A00801-610800.pdf
PDF 873 KB Posted
- Attached to
- 610800 BARNSTABLE FAP No. CRP-003S(984)X Park and Ride Expansion and Improvements at Route 132
- Solicitation number
- BD-27-1030-0H100-0H002-131511
- Issued by
- Barnstable County, Massachusetts
About this file
This document contains Special Provisions for a Massachusetts Department of Transportation Highway Division construction project involving the Park and Ride Expansion and Improvements at Route 132 in Barnstable (Federal Aid Project No. CRP-003S(984)X, Proposal No. 610800-135580). The scope of work includes reconstruction and expansion of the existing park and ride facility to accommodate increased users, including expansion of parking lots, drainage basin construction, new lighting and electrical conduit, relocation of EV charging stations, ADA-compliant sidewalks and curb ramps, replacement of bus shelters, and updated signage and pavement markings. The Contractor must achieve three contractual milestones: Full Beneficial Use within 1,098 calendar days from Notice to Proceed, Substantial Completion within 1,119 calendar days, and Contractor Field Completion within 1,149 calendar days. Labor participation goals require 15.3% minority and 6.9% women participation for each job category. The project must comply with 2026 Standard Specifications for Highways and Bridges and various other standards including MUTCD and manual on uniform traffic control devices. Prospective bidders must submit questions to the Construction Contracts Engineer by 3:00 P.M. on the Tuesday of the previous week before the scheduled bid opening date.
The project is subject to Build America, Buy America Act requirements mandating that all iron, steel, manufactured products, and construction materials be produced in the United States, with limited exceptions for foreign materials not exceeding 0.1% of total contract cost or $2,500, whichever is greater. Holiday work restrictions apply to major arterial and local roadways for specified federal and state holidays, with some restrictions requiring District Highway Director and local police chief approval. The Contractor must coordinate with concurrent work at the adjacent Barnstable Service Plaza and will receive no additional compensation or time extensions for delays caused by such concurrent work. The project includes environmental health and safety provisions requiring a site-specific Environmental Health and Safety Plan approved by a Certified Industrial Hygienist, Licensed Site Professional services for potential contaminated media, and management of invasive plant species under Items 102.3 and 102.33. The Contractor is responsible for proper characterization, transport, and disposal of any contaminated soils encountered, with costs paid under Items 181.11-181.14 depending on soil classification. All equipment, telecommunications services, and video surveillance equipment must comply with 2 CFR 200.216 prohibitions on certain foreign manufacturers including Huawei, ZTE, Hytera, Hikvision, and Dahua.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Massachusetts Department Of Transportation Highway Division Proposal No. 610800-135580
A00801 - 1
DOCUMENT A00801
SPECIAL PROVISIONS
BARNSTABLE
Federal Aid Project No. CRP-003S(984)X
PARK AND RIDE EXPANSION AND IMPROVEMENTS AT ROUTE 132
Labor participation goals for this Project shall be 15.3% for minorities and 6.9% for women for each job category. The goals are applicable to both Contractor’s and Subcontractor’s on-site construction workforce. Refer to Document 00820 for details.
SCOPE OF WORK
The proposed work includes expanding the existing Park and Ride in Barnstable at Route 132 to accommodate a growing number of users. Work involves the reconstruction of the existing park and ride’s footprint as well as expansions to both lots, drainage design for the new layout including the construction of a drainage basin, new lighting and conduit throughout the project, the relocation of multiple EV charging stations, ADA compliant sidewalks and pedestrian curb ramps, replacement of the existing bus shelters, and updated signs and pavement markings.
All work under this Contract shall be done in conformance with the 2026 Standard Specifications for Highways and Bridges, the Supplemental Specifications contained in this book, the Construction Standard Details in effect as of May 2026, the 1990 Standard Drawings for Signs and Supports, the 2015 Overhead Signal Structure and Foundation Standard Drawings, the 11th Edition of the Manual on Uniform Traffic Control Devices (MUTCD) and the January 2026 Massachusetts Amendments to the MUTCD, the 1968 Standard Drawings for Traffic Signals and Highway Lighting, the latest edition of The American Standard for Nursery Stock, the Plans and these Special Provisions.
CONTRACTOR QUESTIONS AND ADDENDUM ACKNOWLEDGEMENTS
Prospective bidders are required to submit all questions to the Construction Contracts Engineer by 3:00 P.M. on the Tuesday of the previous week before the scheduled bid opening date. Any questions received after this time will not be considered for review by the Department.
Contractors should email questions and addendum acknowledgements to the following email address massdotspecifications@dot.state.ma.us The MassDOT proposal number and municipality is to be placed in the subject line.
mailto:MassDOTSpecifications@dot.state.ma.us
A00801 - 2
HOLIDAY WORK RESTRICTIONS
(Supplementing Subsection 7.09)
The District Highway Director (DHD) may authorize work to continue during these specified time periods if it is determined by the District that the work will not negatively impact the traveling public. DHD may allow work in those areas on a case by case basis and where work is behind barrier and will not impact traffic
Below are the holiday work restrictions:
New Years Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day. No work on local roadways on the holiday without permission by the DHD and the local police chief.
Martin Luther King's Birthday (Federal Holiday) No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.
President's Day (Federal Holiday) No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.
Evacuation Day (Suffolk County State Holiday) No work restrictions due to traffic concerns.
Patriot's Day (State Holiday) Work restrictions will be in place for Districts 3 and 6 along the entire Boston Marathon route and any other locations that the DHD in those districts determine are warranted so as to not to impact the marathon. All other districts work restrictions will be as per DHD.
Mother’s Day No work on Western Turnpike and Metropolitan Highway System from 5:00 AM on the Friday before, until the normal start of business on the following day.
Memorial Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the Friday before, until the normal start of business on the following day.
Bunker Hill Day (Suffolk County State Holiday) No work restrictions due to traffic concerns.
Juneteenth No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.
A00801 - 3
HOLIDAY WORK RESTRICTIONS (Continued)
Independence Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day. No work on local roadways on the holiday without permission by the DHD and the local police chief.
Labor Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the Friday before, until the normal start of business on the following day.
Columbus Day (Federal Holiday) No work on major arterials from 5:00 AM on the Friday before, until the normal start of business on the following day
Veterans' Day (Federal Holiday) No work restrictions due to traffic concerns.
Thanksgiving Day (Federal Holiday) No work on major arterials from 5:00 AM two days before until the normal start of business on the following Monday.
Christmas Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day.
CONCURRENT WORK BY OTHERS WITHIN AND/OR ADJACENT TO PROJECT
LIMITS
(Supplementing Subsection 5.06)
Concurrent work may take place within and/or adjacent to Project 610800 Barnstable – Park & Ride Expansion and Improvements at Route 132 by the Barnstable Service Plaza’s owner MassDOT and/or its Lessee, Utilities, and/or other Contractors hired by these parties. The existing Barnstable Service Plaza is located immediately adjacent to the Park & Ride facility and will have its lease readvertised during the expected construction period for Project 610800. The Project 610800 Contractor will be required to coordinate his work with any work being performed by the Barnstable Service Plaza’s owner MassDOT and/or its Lessee, Utilities, and/or other Contractors hired by these parties. This coordination includes but is not limited to concurrent use of the existing Access Drive between facilities and access to the Service Plaza’s septic/leaching system which is located underneath the upper portion of the existing/proposed Park & Ride facility. No additional compensation and/or extension of time shall be granted to the Project 610800 Contractor due to any delays that may result from concurrent work being performed at the Barnstable Service Plaza facility, which may be encountered during the prosecution of their work.
A00801 - 4
COMPLIANCE WITH THE NATIONAL DEFENSE AUTHORIZATION ACT
(Supplementing Subsection 7.01)
On all projects, the “Prohibition on Certain Telecommunications and Video Surveillance Services or Equipment” Regulation (2 CFR 200.216) prohibits the Contractor from using or furnishing the following telecommunications equipment or services:
• Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities).
• For the purpose of public safety, security of government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities).
• Telecommunications or video surveillance services provided by such entities or using such equipment.
• Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.
This prohibition applies to all products manufactured by the aforementioned companies, including any individual components or parts.
By submitting a bid on a project, the Contractor certifies that all work will be in compliance with the terms of 2 CFR 200.216. The Contractor shall submit a COC indicating compliance with the above provisions for all telecommunications equipment or services included in the Contract.
Payment for the item in which the materials are incorporated may be withheld until these COCs are received. Any cost involved in furnishing the certificate(s) shall be borne by the Contractor.
SUBSECTION 8.02 SCHEDULE OF OPERATIONS
Replace this subsection with the following:
An integrated cost and schedule controls program shall be implemented by the Contractor to track and document the progress of the Work from Notice to Proceed (NTP) through the Contractor Field Completion (CFC) Milestone. The Contractor’s schedules will be used by the Engineer to monitor project progress, plan the level-of-effort required by the Department’s work force and consultants and as a critical decision-making tool. Accordingly, the Contractor shall ensure that it complies fully with the requirements specified herein and that its schedules are both accurate and updated as required by the specification throughout the life of the project.
Detailed requirements are provided in Division II, Section 722 Construction Scheduling.
A00801 - 5
BIDDERS LIST
Pursuant to the provisions of 49 CFR Part 26.11 all official bidders will be required to report the names, addresses and telephone numbers of all firms that submitted bids or quotes in connection with this project. Failure to comply with a written request for this information within 15 business days may result in a recommendation to the Prequalification Committee that prequalification status be suspended until the information is received.
The Department will survey all firms that have submitted bids or quotes during the previous year prior to setting the annual goal and shall request that each firm report its age and gross receipts for the year.
BUILD AMERICA BUY AMERICA PREFERENCE
On Federally-aid projects the Buy America (23.CFR § 635.410) and Build America, Buy America Act. requires the following,
(1) all iron and steel used in the project are produced in the United States--this means all manufacturing processes, from the initial melting stage through the application of coatings, must occur in the United States. Foreign steel and iron can be used if the cost of the materials does not exceed 0.1% of the total Contract cost or $2,500, whichever is greater. The action of applying a coating to a covered material (i.e., steel and iron) is deemed a manufacturing process subject to Buy America. Coating includes epoxy coating, galvanizing, painting and any other coating that protects or enhances the value of a material subject to requirements of Build America, Buy America. Steel used for temporary support of excavation, including H piles, soldier piles, and sheeting when the steel is required to be left in place is subject to requirements of Build America, Buy America. Temporary steel, shall remain in place when it falls within the influence zone of the soil supporting any structure or railroad tracks.
(2) all manufactured products used in the project are produced in the United States—this means the manufactured product was manufactured in the United States and
(3) all construction materials are manufactured in the United States—this means that all manufacturing processes for the construction material occurred in the United States.
“Construction materials” includes an article, material, or supply—other than an item of primarily iron or steel; a manufactured product; cement and cementitious materials;
aggregates such as stone, sand, or gravel; or aggregate binding agents or additives—that is or consists primarily of:
• non-ferrous metals,
• plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables),
• glass (including optic glass),
• lumber; or
• drywall.
A00801 - 6
BUILD AMERICA BUY AMERICA PREFERENCE (Continued)
The Buy America preference only applies to articles, materials, and supplies that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, brought to the construction site and removed at or before the completion of the infrastructure project. Nor does a Buy America preference apply to equipment and furnishings, such as movable chairs, desks, and portable computer equipment, that are used at or within the finished infrastructure project but are not an integral part of the structure or permanently affixed to the infrastructure project.
All articles, materials, and supplies should be classified as an iron or steel product, a manufactured product, or another product as specified by law or in 2 CFR part 184 (such other products specified by law or in 2 CFR part 184 include “excluded materials” and “construction materials”); an article, material, or supply must not be considered to fall into multiple categories.
NATIONAL GRID EMERGENCY TELEPHONE NUMBERS
GAS:
Emergency: 1-800-233-5325 New Service: 1- 877-696-4743 Customer Support: 1-800-732-3400
EVERSOURCE EMERGENCY TELEPHONE NUMBERS
ELECTRIC:
Outage/ Emergency: 800-592-2000 or 844-726-7562 New Service: 1-888-633-3797 (1-888-need pwr) Customer Support: 1-800-340-9822
EMERALD ASH BORER ADVISORY
To the extent possible, all trees and brush shall be disposed on site, typically chipped and spread in place. When trees or brush must be removed, such as in urban, or otherwise populated areas, Contractor shall identify proposed location for disposal, and provide written notification to the Engineer for approval. Disposal shall be in city or town of project, or at minimum, within county, of construction operations.
EQUIVALENT SINGLE AXLE LOADS (ESALS)
The estimated traffic level to be used for SUPERPAVE HMA mixture designs for this contract, expressed in Equivalent Single Axle Loads (ESALs) for the design travel lane over a 20-year period, is a Traffic Level 2 (0.3 Million to <10 Million 18-kip (80-kn) ESALs).
A00801 - 7
NONCONFORMING COMPRESSIVE STRENGTH OF CEMENT CONCRETE
Concrete with compressive strength test results failing to attain the limits specified in Table 901.64-3 of 901.64.B: Acceptance Testing shall be evaluated for structural adequacy and serviceability at the Contractors’ expense. The Department will review all production records, the concrete test records, petrographic analysis report, field notes, and the placement records for the concrete in question. If the Engineer determines the material is found to be adequate to remain in place, payment shall be adjusted in accordance with the following formula:
Where:
𝑃𝑃 = 𝑝𝑝𝑝𝑝𝑝𝑝 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑓𝑓𝑓𝑓𝑓𝑓 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐
𝑓𝑓′𝑐𝑐 = 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠ℎ 𝑎𝑎𝑎𝑎 28 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑓𝑓𝑓𝑓 = 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠ℎ 𝑎𝑎𝑎𝑎 56 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑄𝑄 = 𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 𝑏𝑏𝑏𝑏 𝑡𝑡ℎ𝑒𝑒 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 𝑈𝑈𝑈𝑈 = 𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑜𝑜𝑜𝑜 𝑡𝑡ℎ𝑒𝑒 𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑠𝑠𝑠𝑠𝑠𝑠 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑝𝑝𝑝𝑝𝑝𝑝 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦 𝑓𝑓𝑓𝑓𝑓𝑓 𝑡𝑡ℎ𝑒𝑒 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑖𝑖𝑖𝑖 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝
TRUCK SAFETY DEVICES
(Supplementing Subsection 7.04: Motor Vehicles)
All motor vehicles subject to Section 7 of Chapter 90 to be operated under this Contract shall be equipped with safety devices as provided therein and in 540 CMR 4.00.
The Contractor shall certify to the Registry of Motor Vehicles, in a manner prescribed by the Registrar, that all applicable vehicles are equipped with Lateral Protective Devices, Convex Mirrors, Cross Over Mirror(s) and Back Up Cameras in accordance with the requirements of 540
CMR 4.00.
The Contractor shall provide evidence satisfactory to the Department to demonstrate compliance with the above certification requirement for all applicable vehicles operated under this Contract by the Contractor and its subcontractors and vendors in a manner set forth by the Department.
Thereafter, the Contractor shall have an affirmative obligation to continue to provide such evidence of compliance on an ongoing basis and no later than 7 days after certification with the Registry of Motor Vehicles of any additional vehicles operated under this Contract by the Contractor and its subcontractors and vendors.
Non-compliance with respect to a vehicle that is subject to 540 CMR 4.00 may subject the Contractor to statutory fines as established in M.G.L. c. 90, § 7 and/or contractual remedies up to and including termination of the Contract.
A00801 - 8
NORTHERN LONG-EARED BAT AND TRICOLORED BAT PROTECTION
The northern long-eared bat (Myotis septentrionalis; NLEB) and tricolored bat (Perimyotis subflavus; TCB) are listed as federally endangered or proposed endangered, respectfully, under the Endangered Species Act (ESA). The U.S. Fish and Wildlife Service (USFWS) developed this guidance to address ESA compliance and promote conservation of NLEB and TCB. MassDOT, on behalf of FHWA, submitted a Northern Long-eared Bat and Tricolored Bat Range-wide Determination Key Consultation through Information for Planning and Consultation (IPaC) and generated a May Affect, Not Likely to Adversely Affect (NLAA) determination (see Document A00871 USFWS NLAA). Subsequently, the project has completed Section 7 consultation under the ESA.
In advance of the uplisting of the TCB to endangered under the ESA, the following Avoidance and Minimization Measures (AMMs) must be strictly adhered to in order to protect NLEB and TCB and to be in compliance with the ESA. Contact MassDOT Environmental Services - Wildlife Unit Supervisor for questions about project limits, restrictions, or conservation measures.
General AMM
• The Contractor shall ensure all personnel working in on the project site are aware of all environmental commitments related to NLEB and TCB, including all applicable AMMs.
NLEB and TCB information (https://www.fws.gov/midwest/endangered/mammals/nleb/ and https://www.fws.gov/species/tricolored-bat-perimyotis-subflavus) shall be made available to all personnel.
Lighting AMMs
• Direct temporary lighting away from suitable habitat during the active season: March 15 to
November 30
• When installing new or replacing existing permanent lights, use downward-facing, full cut-off lens lights (with same intensity or less for replacement lighting); or for those transportation agencies using the BUG system developed by the Illuminating Engineering Society, be as close to 0 for all three ratings with a priority of “uplight” of 0 and “backlight” as low as practicable.
Tree Removal AMMs
• If additional cutting is proposed by the Contractor that is outside the scope of this contract, additional review is required by the MassDOT Highway Division’s Environmental Services Section, and additional review and restrictions may be required by the USFWS.
• Ensure tree removal is limited to that specified in project plans and ensure that contractors understand clearing limits and how they are marked in the field (e.g., install bright colored flagging/fencing prior to any tree clearing to ensure contractors stay within clearing limits).
• No tree cutting, trimming, or removal of trees and/or woody vegetation >3-inch in diameter shall be conducted between March 15 to September 30
• The Contractor shall ensure all personnel working in on the project site are aware of all environmental commitments related to NLEB and/or TCB, including the TOY restriction.
https://www.fws.gov/midwest/endangered/mammals/nleb/
A00801 - 9
SUBSECTION 8.03 PROSECUTION OF WORK
Contractual Milestones:
This Contract contains the following Contractual Milestones that are to be included in the Contractor’s Baseline Contract Progress Schedule submission. The Contractor shall identify the completion of the work pertaining to each Contractual Milestone through the inclusion of a Finish Milestone and hammock activities in the accepted baseline Contract Progress Schedule using the stated description.
MS#01 – Contractor Field Completion: The Contractor shall achieve Contractor Completion within 1149 calendar days from Notice to Proceed.
Contractor Field Completion is defined as: All physical contract Work is complete including punch list. The Contractor has fully de-mobilized from field operations.
MS#02 – Substantial Completion: The Contractor shall achieve Substantial Completion within 1119 calendar days from Notice to Proceed.
Substantial Completion is defined as: A walkthrough of the entire contract Work has been performed by the Resident Engineer, a Punch List has been generated and the Work required by the contract, including paper work, has been completed, except for work having a contract price of less than one percent of the adjusted total contract price, including overruns, underruns and all contract amendments. All material submittals have been received by the District Materials Lab.
MS#03 –Full Beneficial Use: The Contractor shall achieve Full Beneficial Use within 1098 calendar days from Notice to Proceed.
Full Beneficial Use is defined as: The majority of contract Work has been completed and the asset(s) has been opened for full multi-modal transportation use, except for limited contract work items that do not materially impair or hinder the intended public use of the transportation facility. All anticipated lane takings have been completed, except for minor, short term work items.
The Contractor must clearly identify all aspects of this work in the preparation of the Construction Schedule and throughout the contract duration.
The Contractor is reminded that, in bidding this work, the Contractor is obligated to meet the Contract Milestones and Durations (Time) and is obligated to plan the successful completion of Work, prior to submitting the bid.
In submitting a bid price for this contract, the Contractor acknowledges that a detailed plan, has been developed to meet the Contract Time for all aspects of the Contact; including shift work;
extended work hour requirements/restrictions; winter work, multiple crews and parallel work efforts, as well as the planning of all subcontractor and supplier operations.
A00801 - 10
VALUE ENGINEERING CHANGE PROPOSAL
This Subsection defines the conditions and requirements which apply to Value Engineering Change Proposals (“VECPs”). The purpose of this provision is to encourage the Contractor to propose changes in certain project requirements that will maintain the project’s functional requirements at a savings in contract time, contract price, or both. The net savings obtained by using a VECP that meets the conditions and requirements set forth here will be shared by the Contractor and MassDOT.
VECP’s under this provison are to be initiated, developed and submitted to MassDOT by the Contractor. The VECP must show the contemplated changes to the Drawings, Specifications and other requirements in the Contract. When a VECP submitted pursuant to this section is fully accepted by MassDOT, the VECP will be implemented by the Contractor and paid using the current cost and resource loaded schedule. Contractor shall demonstrate that the VECP is equal to, or better than, the original design or material; that there is an interest in public safety within the VECP; that there is a life-cycle cost benefit; and/or that end users will benefit from the shortened schedule. VECPs shall be consistent with the MassHighway/MassDOT Standard Specifications for Highways and Bridges and other applicable reference documents and directives. Any proposed deviation from these documents will need to be clearly identified in the VECP Proposal Documents, and must be approved by MassDOT’s Chief Engineer before accepting this VECP.
A. In order to be considered for MassDOT review each VECP shall:
1. Be clearly labeled pursuant to this Subsection;
2. Yield a net savings at least two hundred and fifty thousand (250,000.00) Dollars and/or a net saving of contract completion duration of at least three (3) months;
3. The proposed changes to contract items must:
a. maintain the specified items’ required functions (service life, reliability);
b. meet applicable safety regulations and codes;
c. material substitutions must be in accordance with DOT prequalified/preapproved products and must be tested in accordance with standard material specs/testing methods ( and considering all relevant environmental, load, and other relevant factors);
d. show economy of operation, ease of maintenance, ease of construction, and necessary standardized features and appearance; and
4. Shall not require an extension of Contract Time or Contract Milestones, with the exception of cases when there are anticipated significant cost saving.
A00801 - 11
VALUE ENGINEERING CHANGE PROPOSAL (Continued)
The thresholds above are considered to be a general guideline. MassDOT will consider VECPs outside of these thresholds if a significant benefit is demonstrated. Additionally, notwithstanding this VECP process, MassDOT will consider minor revisions in the form of a Contract Modification.
Further, any VECP submitted shall be in sufficient detail to clearly define the proposed change.
The Contractor's failure to provide information of the type, detail and in a format to facilitate the MassDOT's review, may be grounds for rejection of the VECP. Additionally, the Contractor will not be entitled to any equitable adjustment or increased Time, due to any aspect of any of the proposed VECP including permitting, right of way, utility coordination or delayed responses by MassDOT. If, after the progression of the work associated with the executed Contract Modification for the VECP, any additional costs are realized by the Contractor or any of the sub-consultants, sub-contractors, or suppliers, the Contractor shall be obligated to pay for any and all costs.
B. The following initial items shall be provided by the Contractor for MassDOT’s review.
Items 1-6 need to be submitted prior to the start of MassDOT’s review of the VECP and item 7 is an important consideration for the pricing of the VECP and the timeline of the proposed VECP schedule.
1. VECP Description: A description of the difference between the existing and the proposed Contract requirements, and the comparative advantages and disadvantages of each;
2. VECP Change Listing: A listing of the Contract requirements that will need to be changed, modified, or reviewed as well as the proposed Contract document changes in the Instructions to Bidders, Contract, Standard Specifications, General Requirements and Special Provisions required by the VECP.
3. Construction Schedule Update: Any changes in the Contract Time(s) or Contract
Milestone(s), that will result from acceptance of the VECP, shall be accompanied by a contemporaneous schedule analysis (i.e, the Contractor’s baseline schedule submission, all past/required monthly schedule updates, a detailed assessment of all past delays, and a resource loaded Crticial Path Method schedule as specified in Section 8.0 / Subsection 8.02 of this Contract) of the projected Work that remains including the proposed VECP related schedule changes (inclusive of the timeline to review accept the VECP and the timeline for implementing the design changes) in the remaining work. This shall be submitted in the form of a Proposal Schedule until the VECP has been formally accepted. Note: All of this information is to be updated, recertified, and formally accepted by MassDOT before final acceptance of this this VECP is issued.
A00801 - 12
4. Date for MassDOT’s Acceptance: A statement that clearly justifies the date by which the VECP must be accepted to obtain the maximum price reduction, noting any effect upon the Contract Time(s) and/or Contract Milestone(s). This statement must include a narrative that demonstrates the most recent construction schedule has been utilized to justify that proposed acceptance date (e.g. “in order to start to fabricate critical materials, authorization must be provided to work on the shop drawings by no later than [date]”). The Contractor should allow for at least sixty (60) to ninety (90) days for acceptance by MassDOT once all of the VECP documentation has been provided. Acceptance shall mean that MassDOT has received a finalized and executed contract modification. However, this is a proposed Contract change.
The Contractor is fully obligated to progress the Work of the original Contract and MassDOT is not liable for any delays or costs that may occur in the review phase of any VECP proposal.
5. Cost and Savings Estimates: A detailed estimate of the anticipated net savings, calculated as follows:
a. Original Scope: Isolate the cost of performing the original contract construction activities, in accordance with the original Contract Documents, as originally bid by the Contractor, that are anticipated to be superseded by the VECP. This cost is to include any original contract scope that is anticipated to be altered or eliminated by the VECP such as, shop drawing preparation, inspection work, testing, maintenance of traffic, or any other original contract costs, that have yet to have been performed at the time of this VECP submission.
b. New VECP Scope: Calculate the cost of performing the comparable construction activities associated with the VECP.
c. Contractor’s Engineer & Inspection: Calculate the cost of engineering, inspection, and design work by the Contractor’s Engineer/Designer. This should be a realistic estimate of the costs of any required engineering, design and review work by the Contractor’s Engineer.
d. MassDOT’s Costs: MassDOT's estimate of costs to perform engineering/design reviews, cost estimate reviews, schedule reviews, and any other administrative costs to review and recommend implementation of the proposed VECP. (including all anticipated increased costs to MassDOT on other Contracts and all anticipated follow-on increased costs to MassDOT, if any) as provided by MassDOT. MassDOT’s estimated costs must be included the VECP calculation and will be provided by MassDOT in support of the VECP evaluation process.
e. Other Costs: Estimated costs associated with any revisions to other project related costs, such as Environmental Permits or Right of Way acquisitions, including other agency or municipality costs, as provided by MassDOT.
A00801 - 13
Net Savings:
The net savings to be split between MassDOT and the Contractor shall be calculated using the items above as follows: a - (b+c+d+e) = net savings
6. The Contractor shall also provide:
a. A proposed Change Order, which explains and justifies any required Equitable Adjustment in the Contract Price.
b. The Contractor's actual costs expended for developing the VECP as of the date of the VECP submission;
7. Design Changes and Drawings: The costs that are outlined above should be inclusive of the following design and engineering responsibilities.
a. Design changes shall be prepared and stamped by the Contractor’s professional designer and/or engineer. In addition, in the development of the VECP; the Contractor is responsible for anticipating and managing all aspects associated with any VECP design work that must be performed by a licensed Engineer.
b. The Contractor’s engineer must analyze and stamp all components of any aspect of the project that has been redesigned, changed, or altered as a result of this
VECP.
c. The Contractor’s engineer shall provide all calculations and supporting design/engineering documentation that was utilized to develop the changes and stamped drawings. These will be used by MassDOT’s Designer-of-Record to review the VECP changes. The Contractor is limited to selecting only those engineer’s that have been pre-qualified by MassDOT’s A&E Board.
d. MassDOT’s Designer-of-Record will review and respond to all completed design submissions related to this VECP within thirty (30) calendar days, unless determined to be a non-critical path item.
e. MassDOT will be responsible for estimating and managing MassDOT’s Designer-of-Record during the VECP review and implementation. Should any significant conflicts arise, between the Contractor’s Engineer and MassDOT’s Designer-of- Record, the DOT and the Contractor will work expeditiously to resolve the conflict. Should this type of conflict continue for greater than five (5) days, the Contractor is to bear all financial and time related impacts of such delay and must seek to resolve the design conflict, in an acceptable manner to MassDOT. The resolution of this conflict will be funded at the Contractor’s expense – exclusive of the net saving that was agreed to at the execution of the contract modification for this VECP.
f. The Contractor’s Engineer may also be required to inspect the construction work.
The Contractor is to include such anticipated inspection costs in the initial VECP.
A00801 - 14
g. MassDOT’s Designer of Record will remain the Designer-of-Record for the entire Project. Any costs incurred in the use of MassDOT’s Designer-of-Record by MassDOT or Contractor associated with the review of a VECP are to be included in the calculated net savings.
C. Approval of the VECP shall not occur until a Contract Modification, incorporating the
VECP, is issued by MassDOT and properly executed by the Contractor. MassDOT may accept or reject part or all of any VECP at any time prior to an executed Contract Modification for the applicable VECP. The decision of MassDOT, concerning acceptance or rejection of any VECP, shall be final and shall not be subject to dispute resolution.
It is expected that several weeks may go by before the final VECP documentation has been executed with a Contract Modification. Therefore, MassDOT intends to make certain that the initial cost estimate information has not changed before entering into a Contract Modification. As the VECP evaluation process is finalized, and prior to the signed Contract Modification for the VECP, the Contractor and MassDOT must re-certify the current status of the originally proposed cost and/or schedule savings.
Until a contract modification is issued and schedule and cost/savings re-certification is complete and accepted by MassDOT, the Contractor shall remain obligated to perform the Work in accordance with the terms and conditions of the original Contract Documents.
Upon completion of the work associated with the VECP, MassDOT may require verification that the VECP savings has been achieved.
D. VECPs will be processed (distributed, reviewed, commented upon, accepted or rejected) expeditiously (pursuant to M.G.L. c. 30, § 39R); however, as this is an elective modification to the contract, MassDOT shall not be liable for any delay or cost in the review and acceptance of the VECP. During the review of the VECP, the Contractor remains obligated to progress the original Contract scope, and schedule, as planned; until a Contract Modification, accepting the Contractor re-certified VECP, has been executed by MassDOT.
The Contractor has the right to withdraw part, or all of any VECP, prior to acceptance by MassDOT. Such withdrawal shall be made in writing to the Engineer. The Contractor shall state the period of time, from the date of the initial VECP submittal, that the VECP shall remain valid and feasible. Revision of this validity and feasibility period shall be allowed only by mutual agreement of the Contractor and the Engineer in writing.
If the Contractor desires to withdraw the proposal prior to the expiration of this period for non-technical reason, MassDOT reserves the right to recover all actual costs that have been incurred to MassDOT.
A00801 - 15
If the Contractor withdraws the VEC Proposal, MassDOT reserves the right to proceed with the VECP or any portion of the VECP as a normal change and the Contractor waives any right it may have had to share in net savings thereunder.
For purposes of this provision, expiration of the time established by the Contractor for approval shall be considered as withdrawal by the Contractor if MassDOT requests an extension of that time and the Contractor does not provide a written extension.
E. With regard to unknown conditions or sub-surface work, in general, the expectation is that the Contractor and MassDOT will strive to gain enough knowledge about the risks in order to provide a forward-priced Change Proposal. Therefore, any costs to fully evaluate the proposal, such as additional borings and/or test pits, must be considered in the cost evaluation of whether the VECP is worth pursuing. However, if it is impractical to gather conclusive exploratory information, before the VECP is executed, MassDOT may consider provisions in the VECP that clearly identifies the risk sharing (cost and time) related specifically to the unknown/sub-surface conditions. If these VECP provisions are acceptable to MassDOT they are to include supplemental language to provide a determination of the final savings/cost, and time impacts, no later than 45 days after the sub-surface work is completed. All other aspects of the VECP, unrelated to these Provisions, will be binding upon execution of the VECP.
TRUCK SAFETY DEVICES
(Supplementing Subsection 7.04: Motor Vehicles)
All motor vehicles subject to section 7 of chapter 90 to be operated under this Contract shall be equipped with safety devices as provided therein and in 540 CMR 4.00.
By December 31, 2025, the contractor shall certify to the Registry of Motor Vehicles, in a manner prescribed by the Registrar, that all applicable vehicles are equipped with Lateral Protective Devices, Convex Mirrors, Cross Over Mirror(s) and Back Up Cameras in accordance with the requirements of 540 CMR 4.00.
The Contractor shall provide evidence satisfactory to the Department to demonstrate compliance with the above certification requirement for all applicable vehicles operated under this contract by the Contractor and its subcontractors and vendors in a manner set forth by the Department.
Thereafter, the Contractor shall have an affirmative obligation to continue to provide such evidence of compliance on an ongoing basis and no later than 7 days after certification with the Registry of Motor Vehicles of any additional vehicles operated under this contract by the Contractor and its subcontractors and vendors.
Non-compliance with respect to a vehicle that is subject to 540 CMR 4.00 may subject the Contractor to statutory fines as established in M.G.L. c. 90, § 7 and/or contractual remedies up to and including termination of the contract.
A00801 - 16
SUBSECTION 8.14 UTILITY COORDINATION, DOCUMENTATION, AND
MONITORING RESPONSIBILITIES
A. GENERAL
In accordance with the provisions of Section 8.00 Prosecution and Progress, utility coordination is a critical aspect to this Contract. This section defines the responsibility of the Contractor and MassDOT, with regard to the initial utility relocation plan and changes that occur as the prosecution of the Work progresses. The Engineer, with assistance from the Contractor shall coordinate with Utility companies that are impacted by the Contractor’s operations. To support this effort, the Contractor shall provide routine and accurate schedule updates, provide notification of delays, and provide documentation of the steps taken to resolve any conflicts for the temporary and/or permanent relocations of the impacted utilities. The Contractor shall provide copies to the Engineer of the Contractor communication with the Utility companies, including but not limited to:
• Providing advanced notice, for all utility-related meetings initiated by the Contractor.
• Providing meeting minutes for all utility-related meetings that the Contractor attends.
• Providing all test pit records.
• Request for Early Utility work requirements of this section (see below).
• Notification letters for any proposed changes to Utility start dates and/or sequencing.
• Written notification to the Engineer of all apparent utility delays within seven (7)
Calendar Days after a recognized delay to actual work in the field – either caused by a Utility or the Contractor.
• Any communication, initiated by the Contractor, associated with additional Right-of-Way needs in support of utility work.
• Submission of completed Utility Completion Forms.
B. PROJECT UTILITY COORDINATION (PUC) FORM
The utility schedule and sequence information provided in the Project Utility Coordination Form (if applicable) is the best available information at the time of the bid and has been considered in setting the contract duration. The Contractor shall use all of this information in developing the bid price and the Baseline Schedule Submission, inclusive of the individual utility durations sequencing requirements, and any work that has been noted as potentially concurrent utility installations.
C. INITIATION OF UTILITY WORK
The Engineer will issue all initial notice-to-proceed dates to each Utility company based on either the:
1) Contractor’s accepted Baseline Schedule
2) An approved Early Utility Request in the form of an Early Utility sub-net schedule (in accordance with the requirements of this Subsection)
3) An approved Proposal Schedule
C.1 - BASELINE SCHEDULE – UTILITY BASIS
The Contractor shall provide a Baseline Schedule submission in accordance with the requirements of Subsection 8.02 and inclusive of all of the information provided in the PUC Form that has been issued in the Contract documents. This is to include the utility durations, sequencing of work, allowable concurrent work, and all applicable considerations that have been depicted on the PUC Form.
A00801 - 17
SUBSECTION 8.14 (Continued)
C.2 – EARLY UTILITY REQUEST – (aka SUBNET SCHEDULE) PRIOR TO THE
BASELINE
All early utility work is defined as any anticipated/required utility relocations that need to occur prior to the Baseline Schedule acceptance. In all cases of proposed early utility relocation, the Contractor shall present all known information at the pre-construction conference in the form of a ‘sub-net’ schedule showing when each early utility activity needs to be issued a notice-to-proceed. The Contractor shall provide advance notification of this intent to request early utility work in writing at or prior to the Pre-Construction meeting. Prior to officially requesting approval for early utility work, the Contractor shall also coordinate with MassDOT and all utility companies (private, state or municipal) which may be impacted by the Contract. If this request is acceptable to the Utilities and to MassDOT, the Engineer will issue a notice-to-proceed to the affected Utilities, based on these accepted dates.
C.3 – PROPOSAL SCHEDULE - CHANGES TO THE PUC FORM
If the Contractor intends to submit a schedule (in accordance with MassDOT Standard Specifications, Division I, Subsection 8.02) that contains durations or sequencing that vary from those provided in the Project Utility Coordination (PUC) Form, the Contactor must submit this as an intended change, in the form of a Proposal Schedule and in accordance with MassDOT Standard Specifications, Division I, Subsection 8.02. These proposed changes are subject to the approval of the Engineer and the impacted utilities, in the form of this Proposal Schedule and a proposed revision to the PUC form. The Contractor shall not proceed with any changes of this type without written authorization from the Engineer, that references the approved Proposal Schedule and PUC form changes. The submission of the Baseline Schedule should not include any of these types of proposed utility changes and should not delay the submission of the Baseline Schedule. As a prerequisite to the Proposal Schedule submission, and in advance of the utility notification(s) period, the Contractor shall coordinate the proposed utility changes with the Engineer and the utility companies, to develop a mutually agreed upon schedule, prior to the start of construction.
D. UTILITY DELAYS
The Contractor shall notify the Engineer upon becoming aware that a Utility owner is not advancing the work in accordance with the approved utility schedule. Such notice shall be provided to the Engineer no later than seven (7) calendar days after the occurrence of the event that the Contractor believes to be a utility delay. After such notice, the Engineer and the Contractor shall continue to diligently seek the Utility Owner’s cooperation in performing their scope of Work.
In order to demonstrate that a critical path delay has been caused by a third-party Utility, the Contractor must demonstrate, through the requirements of the monthly Progress Schedule submissions and the supporting contract records associated with Subsection 8.02, 8.10 and 8.14, that the delays were beyond the control of the Contractor.
A00801 - 18
SUBSECTION 8.14 (Continued)
All documentation provided in this section is subject to the review and verification of the Engineer and, if required, the Utility Owner. In accordance with MassDOT Specifications, Division I, Subsection 8.10, a Time Extension will be granted for a delay caused by a Utility, only if the actual duration of the utility work is in excess of that shown on the Project Utility Coordination Form, and only if;
1) proper Notification of Delay was provided to MassDOT in accordance with the time requirements that are specified in this Section
2) the utility delay is a critical path impact to the Baseline Schedule (or most recently approved Progress Schedule)
E. LOCATION OF UTILITIES
The locations of existing utilities are shown on the Contract drawings as an approximation only.
The Contractor shall perform a pre-construction utility survey, including any required test pits, to determine the location of all known utilities no later than thirty (30) calendar days before commencing physical site work in the affected area.
F. POST UTILITY SURVEY – NOTIFICATION
Following completion of a utility survey of existing locations, the Contractor will be responsible to notify the Engineer of any known conflicts associated with the actual location of utilities prior to the start of the work. The Engineer and the Contractor will coordinate with any utility whose assets are to be affected by the Work of this Contract. A partial list of utility contact information is provided in the Project Utility Coordination Form.
G. MEETINGS AND COOPERATION WITH UTILITY OWNERS
The Contractor shall notify the Engineer in advance of any meeting they initiate with a Utility Owner’s representative to allow MassDOT to participate in the meeting if needed.
Prior to the Pre-Construction Meeting, the Contractor should meet with all Utility Owners who will be required to perform utility relocations within the first 6 months of the project, to update the affected utilities of the Project Utility Coordination Form and all other applicable Contract requirements that impact the Utilities. The Contractor shall copy the Engineer on any correspondence between the Utility Owner and the Contractor.
H. FORCE ACCOUNT / UTILITY MONITORING REQUIREMENTS
The Engineer will be responsible for recording daily Utility work force reports. The start, suspension, re-start, and completion dates of each of the Utilities, within each phase of the utility relocation work, will be monitored and agreed to by the Engineer and the Contractor as the work progresses.
I. ACCESS AND INSPECTION
The Contractor shall be responsible for allowing Utility owners access to their own utilities to perform the relocations and/or inspections. The Contractor shall schedule their work accordingly so as not to delay or prevent each utility from maintaining their relocation schedule.
A00801 - 19
SOIL STOCKPILING DIRECTIVE P-22-001
Any stockpiling of soil must be performed in compliance with Policy Directive P-22-001, Off- Site Stockpiling of Soil from MassDOT Construction Projects. This directive limits the allowable locations for off-site stockpiling of soil generated during MassDOT projects and includes various requirements that must be satisfied by the contractor prior to off-site stockpiling. The Contractor is responsible for identifying a suitable stockpile location.
CONTAMINATED SOIL
Soil to be removed from the project area shall not be assumed to be uncontaminated and must be evaluated prior to off-site management for potential contamination with hazardous materials. No soil may be disposed of off-site without proper assessment by the contractor and approval from the Resident Engineer (RE), District Environmental Engineer (DEE), or the project designee.
ENVIRONMENTAL PERMITTING
Wetland permits have not been obtained, as no work (either temporary or permanent) is proposed to occur in water or wetland resource areas. If Contractor erection, demolition, storage, or other procedures require work to occur in or otherwise impact water, wetland resource areas, buffer zones, etc., the Contractor is advised that no associated work can occur until all required environmental permits have been obtained. The Contractor must notify the District Highway Director and Resident Engineer in writing at least 60 days prior to desired commencement of the proposed activity. All environmental submittals, including any contact with Local, State, or Federal environmental agencies, must be coordinated through the District Environmental Engineer. The Contractor is expected to fully cooperate with requests for information and provide same in a timely manner. The Contractor is further advised that the Department will not entertain a delay claim due to the time required to obtain the environmental permits. As a supplement to Section 7.00 of the Standard Specifications, the Contractor is reminded that no debris of any type shall be allowed to enter water or wetland resource areas, either temporarily or permanently.For various locations projects with work on or around existing steel or bearing areas.
A00801 - 20
ITEM 102.3…