9-Liquidated Damages Form.pdf
PDF 84 KB Posted
- Solicitation number
- ITB No. 2026-024
- Issued by
- Palm Beach County, Florida
About this file
This is a Liquidated Damages Form from the Town of Palm Beach, Florida, establishing the financial penalties associated with project delays. The form outlines that the Town requires timely completion of work, with time being of the essence. The contractor and the contractor's surety are jointly liable for liquidated damages assessed on a per-calendar-day basis following the scheduled completion date. The damages are assessed according to the Town's adopted Florida Department of Transportation schedule (paragraph 8-10) and continue to accrue if the contractor is terminated for default prior to project completion. The form requires the contractor to acknowledge understanding and compliance with the liquidated damages terms through authorized signature, confirming the contractor's awareness of financial exposure for schedule delays or failure to complete the work.
This document serves as a binding acknowledgment by the contractor regarding delay penalties applicable to the A39, A42, A43 Pump Station Ventilation Improvements project. The liquidated damages calculation follows the FDOT schedule, though the specific dollar amounts per calendar day are referenced as "attached list" within the form but not detailed in this document excerpt. The form does not address pricing for the work itself, set-asides, or funding sources, as those elements are covered in the related Invitation to Bid and associated contract documents. The liquidated damages provision applies regardless of whether delays result from contractor performance issues or other circumstances, and penalties continue accumulating through project completion.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TOWN OF PALM BEACH
Liquidated Damages Form
Contractor is aware of Town's requirement that the Work achieve timely Completion, time being of the essence. Town and Contractor recognize and hereby acknowledge the difficulty and uncertainty of computing the damages that would be realized by Town in the event the Completion is not timely achieved. It is therefore agreed by Town and Contractor, that the Contractor and the Contractor's surety, shall be liable to and shall pay Town liquidated damages in the amount per attached list - Town adopted Florida Department of Transportation schedule, paragraph 8-10, see attached - for each calendar day after the date on which Completion was to have been achieved (including any Time Extension in approved, written Change Order(s) until Completion of the Work is achieved. In the event Contractor is terminated by reason of default prior to Completion being achieved, any liquidated damages shall continue to accrue and be charged against Contractor until Completion is achieved.
I hereby confirm that our company understands and will comply with Liquidated Damages Term above:
Company Name: Name:
Date: Authorized Signature:
TOWN OF PALM BEACH – Liquidated Damages Form