A04-SOW_RP_Facility_Improvements-Final_CDs_Specs.pdf

PDF 3 MB Posted

Attached to
Cape Cod National Seashores Racepoint Area Facilit
Solicitation number
140P4325R0017
Issued by

About this file

This is a Statement of Work (SOW) for the Cape Cod National Seashore Racepoint Area Facility Improvements project located in Provincetown, Massachusetts. The project involves comprehensive site and facility upgrades, including demolition and construction of new infrastructure at the Racepoint Beach area.

The base bid and optional work include: demolishing existing lifeguard and women's changing room facilities; constructing two new modular double vault toilets; installing new walkways, ramps, and accessible parking; creating new changing room facilities; installing outdoor showers; and performing site grading and cleanup. The project requires obtaining Massachusetts Department of Environmental Protection permits, submitting a Notice of Proposed Construction to the FAA, and completing all work in compliance with local and federal regulations. The work will be performed under a single prime contract, with careful consideration for environmental protection, accessibility requirements, and minimal disruption to the national seashore's operations. Specific requirements include seasonal work restrictions, archaeological monitoring, and adherence to erosion control and storm water management guidelines.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CAPE COD NATIONAL SEASHORE

MASSACHUSETTS

RACEPOINT AREA FACILITY IMPROVEMENTS

PMIS NO. 337276

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

CAPE COD NATIONAL

SEASHORE

FINAL CONSTRUCTION DOCUMENT SUBMISSION

JANUARY 12, 2025

CACO - 337276 00 01 10 - 1

TABLE OF CONTENTS

SECTION 00 01 10 - TABLE OF CONTENTS

DIVISION 01 -- GENERAL REQUIREMENTS

01 11 00 - Summary of Work

01 26 01 - Contract Modification Procedures

01 27 00 - Definition of Contract Line Items

01 31 00 - Project Management & Coordination

01 32 16 - Construction Schedule

01 32 33 - Photo Documentation

01 33 23 - Submittal Procedures

01 35 23 - Safety Requirements

01 40 00 - Quality Requirements

01 42 00 - Reference Standards

01 50 00 - Temporary Facilities and Controls

01 57 19.12 - Noise & Acoustics Management

01 57 23 - Temporary Storm Water Pollution Prevention

01 67 00 - Product Requirements

01 73 40 - Execution

01 74 19 - Construction Waste Management and Disposal

01 77 00 - Closeout Procedures

01 78 23 - Operation and Maintenance Data

01 79 00 - Demonstration and Training

01 81 13.13 - Sustainable Design Requirements

DIVISION 02 -- EXISTING CONDITIONS

02 41 13 - Selective Site Demolition

DIVISION 03 -- CONCRETE

CACO - 337276 00 01 10 - 2

03 30 00 - Cast-in-Place Concrete

DIVISION 04 – MASONRY – NOT USED

DIVISION 05 -- METALS

05 50 00 - Metal Fabrications

DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES

06 10 00 - Rough Carpentry

06 20 00 - Finish Carpentry

DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

07 25 00 - Weather Barriers

07 31 29 - Wood Shingles and Shakes

07 62 00 - Sheet Metal Flashing and Trim

07 92 00 - Joint Sealants

DIVISION 08 -- OPENINGS

08 16 13 - Fiberglass Doors and Frames

08 71 00 - Door Hardware

DIVISION 09 -- FINISHES

09 91 13 - Exterior Painting

09 91 23 - Interior Painting

DIVISION 10 – SPECIALTIES- NOT USED

DIVISION 11 -- EQUIPMENT – NOT USED

DIVISION 12 – FURNISHINGS – NOT USED

DIVISION 13 -- SPECIAL CONSTRUCTION – NOT USED

DIVISION 14 -- CONVEYING EQUIPMENT – NOT USED

DIVISION 21 -- FIRE SUPPRESSION – NOT USED

CACO - 337276 00 01 10 - 3

DIVISION 22 – PLUMBING-NOT USED

DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23 05 00 – Basic Mechanical Materials and Methods

23 07 00 – Mechanical Insulation

23 81 26 – Split System Air Conditioners

DIVISION 26 – ELECTRICAL

26 05 00 – Common Work Results for Electrical

26 05 19 – Low-Voltage Electrical Power Conductors and Cables

26 05 26 – Grounding and Bonding for Electrical Systems

26 05 29 – Hangers and Supports for Electrical Systems

26 05 33 – Raceways and Boxes for Electrical Systems

26 05 44 – Sleeves and Sleeve Seals for Electrical

Raceways and Cabling

26 05 53 – Identification for Electrical System

26 08 00 – Commissioning of Electrical Systems

26 27 26 – Wiring Devices

26 51 00 – Interior Lighting

DIVISION 27 – COMMUNICATIONS – NOT USED

DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY – NOT USED

DIVISION 31 -- EARTHWORK

31 10 00 – Site Clearing

31 20 00 - Earth Moving

31 25 00 - Erosion and Sedimentation Control 31 50 00 – Excavation Support and Protection

CACO - 337276 00 01 10 - 4

DIVISION 32 -- EXTERIOR IMPROVEMENTS

32 12 16 - Bituminous Paving and Surfacing

32 13 13 – Concrete Paving

32 17 13 - Parking Bumpers

32 17 23 - Pavement Markings

DIVISION 33 -- UTILITIES

33 11 00 – Water Utilities

33 39 00 – Precast Modular Double Vault Toilets (Restrooms)

DIVISION 46 -- WATER AND WASTEWATER EQUIPMENT – NOTUSED

END OF SECTION

CACO - 337276

01 11 00 - 6

SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

10. Soils Investigation Report.

11. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Racepoint Beach within the Cape Cod National Seashore at Provincetown, Massachusetts off of Racepoint Road. Note that the project site is approximately 1/2 mile from Provincetown Municipal Airport.

B. The Work consists of the following:

1. Base Bid: The work includes all supervision, equipment, labor material and plant for the following: a. provide Massachusetts Department of Environmental Protection permits, permit closeout, provide Ma DEP required inspections using a licensed State of Massachusetts engineer, coordinate and schedule Massachusetts Department of Environmental Protection (Ma DEP) required inspections; b. submit a Notice of Proposed Construction or Alteration (FAA Form 7460-1) to the Federal Aviation Administration (FAA). Complete and submit the form through the FAA's Obstruction Evaluation/Airport Airspace Analysis (OE/AAA) system. c. Demolish and remove the existing lifeguard and women’s changing room facility, slab, footing, walkways, electric and appurtenances; d.

Provide site preparation, required to provide two (2) new modular double vault toilets, new walkways, ramps and slabs; e. The vault toilet site work shall include site clearing, new sidewalk, new detectable warning fields, new parking stops, new accessible parking posts, installation of accessible parking signs and new ramp with handrails to create an accessible route from the parking lot to the new vault toilets and women’s changing room; f. Purchase, deliver and install a new shipping container (Conex Box) for the storage of lifeguard equipment during construction period; g. provide selective demolition of the existing men’s changing facility; h. Divide the existing Men’s changing facility to create a men’s changing room and a new women’s changing room facility; i. provide new connections to existing water lines for two (2) new free standing modular outdoor showers; j. provide concrete aprons, walkways, doors, privacy screen; and k. provide final grading and cleanup of the site.

01 11 00 - 7

2. Option 1: Provide all supervision, equipment, labor material and plant to selectively demolish and renovation the existing men’s restroom and women’s restroom. Provide new work to convert the existing bathrooms to a new lifeguard work room and lifeguard equipment storage room.

3. Option 2: Provide all supervision, equipment, labor material and plant to selectively demolition and provide site preparation at Racepoint Location 2 for two (2) new modular double vault toilets, new walkway, new detectable warning field, new parking stops, parking lot paint removal, new lot restriping of four parking spots and two new accessible parking signs.

C. Project will be constructed under a single prime contract.

1.3 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to the limit of disturbance (LOD) and the facilities designated for renovation.

2. Limit site disturbance, including earthwork and clearing of vegetation, to 10 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter.

B. Storage of Materials: Confine storage of materials to the “Off season OFFO” staging area and “Construction Season” staging areas defined on drawings.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing plants and root zones.

3. Do not remove, injure, or destroy plants and grass without prior approval. Consult with

Contracting Officer and remove agreed-on roots and vegetation that interfere with construction.

4. Carefully supervise excavating, grading, filling, and other construction operations near existing vegetation to prevent damage.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for

01 11 00 - 8 vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

G. Archeological Monitoring: The entire project site has been heavily disturbed during previous construction activity, and the work of this project likely will not impact previously undisturbed areas.

However, it is possible that deeply buried archeological features or deposits may be located in the vicinity of the project, though unlikely the demolition would affect these should they exist. A NPS Archeologist will monitor ground disturbing work and has the authority to stop the work if any potential archeological resources are unearthed. Every precaution shall be taken to avoid and/or minimize impacts to areas adjacent to the bathhouse that do not fall within the demolition limits.

1. Excavation for pavement and concrete slab removal shall not exceed the depth of the existing asphalt pavement and granular base material.

2. The contractor shall limit all subsurface excavation to within the limits of the exact areas where items to be removed are located to the greatest extent possible. Whenever possible, when using equipment for excavation and removal, especially at the parking lot, the contractor shall use a bucket with a flat blade, not one with teeth. If heavy equipment is to be operated outside of the previously disturbed area, construction matting shall be employed to prevent impacts to the ground surface.

1.4 PUBLIC USE OF SITE

A. A portion of the parking lot and site will be closed to the public during construction. The remainder not used for construction staging will be open to the public during construction. Beach access and access to the Old Harbor Life Saving Station will remain open during construction.

1.5 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas directly under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations.

Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, paths and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).

B. Renovated Facilities

1. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of facilities, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.

a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.

b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.

c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.

01 11 00 - 9

On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.

d. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.

1.6 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 72 hours advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.7 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:30 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: To be requested in writing to the CO and approved at least Seventy-Two

(72) hours in advance of the work.

2. Early Morning Hours: None.

3. Hours for noisy activity: 7: a.m. to 5:30 p.m.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities.

P r i o r t o t h e s t a r t o f c o n s t r u c t i o n a c t i v i t i e s , t h e c o n t r a c t o r s h a l l p r o v i d e a f u l l g r o u n d p e n e t r a t i n g r a d a r s u r v e y o f t h e a r e a s t o b e d i s t u r b e d . G P R s h a l l c o m p l y w i t h A S T M D 6 4 3 2 — S t a n d a r d G u i d e f o r U s i n g G r o u n d P e n e t r a t i n g R a d a r ( G P R ) f o r S u b s u r f a c e I n v e s t i g a t i o n s . U t i l i t i e s t h a t c o n f l i c t w i t h n e w w o r k s h a l l b r o u g h t t o t h e a t t e n t i o n o f t h e c o n t r a c t i n g o f f i c e r .

If damage occurs to utilities, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than one week in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. The contractor shall provide temporary power to maintain facility heat, fire alarm and basic building

01 11 00 - 10 functions during power outages. The contractor shall provide all required equipment, fuel and connections to maintain heat, fire alarm and basic building functions.

4. Hours for Utility Shutdowns: Shutdowns to be as brief as possible and limited to eight

(8) hours.

D. Non-smoking/Non-vaping Facility: Smoking and vaping are not permitted on government property.

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered and paid for by the contractor can be used for purposes of managing communication and documents during the construction stage.

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

B. Notify “Dig Safe” or other utility marking entity and have all existing utility locations marked for review by the Contracting Officer Representative in field and at least one week prior to beginning construction and any excavation. If damage occurs, repair utility at no additional expense to the Government.

C. Seasonal Restrictions

1. No ground-disturbing construction will occur between April 15 and October 15 to minimize activity during the box turtle active season. Eastern Box Turtle Protection Plan will be required unless all ground-disturbing work associated with the project occurs during the Eastern Box Turtle’s inactive season (October 15 through April 15). See following section for special construction conditions.

2. Visual sweeps of the construction limits by certified Contractor employee (s) will occur daily dur-ing construction through November, and any turtles found will be relocated from the construction limits. See Special Construction Conditions (01 11 00.1 in the Division 01 General Requirements specifications).

1.9 SOILS INVESTIGATION REPORT

A. A soils investigation report has not been conducted. The contractor shall rely on its own investigation.

B. Soil Bearing Capacity: The soil's load-bearing capacity is based on the International Building Code (IBC) 2024, Table 1804.2. The site is presumed to have sandy soil (classified as SP) with a presumptive bearing capacity of 1,000 to 2,000 pounds per square foot (psf). This classification is an assumption and is provided for bidding purposes only. The Government will not be responsible for engineering interpretations or conclusions drawn from this data.

C. The contractor shall retain an engineer, licensed in the state of Massachusetts, to classify the soil within the project’s limit of work and confirm the soil bearing capacity prior to the submission of shop drawings for foundations. The contractor shall submit a soil classification and confirmation letter, signed and sealed by the contractor’s engineer of record.

D. If conflicts arise between the contractor’s soil report, the contractor’s engineer’s findings, and the contract drawings or specifications, the contractor shall provide written notice to the contracting officer. The contractor shall also submit a detailed plan to resolve the conflict. Unless otherwise directed, the drawings and specifications shall govern.

01 11 00 - 11

PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

01 26 01 - 1

CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

01 26 01 - 2

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

01 26 01 - 3

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the

Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.

Contractor may utilize the government provided Contractor Estimate

01 26 01 - 4

Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)

01 26 01 - 5

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.

Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized, then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead ....................... 10% Profit ....................... 8%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, then the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3, E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

01 27 00 - 7

DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No.1 – Base Bid – Demolish Lifeguard and Women’s Changing Room Facilty and Provide two (2) Double Vault Modular toilets.

1. This line item includes all supervision, equipment, labor material and plant for the following: a.

provide Massachusetts Department of Environmental Protection permits, close permits, provide required MaDEP inspections using a licensed State of Massachusetts engineer, coordinate and schedule Massachusetts Department of Environmental Protection (Ma DEP) required inspections; b.

submit a Notice of Proposed Construction or Alteration (FAA Form 7460-1) to the Federal Aviation Administration (FAA). Complete and submit the form through the FAA's Obstruction Evaluation/Airport Airspace Analysis (OE/AAA) system c. Demolish and remove the existing lifeguard and women’s changing room facility, slab, footing, walkways, electric and appurtenances;

d. Provide site preparation, required to provide two (2) new modular double vault toilets, new walkways, ramps and slabs; e. The vault toilet site work includes site clearing, new sidewalk, new detectable warning field, new parking stops, new accessible parking posts and new ramp and handrails to create an accessible route from the parking lot to the new vault toilets and changing rooms; f. Purchase, deliver and install a new shipping container (Conex Box) for the storage of lifeguard equipment during construction period; g. provide selective demolition of the existing men’s changing facility; h. Divide the existing Men’s changing facility to create a men’s changing room and a new women’s changing room facility; i. provide new connections to existing water lines for two (2) new free standing modular outdoor showers; j. provide concrete aprons, walkways, doors, privacy screen; and k. provide final grading and cleanup of the site.

2. Measurement for payment will be percentage complete of line item per scheduled value.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item No. 2 – Bid Option 1 – Convert Existing Bathrooms to Lifeguard storage and workroom.

1. This line item includes all supervision, equipment, labor material and plant to selectively demolish and renovation the existing men’s restroom and women’s restroom. Provide new work to convert

01 27 00 - 8

DEFINITION OF CONTRACT LINE ITEMS

the existing bathrooms to a new lifeguard work room and lifeguard equipment storage room.

3. Payment will be made at the contract lump sum price.

C. Contract Line Item No. 3 – Bid Option 2 – Provide two (2) double vault modular toilets.

1. This line items provides all supervision, equipment, labor material and plant to selectively demolition and provide site preparation at Racepoint Location 2 for two (2) new modular double vault toilets, new walkway, new detectable warning field, new parking stops, parking lot paint removal, new lot restriping of four parking spots and two new accessible parking signs.

3. Payment will be made at the contract lump sum price.

RAVEPOINT AREA FACILITY IMPROVEMENTS

CACO - 373276

01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Submittals

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. Contractor Project Website.

7. Project meetings.

8. Environmental Coordination.

9. Permits

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

1.2 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

01 31 00 - 2

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Permit requirements.

7. Pre-installation conferences.

8. Project closeout activities.

9. Commissioning activities.

1.3 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

8. Waste Management Plan.

9. Quality Control Plan.

10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).

11. Indoor Air Quality (IAQ) Management Plan.

12. Contractors Commissioning Plan.

13. Historic Preservation Treatment Plan.

14. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit.

b. The Agency(ies) with Jurisdiction issuing the permit.

c. Information required from the Government to complete the permit application.

01 31 00 - 3

15. Eastern Box Turtle Protection Plan.

16. Environmental Procedures.

17. Resume of Project Scheduler.

B. All items listed must be provided to the Contracting Officer before the Pre-Construction

Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1.4 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:

1. Enter the general information at the top of the form.

2. Under the “Action” section at the bottom of the form, select “Question” then select

“CMR” in the drop-down of the “Send to” box.

3. Enter the details of the question and attach related documents.

4. Select “Submit Form” at the bottom of the page.

D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.

CO will determine the critical nature of each RFI and issue a response accordingly.

01 31 00 - 4

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.5 PROJECT WEB SITE

A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period.

The NPS/DSC SharePoint Project website will be used for the following functions:

1. Project directory.

2. Project correspondence.

3. Meeting agendas and minutes.

4. Contract modifications forms and logs.

5. RFI form and processing.

6. Task and issue management.

7. Photo documentation.

8. Baseline schedule, schedule updates and calendar management.

9. Submittal form and processing.

10. Payment coordination documentation.

11. Drawing and specification document hosting, viewing, and updating.

12. Online document collaboration.

13. Reminder and tracking functions.

14. Archiving functions.

15. Notification of submittal and RFI statuses and current responsible party.

16. Permits and addendums

B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.

C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.

http://www.nps.gov/dscw/precon_spproj.htm

01 31 00 - 5

D. All users will be required to have the following software packages:

1. Internet Explorer version 7 or later.

2. Adobe Acrobat Professional (Pro) version 9 or later

1.6 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 01 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Payments to Contractor.

9. Payroll reports.

10. Contract time.

11. Liquidated damages.

12. Contractor Performance Evaluation.

13. Display of Hotline posters.

14. Notice to proceed.

15. Correspondence procedures.

16. NPS/DSC SharePoint Project website.

17. Acceptance/rejection of work.

18. Progress meetings.

19. Submittal procedures.

20. NPS Final Accessibility Inspection.

21. Environmental requirements and management procedures.

22. Permit requirements.

23. As-constructed drawings/operation and maintenance (O&M) manuals.

24. Saturday, Sunday, holiday and night work.

25. Reference materials.

26. Value engineering.

27. Designation of Approved Project Scheduler.

28. Construction Schedule Quality Review.

29. Staging location/logistics.

30. Schedule of Values.

B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

01 31 00 - 6

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections,

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

k. Permit requirements.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Sustainable design requirements.

i. Review of mockups.

j. Possible conflicts.

k. Compatibility requirements.

l. Time schedules.

m. Weather limitations.

n. Manufacturer's written instructions.

o. Warranty requirements.

p. Compatibility of materials.

q. Acceptability of substrates.

r. Temporary facilities and controls.

s. Space and access limitations.

t. Regulations of agency(ies) with jurisdiction.

u. Testing and inspecting requirements.

v. Installation procedures.

w. Coordination with other work.

x. Required performance results.

01 31 00 - 7

y. Protection of adjacent work.

z. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

1.7 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate a full-time, on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Waste Management Plan (WMP).

c. Implementation of the Indoor Air Quality (IAQ) Management Plan.

d. Implementation of the Storm Water Pollution Prevention Plan (SWPPP).

e. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.

f. Training for Contractor personnel in accordance with their position requirements.

g. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Indoor Air Quality (IAQ) Management.

4. Noise & Acoustics Management.

5. Temporary Storm Water Pollution Prevention Environmental Management.

6. Construction Waste Management.

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:

1. Overview of environmental issues related to the building industry.

2. Overview of environmental issues related to the Project.

3. Review of site specific procedures and management plans:

a. Construction Waste Management.

01 31 00 - 8

b. Indoor Air Quality (IAQ) Management.

c. Noise & Acoustics Management.

d. Temporary Storm Water Pollution Prevention.

4. Pollution Prevention (P2) practices: Submit evidence of familiarity with P2 practices.

5. Green Building Rating Programs: Submit evidence of familiarity with USGBC-LEED.

6. Compliance with environmental regulations: As specified in Regulatory Requirements.

Submit Contractor 40 CFR employee training records upon request of Contracting Officer.

D. Provide…

This is the start of the file's text. The full file is on GovTribe.