This document is a Summary of Work specification for a federal construction project at Racepoint Beach within Cape Cod National Seashore in Provincetown, Massachusetts. The project involves demolishing and renovating existing facilities, including removing a lifeguard and women's changing room facility, installing two new modular double vault toilets, creating new walkways and accessible routes, and performing site improvements. The base bid and two optional scopes of work include site preparation, installing new parking infrastructure, relocating facilities, and completing required environmental and FAA permitting.

Key project details include specific requirements for site disturbance, archeological monitoring, and seasonal construction restrictions (no ground-disturbing work between April 15 and October 15 to protect Eastern Box Turtles). The project requires obtaining Massachusetts Department of Environmental Protection permits, submitting FAA Form 7460-1 for airport airspace analysis, and ensuring accessibility compliance. The work will be conducted under a single prime contract with limited site access, and the contractor must coordinate closely with the National Park Service, follow park regulations, and minimize disruption to existing park operations and public access.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 11 00 - SUMMARY OF WORK -Revised June 18, 2025

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

10. Soils Investigation Report.

11. Additional Reports.

12. Accessible Route Layout and Elevation Coordination

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Racepoint Beach within the Cape Cod National Seashore at Provincetown, Massachusetts off of Racepoint Road. Note that the project site is approximately 1/2 mile from Provincetown Municipal Airport.

B. The Work consists of the following:

1. Base Bid: The work includes all supervision, equipment, labor material and plant for the following: a. provide Massachusetts Department of Environmental Protection permits, permit closeout, provide Ma DEP required inspections using a licensed State of Massachusetts engineer, coordinate and schedule Massachusetts Department of Environmental Protection (Ma DEP) required inspections Comply with all conditions of the Massachusetts Department of Environmental Protection (MassDEP) Plan Approval, Permit No. 25-WP64A-APP, which has been obtained by the Government and is provided as Attachment A. The contractor is responsible for all costs and coordination required to comply with this permit, including scheduling, inspections, and documentation as required by MassDEP. b. submit a Notice of Proposed Construction or Alteration (FAA Form 7460-1) to the Federal Aviation Administration (FAA). Complete and submit the form through the FAA's Obstruction Evaluation/Airport Airspace Analysis (OE/AAA) system. c. Demolish and remove the existing lifeguard and women’s changing room facility, slab, footing, walkways, electric and appurtenances; d. Provide site preparation, required to provide two (2) new modular double vault toilets, new walkways, ramps and slabs; e. The vault toilet site work shall include site clearing, new sidewalk, new detectable warning fields, new parking stops, new accessible parking posts, installation of accessible parking signs and new ramp with handrails to create an accessible route from the parking lot to the new vault toilets and women’s changing room; f. Purchase, deliver and install a new shipping container (Conex Box) for the storage of lifeguard equipment during construction period; g. provide selective demolition of the existing men’s changing facility; h. Divide the existing Men’s changing facility to create a men’s changing room and a new women’s changing room facility; i. provide new connections to existing water lines for two (2) new free standing modular outdoor showers; j. provide concrete aprons, walkways, doors, privacy screen; and k. provide final grading and cleanup of the site.

2. Option 1: Provide all supervision, equipment, labor material and plant to selectively demolish and renovation the existing men’s restroom and women’s restroom. Provide new work to convert the existing bathrooms to a new lifeguard work room and lifeguard equipment storage room.

3. Option 2: Provide all supervision, equipment, labor material and plant to selectively demolition and provide site preparation at Racepoint Location 2 for two (2) new modular double vault toilets, new walkway, new detectable warning field, new parking stops, parking lot paint removal, new lot restriping of four parking spots and two new accessible parking signs. Comply with all conditions of the Massachusetts Department of Environmental Protection (MassDEP) Plan Approval, Permit No. 25-WP64A-APP, which has been obtained by the Government and is provided as Attachment A. The contractor is responsible for all costs and coordination required to comply with this permit, including scheduling, inspections, and documentation as required by MassDEP.

C. Project will be constructed under a single prime contract.

1.3 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to the limit of disturbance (LOD) and the facilities designated for renovation.

2. Limit site disturbance, including earthwork and clearing of vegetation, to 10 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter.

B. Storage of Materials: Confine storage of materials to the “Off season OFFO” staging area and “Construction Season” staging areas defined on drawings.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing plants and root zones.

3. Do not remove, injure, or destroy plants and grass without prior approval. Consult with Contracting Officer and remove agreed-on roots and vegetation that interfere with construction.

4. Carefully supervise excavating, grading, filling, and other construction operations near existing vegetation to prevent damage.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

G. Archeological Monitoring: The entire project site has been heavily disturbed during previous construction activity, and the work of this project likely will not impact previously undisturbed areas. However, it is possible that deeply buried archeological features or deposits may be located in the vicinity of the project, though unlikely the demolition would affect these should they exist. A NPS Archeologist will monitor ground disturbing work and has the authority to stop the work if any potential archeological resources are unearthed. Every precaution shall be taken to avoid and/or minimize impacts to areas adjacent to the bathhouse that do not fall within the demolition limits.

1. Excavation for pavement and concrete slab removal shall not exceed the depth of the existing asphalt pavement and granular base material.

2. The contractor shall limit all subsurface excavation to within the limits of the exact areas where items to be removed are located to the greatest extent possible. Whenever possible, when using equipment for excavation and removal, especially at the parking lot, the contractor shall use a bucket with a flat blade, not one with teeth. If heavy equipment is to be operated outside of the previously disturbed area, construction matting shall be employed to prevent impacts to the ground surface.

1.4 PUBLIC USE OF SITE

A. A portion of the parking lot and site will be closed to the public during construction. The remainder not used for construction staging will be open to the public during construction. Beach access and access to the Old Harbor Life Saving Station will remain open during construction.

1.5 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas directly under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, paths and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).

B. Renovated Facilities

1. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of facilities, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.

a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.

b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.

c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.

d. On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.

e. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.

1.6 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 72 hours advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.7 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:30 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: To be requested in writing to the CO and approved at least Seventy-Two

(72) hours in advance of the work.

2. Early Morning Hours: None.

3. Hours for noisy activity: 7: a.m. to 5:30 p.m.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities.

3. P r i o r t o t h e s ta r t o f c o n s t r u c t i o n a c t i v i t ie s , t h e co n t r a c t o r s ha l l pr o vi d e a f ul l gr ou nd p e n e t r a t i ng r a d a r s ur ve y of t h e a r e a s t o be d i s t ur be d. G P R s h a ll c o m p l y w i th AS T M D6 4 3 2 — S t a nd a r d G ui de f o r U s i n g G r o un d P e ne t r a t i ng R a da r ( G P R ) f or S ubs ur f a c e I nve s t i g a t i ons . U t i li t i e s t h a t c o n f l i c t w i t h n e w w o r k s ha l l br ou gh t t o t h e a t t e nt i on of t h e c o nt r a c t i n g of f i c e r . If damage occurs to utilities, repair utility at no additional expense to the Government.

4. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than one week in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. The contractor shall provide temporary power to maintain facility heat, fire alarm and basic building functions during power outages. The contractor shall provide all required equipment, fuel and connections to maintain heat, fire alarm and basic building functions.

4. Hours for Utility Shutdowns: Shutdowns to be as brief as possible and limited to eight

(8) hours.

D. Non-smoking/Non-vaping Facility: Smoking and vaping are not permitted on government property.

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered and paid for by the contractor can be used for purposes of managing communication and documents during the construction stage.

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

B. Notify “Dig Safe” or other utility marking entity and have all existing utility locations marked for review by the Contracting Officer Representative in field and at least one week prior to beginning construction and any excavation. If damage occurs, repair utility at no additional expense to the Government.

C. Seasonal Restrictions

1. No ground-disturbing construction will occur between April 15 and October 15 to minimize activity during the box turtle active season. Eastern Box Turtle Protection Plan will be required unless all ground-disturbing work associated with the project occurs during the Eastern Box Turtle’s inactive season (October 15 through April 15). See following section for special construction conditions.

2. Visual sweeps of the construction limits by certified Contractor employee (s) will occur daily during construction through November, and any turtles found will be relocated from the construction limits. See Special Construction Conditions (01 11 00.1 in the Division 01 General Requirements specifications).

1.9 SOILS INVESTIGATION REPORT

A. A soils investigation report has not been conducted. The contractor shall rely on its own investigation.

B. Soil Bearing Capacity: The soil's load-bearing capacity is based on the International Building Code (IBC) 2024, Table 1804.2. The site is presumed to have sandy soil (classified as SP) with a presumptive bearing capacity of 1,000 to 2,000 pounds per square foot (psf). This classification is an assumption and is provided for bidding purposes only. The Government will not be responsible for engineering interpretations or conclusions drawn from this data.

C. The contractor shall retain an engineer, licensed in the state of Massachusetts, to classify the soil within the project’s limit of work and confirm the soil bearing capacity prior to the submission of shop drawings for foundations. The contractor shall submit a soil classification and confirmation letter, signed and sealed by the contractor’s engineer of record.

D. If conflicts arise between the contractor’s soil report, the contractor’s engineer’s findings, and the contract drawings or specifications, the contractor shall provide written notice to the contracting officer. The contractor shall also submit a detailed plan to resolve the conflict. Unless otherwise directed, the drawings and specifications shall govern.

1.10 ADDITIONAL REPORTS

A. A copy of the Massachusetts Department of Environmental Protection (MassDEP) Plan Approval, Permit No. 25-WP64A-APP, is included as Attachment A to these specifications.

B. All conditions of the permit are incorporated into the contract. Compliance with the permit and any associated costs shall be the responsibility of the contractor.

C. The contractor shall review the permit in full prior to initiating any work related to the vault toilet installation. Any questions regarding permit requirements shall be brought to the attention of the Contracting Officer.

1.11 ACCESSIBLE ROUTE LAYOUT AND ELEVATION COORDINATION

A. The finish elevation at the vault toilet pads is established at 41.00 feet, based on existing site survey data. Adjacent parking lot and sidewalk elevations vary (approximately 39.00 feet). The contractor shall verify all existing surface elevations and establish the layout of a code-compliant accessible route between the vault toilets and the accessible parking area. This route shall comply with all applicable ABAAS, ADA, and UFAS requirements for maximum running slope (5.0%), cross slope (2.0%), minimum width, and surface conditions.

B. Shop drawings and layout plans shall incorporate current field survey data and clearly depict all slope transitions and surface connections.

C. The contractor shall notify the Contracting Officer in writing of any field conditions that would prevent construction of a compliant accessible route during the shop drawing submittal process and prior to any layout or construction activities. A soils investigation report has not been conducted. The contractor shall rely on its own investigation.

PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 01 11 00

RACEPOINT AREA FACILITY IMPROVEMENTS CACO - 337276

01 11 00 - 10

SUMMARY OF WORK

File details come from the government source that posted it. Updated .