(A) Exec Scope of Work 1694038 LP-40 ILRF.pdf

PDF 299 KB Posted

Attached to
LP-40 Install In-Line Receipt Filtration, Naval Station Norfolk, Norfolk, Virginia
Solicitation number
N4008525R2655
Issued by

About this file

This is an Executable Scope of Work for the LP-40 In-Line Receipt Filtration project at Naval Station Norfolk, Virginia. The project involves demolishing and removing an existing aboveground fuel filtration system and installing a new filtration system within an existing concrete slab with curb containment. The new system will include a vertical centrifugal pump, three vertical filter/separators, control valves, piping, and supports. Electrical work is required, including installing new buried electrical cabling in existing conduits between Building LP-18, the pump control building, and the pump location, as well as adding new control cabinetry and 480V, three-phase power requirements.

Key project details include a 270-calendar-day completion timeline, with work to be performed during regular government working hours at the LP Fuel Farm. The contractor must obtain Navy installation access through the Defense Biometrics Identification System, submit an Accident Prevention Plan and Activity Hazard Analysis, and comply with safety requirements. All demolished materials must be disposed of off-base, and the job site must be cleaned daily. Invoicing will be conducted electronically through the Wide Area Workflow (WAWF) system, and all work must adhere to standard industry practices, applicable codes, and the Unified Facilities Criteria.

View the file

Other files

Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

eProjects No: 1694038

Executable Scope of Work LP-40 In-Line Receipt Filtration at the

Naval Station, Norfolk, Virginia

PREPARED BY:

NAVFAC MID-ATLANTIC

Facilities Engineering and Acquisition Division Public Works Department Norfolk, Virginia

SUBMITTED BY:

Design Manager: Jeremy B Jones Civil: Jeremy B Jones Electrical David N Burnette

Date: November 25, 2024

APPROVED BY:

Project Management & Engineering Director: John C. Miller, P.E.

Design Director: James M. Smith, R.A.

For Commander, NAVFAC MID-ATLANTIC:

Date:

LP-40 In-Line Receipt Filtration Executable Scope

PWD Norfolk, Facilities Engineering and Acquisition Division Form Version 2023.04.25 Page 1 of 4 eProjects Work Order No: 1694038

Maximo SR Number: 20134493 Building: LP-Fuel Farm Project Title: LP-40 In-Line Receipt Filtration

Customer:

William Bounds william.j.bounds13.civ@us.navy.mil 757-445-3113

Scope By:

Civil JB Jones, PE jeremy.b.jones1.civ@us.navy.mil 757-341-0641 Electrical Dave Burnette david.n.burnette.civ@us.navy.mil 757-341-0676

Date:

October 30, 2024

1. General Description:

Contractor must provide supervision, labor, material, and equipment required to perform all work for the following project: LP-40 In-Line Receipt Filtration. Refer to section 13 “Project Overview and Work Requirements” for additional information.

All work must be performed in accordance with, but not limited to the following:

• Standard industry practices.

• Applicable local, state, federal codes, laws, and regulations.

• The Unified Facilities Criteria.

2. Location:

The work is located at the LP Fuel Farm, Naval Station Norfolk, Virginia. Refer to the attached drawings for a location map.

3. Time for Completion:

The project Contraction Completion Date (CCD) must be 270 calendar days from award.

4. Examination of the Premises:

Contractor must reference FAR Part 52.236-3 “Site Investigation and Conditions Affecting the Work”. Site visits by contractors are encouraged and must be coordinated with the Contracting Officer.

5. Inspection and Approval:

All material and workmanship is subject to the inspection and approval of the Government.

LP-Fuel Farm Secondary Receipt Executable Scope eProjects No.: 1694038

Form Version 2023.04.25 Page 2 of 4

6. Minimum Insurance Requirements:

Contractor must reference FAR Part 52.228-5 “Insurance-Work on a Government Installation” during the entire period of performance under this contract.

7. Special Scheduling Requirements / Work Procedures:

7.1 Utility Services will be in accordance with the procedures in FAR 41.202.

7.2 The work must be performed during regular Government working hours. Regular working hours must consist of an 8 1/2 hour period established by the Contracting Officer, Monday through Friday, excluding Government holidays.

7.3 The Contractor will be working around an active fueling compound. With the exception of the

LP-18 electrical building, do not enter any of the buildings without prior approval of the Contracting Officer.

7.4 Damage caused by construction operations must be repaired, patched and/or replaced to match adjacent areas to the satisfaction of the Contracting Officer at no additional cost to the Government.

7.5 Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.

8. Passes and Badges:

All Contractor employees must obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html .

9. Safety:

9.1 All work must be conducted in a safe manner and must comply with all requirement of the U.S.

Army Corps of Engineers Safety Health Requirements Manual EM-385-1-1.

9.2 Contractor must submit an Accident Prevent Plan (APP), and Activity Hazard Analysis (AHA) for approval by the Contracting Officer. Submit the APP and AHA to the Contracting Officer 15 calendar days prior to the pre-performance conference for acceptance.

10. Pre-Performance Conference:

Within 15 workdays of contract award, the Contractor must coordinate with the Contracting Officer to schedule a pre-performance conference.

https://www.cnic.navy.mil/om/dbids.html

Form Version 2023.04.25 Page 3 of 4

11. Hazardous Materials Disclosure Statements:

11.1 If the contracted work involves the use of hazardous material, submit, to the Contracting Officer, a Hazardous Material Inventory Report and a Daily Report including identification and quantity of the hazardous material used or removed.

11.2 Paint Containing Lead, Cadmium and Chromium (For projects that require disturbance or removal): Work which requires the disturbance or removal of paint that has been determined to contain all or any of the following: lead, cadmium and chromium, must be performed in accordance with 29 CFR 1926.62, 29 CFR 1926.1126 and 29 CFR 1926.1127.

11.3 Other Hazardous Materials (For projects that require disturbance or removal): Work which requires the disturbance or removal of any of the following: mercury and LLR Components, and PCB’s, must be performed in accordance with 29 CFR 1910.1000, 10 CFR 20, 40 CFR 273, and

40 CFR 761.

11.4 The LP-Fuel Farm was constructed in the 1940’s. All of the aboveground fuel piping was replaced in 1997. No hazardous materials should be expected. A Hazardous Materials Inspection survey was not performed. If suspect materials are uncovered, the Contractor must stop work until the materials are properly identified and addressed.

12. Submittals:

12.1 The Contractor must submit the following documents required for government approval, prior to the start of any construction activities:

• Shop Drawings

• Manufacturer’s Product Data

• Test Reports

• Certificates

• Manufacturer’s Warranties

• Work Schedule

• Equipment List

• Additional submittals as required for the project

13. Project Overview and Work Requirements:

13.1 Project Overview: Refer to the attached drawings

a. Demolition and removal of an aboveground fuel filtration system.

b. Filtration system to be removed includes a centrifugal pump, valves, piping, and filtration vessels.

c. The new filtration system includes a vertical centrifugal pump, three vertical filter/separators, control valves, piping, and supports. All work is located within an existing concrete slab with curb containment.

d. No excavation is required.

Form Version 2023.04.25 Page 4 of 4

e. Installation of new buried electrical cabling inside the existing conduit between Building LP-18, the existing pump control building, and the actual pump location.

f. New control cabinetry inside the existing pump control building.

g. New power requirements are 480V, (3) phase.

13.2 Demolition – Electrical Work Requirements

a. Disconnect and demolish wire from panel PP1 to motor starter in Valve Control Bldg... Retain existing conduit.

b. Demolish existing motor starter and wiring to existing 60HP motor.

13.3 New Work – Electrical Work Requirements

a. Provide new wire in existing conduit from panelboard “PP1” to new motor starter.

b. Provide new disconnect switch and wiring to new pump.

c. Provide new emergency stop button at pump.

d. Provide new ground rod and wire at pump.

13.4 The Contactor must dispose of all existing demolished / removed material off base and must completely clean up the job site daily at the end of each workday.

14. Invoicing Procedures:

Invoices rendered under this contract must be submitted electronically through Wide Area Workflow (WAWF). In accordance with DFARS Clause 252.232-7003 titled “Electronic Submission of Payment Requests”; this contract/order requires use of the DoD WAWF system for the submission of invoices.

15. Drawings: Attached

SOW_Cover.pdf
1694038_LP_40_In-Line_Receipt_Filtration_SOW_November_2024.pdf

2024-11-20T17:22:23-0500

2024-11-20T17:22:42-0500

File details come from the government source that posted it. Updated .