XLSX spreadsheet
A3 - Rev SOI LWS Mar2026.pdf PDF
A5 - rev LWS Architectural Set.pdf PDF
A1 - rev2 RFQ T and C.docx DOCX document
A1 - rev2 RFQ T and C.docx DOCX document
Amendment 0002 - 12445226Q0003.pdf PDF
Questions 12445226Q0006.docx DOCX document
A2 - Rev SOW LWS Feb2026.docx DOCX document
A3 - Rev SOI LWS Feb2026.pdf PDF
Amendment 0001 - 12445226Q0003.pdf PDF
A1 - rev RFQ Terms and Conditions 12445226Q0003.docx DOCX document
A1 -RFQ Terms and Conditions 12445226Q0003.docx DOCX document
A2 - Rev SOW LWS Final.docx DOCX document
A5 - LWS Architectural Set.pdf PDF
A7 - LWS CIVIL_100_R1_signed-final.zip ZIP file
A8 - Info SR 180 at Slaughter Crk.docx DOCX document
A9 - WD GA20250107 Bldg Union County.pdf PDF
A4 - Updated Combined SPECS.pdf PDF
A6 - Past Performance Questionnaire.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA FOREST SERVICE

CHATTAHOOCHEE - OCONEE NATIONAL FOREST

LAKE WINFIELD SCOTT CAMPGROUND RECONSTRUCTION - PHASE 1

INDEPENDENT GOVERNMENT ESTIMATE

Lake Winfield Scott Campground Reconstruction Project Phase 1

Optional Bid Item 2 (Entrance/ Dump Station)

Pay Item Description Estimated Units Unit Price Subtotal

Quantity 1 Entrance/Dump Station 1 LS

Soil Erosion Control and Site Stabilization 1 LS $

Survey Staking 1 LS $

6" S DR26PVC 160 LF $

Sanitary Sewer Clean-Out 2 EA $

2"SCH80PVC 55 LF $

1"SCH80PVC 55 LF $

Gate Valve 2 EA $

Asphalt Pavement 2,100 SY $

Grading 1 LS $

Bollards 12 EA $

Dump Station 1 LS $

Demolition 1 LS $

Option 2 Total

Lake Winfield Scott Campground Reconstruction Project Phase 1

Optional Bid Item 3 (Guard Shack)

Pay Item I Description Estimated Quantity

Units Unit Price Subtotal

1 Guard Shack 1 LS General 1 LS $

Concrete 1 LS $

Masonry 1 LS $

Woods and Pasties 1 LS $

Thermo Protection 1 LS $

Openings 1 LS $

Finishes 1 LS $

Specialties 1 LS $

Furnishings 1 LS $

Plumbing 1 LS $

HVAC 1 LS $

Electrical 1 LS $

Option 3 Total

Total Am mount Including All Options and Contingency

Base $

Option 1 $

Option 2 $

Option 3 $

Total $

Pay Item Total

Pay Item Total