This document is a Section 01 27 00 defining contract line items for the Cape Cod National Seashores Racepoint Area Facility Improvements project (Solicitation Number: 140P4325R0017). The contract includes three primary line items: Base Bid and two optional bid items involving facility renovations and modular toilet installations at the Racepoint Location.
The Base Bid (Line Item No. 1) requires demolishing the existing lifeguard and women's changing room facility, installing two double vault modular toilets, obtaining Massachusetts Department of Environmental Protection permits, submitting FAA construction notifications, and completing site preparation including new walkways, ramps, and accessibility features. Optional Line Item No. 2 involves converting existing bathrooms to lifeguard storage and workroom, while Line Item No. 3 focuses on installing modular toilets at a second location with associated site improvements. All line items require compliance with MassDEP Plan Approval Permit No. 25-WP64A-APP, and payment will be made at the contract lump sum price based on percentage of completion. The project is managed by the Department of the Interior National Park Service Northeast Region.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No.1 – Base Bid – Demolish Lifeguard and Women’s Changing Room Facilty and Provide two (2) Double Vault Modular toilets.
1. This line item includes all supervision, equipment, labor material and plant for the following: a. provide Massachusetts Department of Environmental Protection permits, close permits, provide required MaDEP inspections using a licensed State of Massachusetts engineer, coordinate and schedule Massachusetts Department of Environmental Protection (Ma DEP) required inspections Comply with all conditions of the Massachusetts Department of Environmental Protection (MassDEP) Plan Approval, Permit No. 25-WP64A-APP, which has been obtained by the Government and is provided as Attachment A. The contractor is responsible for all costs and coordination required to comply with this permit, including scheduling, inspections, and documentation as required by MassDEP; b. submit a Notice of Proposed Construction or Alteration (FAA Form 7460-1) to the Federal Aviation Administration (FAA). Complete and submit the form through the FAA's Obstruction Evaluation/Airport Airspace Analysis (OE/AAA) system c. Demolish and remove the existing lifeguard and women’s changing room facility, slab, footing, walkways, electric and appurtenances;
d. Provide site preparation, required to provide two (2) new modular double vault toilets, new walkways, ramps and slabs; e. The vault toilet site work includes site clearing, new sidewalk, new detectable warning field, new parking stops, new accessible parking posts and new ramp and handrails to create an accessible route from the parking lot to the new vault toilets and changing rooms; f. Purchase, deliver and install a new shipping container (Conex Box) for the storage of lifeguard equipment during construction period; g. provide selective demolition of the existing men’s changing facility; h. Divide the existing Men’s changing facility to create a men’s changing room and a new women’s changing room facility; i. provide new connections to existing water lines for two (2) new free standing modular outdoor showers; j. provide concrete aprons, walkways, doors, privacy screen; and k. provide final grading and cleanup of the site.
2. Measurement for payment will be percentage complete of line item per scheduled value.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No. 2 – Bid Option 1 – Convert Existing Bathrooms to Lifeguard storage and workroom.
1. This line item includes all supervision, equipment, labor material and plant to selectively demolish and renovation the existing men’s restroom and women’s restroom. Provide new work to convert the existing bathrooms to a new lifeguard work room and lifeguard equipment storage room.
2. Measurement for payment will be percentage complete of line item per scheduled value.
3. Payment will be made at the contract lump sum price.
C. Contract Line Item No. 3 – Bid Option 2 – Provide two (2) double vault modular toilets.
1. This line items provides all supervision, equipment, labor material and plant to selectively demolition and provide site preparation at Racepoint Location 2 for two (2) new modular double vault toilets, new walkway, new detectable warning field, new parking stops, parking lot paint removal, new lot restriping of four parking spots and two new accessible parking signs. Comply with all conditions of the Massachusetts Department of Environmental Protection (MassDEP) Plan Approval, Permit No. 25-WP64A-APP, which has been obtained by the Government and is provided as Attachment A. The contractor is responsible for all costs and coordination required to comply with this permit, including scheduling, inspections, and documentation as required by MassDEP.
2. Measurement for payment will be percentage complete of line item per scheduled value.
3. Payment will be made at the contract lump sum price.
END OF SECTION 012700
01 27 00 - 7
DEFINITION OF CONTRACT LINE ITEMS
RACEPOINT AREA FACILITY IMPROVEMENTS CACO - 337276