17-2026.02.25 A-39, A-42, A-43 WASTEWATER PUMP STATION VENTILATION IMPROVEMENTS.pdf

PDF 6 MB Posted

Attached to
A39, A42, A43 Pump Station Ventilation Improvements
Solicitation number
ITB No. 2026-024
Issued by
Palm Beach County, Florida

About this file

This is a construction bid set prepared for the Town of Palm Beach, Florida, for ventilation improvements at three wastewater pump stations: A-39, A-42, and A-43. The project requires qualified contractors holding a General Contract License and Certified Electric Contractor certification to furnish all labor and materials necessary to complete ventilation system improvements as depicted in the architectural, civil, and electrical drawings and specifications. The bid set includes comprehensive construction plans with 49 sheets covering site plans, demolition and proposed plans for each pump station, electrical layouts, details, and one-line diagrams. Contractors must submit bids online through Euna Procurement (Bonfire) on the Town's eProcurement platform. A non-mandatory pre-bid meeting will be held virtually via Microsoft Teams, with the date and time specified in the events section, strongly encouraged for contractors to seek clarification from the project manager and Town staff. Award will be made to the lowest responsive and responsible bidder meeting all requirements, with the Town reserving the right to award on an all-or-none basis or line-by-line basis. Bid prices must remain valid for ninety days from submission.

The specifications require all work to comply with the National Electrical Code (NFPA 70), Electrical Safety in the Workplace (NFPA 70E), local county and city codes, and the Florida Building Code with amendments. Contractors are required to visit the project site and become familiar with existing conditions before submitting bids, with no allowance provided for unobserved existing conditions. All equipment and materials must be new, unused, and UL-listed, with copper conductors exclusively (no aluminum unless specifically indicated). All electrical equipment and material shall be guaranteed against defects for one year from acceptance. Contractors must coordinate with the instrumentation contractor, local utilities including FPL (with the designated FPL representative being Mr. Reagan Alexander at 561-310-9850), and all other trades to avoid conflicts. Underground yard conduits must be installed minimum 24 inches below grade, and contractors must submit shop drawings for all electrical and control equipment. Control panels must be constructed by a UL 508A-approved vendor and bear a UL 508A label.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A-39, A-42, A-43 WASTEWATER PUMP

STATION VENTILATION IMPROVEMENTS

PREPARED FOR

TOWN OF PALM BEACH

COVER SHEET© G-1

Know what'sbelow.

Callbefore you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

CONSTRUCTION PLANS FOR

A-39, A-42, A-43 WASTEWATER PUMP STATION

VENTILATION IMPROVEMENTS

PREPARED FOR THE

TOWN OF PALM BEACH, FLORIDA

FEBRUARY 2026

Sheet List Table

Sheet Number Sheet Title

G-1 COVER SHEET

C-1 GENERAL NOTES

C-2 A-39 SITE PLAN

C-3 A-39 FIRST FLOOR DEMOLITION PLAN

C-4 A-39 PROPOSED FIRST FLOOR PLAN

C-5 A-39 DEMOLITION WETWELL AND DRYWELL PLAN AND SECTION

C-6 A-39 PROPOSED WETWELL AND DRYWELL PLAN AND SECTION

C-7 A-42 DEMOLITION PLAN AND SECTION

C-8 A-42 PROPOSED PLAN AND SECTION

C-9 A-43 DEMOLITION PLAN AND SECTION

C-10 A-43 PROPOSED PLAN AND SECTION

C-11 CONSTRUCTION DETAILS

E-1 ELECTRICAL LEGEND AND SYMBOLS

E-2 ELECTRICAL GENERAL NOTES

E-3 ELECTRICAL DEMOLITION PLAN

E-4 PROPOSED ELECTRICAL PLAN

E-5 PROPOSED ONE LINE DIAGRAM AND RISER DIAGRAMS

E-6 PROPOSED SCHEMATIC AND MODIFIED PANEL SCHEDULES

E-7 ELECTRICAL DETAILS

E-8 A-42 ELECTRICAL SITE PLAN

E-9 A-43 ELECTRICAL SITE PLAN

GENERAL NOTES© C-1

Know what'sbelow.

Callbefore you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

A-39 PROPOSED LOUVERS COMPONENTS

AND CLADDING WIND PRESSURES

A-39, A-42, A-43 WASTEWATER PUMP

STATION VENTILATION IMPROVEMENTS

PREPARED FOR

TOWN OF PALM BEACH

A-39 PUMP STATION

FIN FLOOR EL. = 7.00'

A-39 SITE PLAN© C-2

Know what'sbelow.

Callbefore you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

NORTH

A-39 SITE PLAN

A-39, A-42, A-43 WASTEWATER PUMP

STATION VENTILATION IMPROVEMENTS

A-39 FIRST FLOOR DEMOLITION

PLAN© C-3

Know what'sbelow.

Callbefore you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

NORTHNORTH

A-39 DEMOLITION FLOOR PLAN

A-39, A-42, A-43 WASTEWATER PUMP

STATION VENTILATION IMPROVEMENTS

L-1

L-1

A-39 PROPOSED FIRST FLOOR

PLAN© C-4

Know what'sbelow.

Callbefore you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

A-39 FLOOR PLAN

NORTH

A-39, A-42, A-43 WASTEWATER PUMP

STATION VENTILATION IMPROVEMENTS

A-39 DEMOLITION WETWELL AND

DRYWELL PLAN AND SECTION© C-5

Know what'sbelow.

Callbefore you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

DEMOLITION PLAN @ EL. (+)5.50' DEMOLITION SECTION 11

C-5

N O

R

TH

A-39, A-42, A-43 WASTEWATER PUMP

STATION VENTILATION IMPROVEMENTS

A-39 PROPOSED WETWELL AND

DRYWELL PLAN AND SECTION© C-6

Know what'sbelow.

Callbefore you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

PROPOSED PLAN @ EL. (+)5.50'

PROPOSED SECTION 11

C-6N

O R

TH

A-39, A-42, A-43 WASTEWATER PUMP

STATION VENTILATION IMPROVEMENTS

PREPARED FOR

TOWN OF PALM BEACH

A-42 DEMOLITION PLAN AND

SECTION© C-7

NORTH

A-42 DEMOLITION PLAN

A-42 DEMOLITION SECTION1

C-7

PREPARED FOR

TOWN OF PALM BEACH

A-42 PROPOSED PLAN AND

SECTION© C-8

A-42 PROPOSED PLAN

NORTH

A-42 PROPOSED SECTION1

C-8

PREPARED FOR

TOWN OF PALM BEACH

A-43 DEMOLITION PLAN AND

SECTION© C-9

A-43 DEMOLITION PLAN

NORTH

A-43 DEMOLITION SECTION1

C-9

PREPARED FOR

TOWN OF PALM BEACH

A-43 PROPOSED PLAN AND

SECTION© C-10

A-43 PROPOSED PLAN

NORTH

A-43 PROPOSED SECTION1

C-10

MASONRY SAW-CUT DETAIL

SCALE: N.T.S.

C-11

MASONRY OPENING CLOSURE DETAIL

SCALE: N.T.S.

C-11

LOUVER SILL DETAIL

SCALE: N.T.S.

C-11

LOUVER HEADER DETAIL

SCALE: N.T.S.

C-11

L-1

CONSTRUCTION DETAILS© C-11

Know what'sbelow.

Callbefore you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

INTAKE/EXHAUST LOUVERS

SCALE: N.T.S.

C-11

A-39, A-42, A-43 WASTEWATER PUMP

STATION VENTILATION IMPROVEMENTS

PHASE

SHIFT

XFMR

VFD-

XXXX

VFD-

XXXX

Know what's below.

Call before you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

ELECTRICAL LEGEND AND

SYMBOLS

E-1

A-39 WASTEWATER PUMP STATION

VENTILATION IMPROVEMENTS

PREPARED FOR

TOWN OF PALM BEACH

THE SCOPE OF ELECTRICAL WORK SHALL CONSIST PRIMARILY OF THE FOLLOWING:

ALL WORK AS DESCRIBED IN THE SPECIFICATIONS AND THE DRAWINGS.

CONTRACTOR SHALL COORDINATE WITH THE INSTRUMENTATION CONTRACTOR/SUPPLIER FOR POWER AND SIGNAL REQUIREMENTS FOR ALL DEVICES TO BE

CONNECTED. CONTRACTOR SHALL ADJUST CONDUIT AND CABLE AS PER INSTRUMENTATION REQUIREMENTS TO MATCH THE EQUIPMENT PROVIDED.

COORDINATION SHALL BE COMPLETED BEFORE CONDUIT AND CABLE ARE INSTALLED.

THE CONTRACTOR SHALL PROVIDE ALL MATERIALS AND LABOR TO INSTALL THE ELECTRICAL SYSTEMS AS INDICATED ON THE DRAWINGS. ITEMS NOT SHOWN BUT

OBVIOUSLY NECESSARY FOR COMPLETION OF THE WORK SHALL BE INCLUDED.

THE INSTALLATION SHALL BE IN ACCORDANCE WITH THE NATIONAL ELECTRICAL CODE (NFPA 70), ELECTRICAL SAFETY IN THE WORKPLACE (NFPA 70E), LOCAL

COUNTY CODES, LOCAL CITY/TOWN CODES, AND FLORIDA BUILDING CODE WITH AMENDMENTS.

THE CONTRACTOR SHALL COORDINATE HIS WORK WITH THE ENGINEER AND OWNER.

THE CONTRACTOR SHALL BEFORE SUBMITTING HIS BID, VISIT THE SITE OF THE PROJECT AND BECOME FAMILIAR WITH THE EXISTING CONDITIONS. NO

ALLOWANCE WILL BE MADE FOR EXISTING CONDITIONS OR FAILURE OF THE CONTRACTOR TO OBSERVE THEM.

IT IS THE CONTRACTOR'S RESPONSIBILITY TO COORDINATE WITH ALL LOCAL UTILITIES, INCLUDING THE POWER AND TELEPHONE UTILITIES TO MEET ALL OF THEIR

INSTALLATION REQUIREMENTS. ALL FEES, LABOR, EQUIPMENT OR MATERIALS NECESSARY TO MEET THESE REQUIREMENTS ARE TO BE INCLUDED IN THE BID.

THE CONTRACTOR SHALL OBTAIN, DELIVER AND INSTALL ALL CONDUITS, PULL-BOXES AND EQUIPMENT AS REQUIRED BY THE UTILITIES TO THEIR

SPECIFICATIONS. PROVIDE TEMPORARY POWER AND TELEPHONE AS PER SPECIFICATION.

FPL REPRESENTATIVE: MR REAGAN ALEXANDER <MATTHEW.ALEXANDER@FPL.COM> PH: 561-310-9850

ALL EQUIPMENT AND MATERIAL SHALL BE NEW, UNUSED, AND U.L. LISTED.

THE CONTRACTOR IS RESPONSIBLE TO TEST ALL SYSTEMS INSTALLED OR MODIFIED UNDER THIS PROJECT AND IS RESPONSIBLE TO REPAIR OR REPLACE ALL

DEFECTIVE WORK TO THE SATISFACTION OF THE ENGINEER AND OWNER.

ALL EQUIPMENT FURNISHED AND INSTALLED BY THE CONTRACTOR SHALL BE GUARANTEED AGAINST DEFECTS IN MATERIAL AND WORKMANSHIP FOR A PERIOD

OF ONE YEAR FROM DATE OF ACCEPTANCE OR AS OTHERWISE NOTED IN SPECIFICATIONS.

ALL CONDUCTORS SHALL BE COPPER. NO ALUMINUM ALLOWED UNLESS SPECIFICALLY INDICATED ON DRAWINGS.

ALL YARD CONDUITS (YC) AND OTHER UNDERGROUND CONDUITS WITHOUT YC NUMBER SHALL BE INSTALLED MINIMUM 24" BELOW GRADE AS PER DETAILS.

SHOP DRAWINGS SHALL BE SUBMITTED FOR ALL ELECTRICAL & CONTROL EQUIPMENT AND MATERIAL.

ALL CONTROL PANELS SHALL BE CONSTRUCTED BY A UL 508A APPROVED PANEL VENDOR AND SHALL BEAR A UL 508A LABEL ON THE PANEL.

THE DRAWINGS ARE NOT INTENDED TO SHOW THE EXACT LOCATION OF CONDUIT RUNS. THESE ARE TO BE COORDINATED WITH THE OTHER TRADES SO THAT

CONFLICTS ARE AVOIDED PRIOR TO INSTALLATIONS.

ALL LOCATIONS OF EQUIPMENT, PANELS, CONDUITS ETC. ARE SHOWN FOR ILLUSTRATION PURPOSES. CONTRACTOR SHALL VERIFY AND COORDINATE EXACT

LOCATION AND SIZE WITH ALL SUBCONTRACTORS AND EQUIPMENT SUPPLIERS PRIOR TO ANY INSTALLATION AND THEN INSTALL AS SUCH WITH CORRESPONDING

CONDUIT STUB-UPS.

SEE OTHER DISCIPLINE DRAWINGS FOR COORDINATION OF ALL EQUIPMENT LOCATIONS. ANY CONFLICTS SHALL BE BROUGHT TO THE ENGINEER'S ATTENTION

AND MOVEMENT OF CONDUITS OR OTHER ELECTRICAL EQUIPMENT SHALL BE ACCOMPLISHED WITHOUT ANY ADDITIONAL COST TO THE OWNER.

LOCATIONS OF MANHOLES, HANDHOLES AND PULL BOXES ARE APPROXIMATE. CONTRACTOR SHALL COORDINATE EXACT LOCATION WITH EXISTING AND NEW

PIPING OR CONDUIT AND ADJUST ACCORDINGLY.

NOT ALL CONDUITS SHOWN ON RISER AND ONE-LINE DIAGRAMS ARE SHOWN ON BUILDING LAYOUTS. CONTRACTOR SHALL SUPPLY ALL CONDUITS AND CABLES

AS SHOWN ON RISER AND ONE-LINE DIAGRAMS.

ALL CIRCUITS SHALL BE IDENTIFIED IN JUNCTION BOXES, PULL BOXES, CONTROL PANELS, PANELBOARDS, LIGHTING POLES, CONTROLLERS AND SERVICE POINTS.

IDENTIFICATION SHALL MATCH PANELBOARD SCHEDULES.

INSTRUMENTATION WIRING IS COMPRISED OF LOW VOLTAGE DC SIGNALS SUCH AS A 4-20MA CURRENT LOOP, TELEPHONE/INTERCOM, CURRENT LOOP COPPER

CABLE AND OTHER COMMUNICATION, AND FIRE ALARM COMMUNICATION WIRING. POWER CONDUIT AND WIRING SHALL ONLY CROSS INSTRUMENTATION CONDUIT

PERPENDICULARLY AT RIGHT ANGLES WITH A MINIMUM OF 6" SEPARATION.

CONDUCTOR PULLING TENSIONS SHALL NOT EXCEED MANUFACTURER'S RECOMMENDATION. CONTRACTOR SHALL INSTALL PULL BOXES TO MEET

MANUFACTURER'S REQUIREMENTS.

MINIMUM DISTANCE ALLOWED BETWEEN POWER CONDUITS AND INSTRUMENTATION CONDUITS SHALL BE:

VOLTAGE DISTANCE

480V 2 FT

120V 1 FT

THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL CONDUIT AND WIRING INSTALLATION FOR ALL VENDOR PROVIDED EQUIPMENT (PACKAGED SYSTEMS). IF THE

SHOP DRAWINGS DIFFER FROM THE DESIGNED FACILITIES, THE CONTRACTOR SHALL REDESIGN THE FACILITIES AND SUBMIT THE REVISED DESIGN FOR THE

ENGINEER'S APPROVAL ALONG WITH THE SHOP DRAWINGS. THERE SHALL BE NO ADDITIONAL COST TO THE OWNER FOR THE REDESIGN NOR FOR ANY

ADDITIONAL CONDUITS AND WIRING. DURING SUBMITTAL THE CONTRACTOR SHALL VERIFY ALL SUPPLIED BREAKER SIZES FOR ALL PACKAGED SYSTEMS SUCH AS

FUEL PUMPING SYSTEM, EXHAUST FANS, ETC., AND MODIFY ALL BREAKERS IN MCC'S AND PANELBOARDS ACCORDINGLY WITHOUT ANY ADDITIONAL COST TO THE

OWNER.

ALL EXCAVATIONS FOR CONDUITS, HANDHOLES, MANHOLES AND PULLBOXES NEAR EXISTING PIPING, CONDUIT AND EQUIPMENT SHALL BE HAND EXCAVATED AND

COORDINATED WITH AUTHORIZED WUD REPRESENTATIVE.

MINIMUM DEPTH FROM TOP OF DUCTBANKS OR CONDUITS TO FINISHED GRADE SHALL BE 24" UNLESS OTHERWISE NOTED.

25.

24.

23.

22.

21.

20.

19.

18.

17.

GENERAL NOTES

15.

16.

14.

13.

12.

10.

11.

9.

8.

7.

6.

5.

4.

3.

2.

A.

1.

COLORED WARNING TAPE 6" WIDE SHALL BE INSTALLED 8" BELOW FINISHED GRADE DIRECTLY ABOVE ALL UNDERGROUND YARD CONDUITS ACCORDING TO THE

FOLLOWING SCHEDULE:

POWER: RED

ALL OTHER CONDUITS: GREEN

CONTRACTOR SHALL RESTORE SIDEWALKS, ROADWAYS, SOD, SPRINKLER SYSTEM PIPING, FLOOR ETC. TO MATCH EXISTING, AFTER THE COMPLETION OF THE

CONDUIT AND PULLBOX INSTALLATION.

ALL EQUIPMENT GROUND WIRE SIZED PER NEC SHALL BE PULLED IN ALL ELECTRICAL CONDUITS, POWER AND CONTROL, WHETHER OR NOT INDICATED ON THE

PLANS.

ALL ENCLOSURES, TJB, WIREWAY, PULL BOXES ETC. SHALL CONTAIN A GROUNDING BUS. CONNECT ALL RACEWAY BONDS TO THIS BUS VIA GROUNDING BUSHING

AND EXTEND BONDING JUMPER FROM THIS BUS TO THE ENCLOSURE.

ALL DUCTBANKS SHALL CARRY A MINIMUM #4/0 AWG BARE TINNED COPPER GROUND WIRE, OVER THE ENTIRE LENGTH, WHICH SHALL BE CONNECTED TO THE

SITE GROUNDING GRID AND GROUND RODS LOCATED IN CONNECTING MANHOLES, HANDHOLES OR PULL BOXES.

ALL CONDUITS PENETRATING RATED FIRE WALLS OR RATED FIRE FLOORS SHALL BE INSTALLED WITH U.L. APPROVED DEVICES TO MAINTAIN THE FIRE RATING OF

THE WALL OR FLOOR PENETRATED.

GROUNDING SHALL BE INSTALLED IN ACCORDANCE WITH NEC, ARTICLE 250. THE GROUNDING SYSTEM TEST SHALL NOT EXCEED A 48 HOUR SPAN DRY

RESISTANCE OF 10 OHMS. ADDITIONAL GROUNDING TO MEET THIS REQUIREMENT SHALL BE INSTALLED AT NO EXTRA COST. GROUNDING AND BONDING

CONNECTIONS SHALL NOT BE PAINTED. ALL GROUNDING CONNECTIONS SHALL BE EXOTHERMIC UNLESS SPECIFICALLY INDICATED OTHERWISE.

CONTRACTOR SHALL X-RAY EXISTING WALLS OR FLOOR SLAB BEFORE SAW CUTTING OR DRILLING FOR CONDUIT PENETRATIONS.

PRIMARY STRUCTURE OR BUILDING GROUNDING SHALL BE AN EMBEDDED GRID OF MINIMUM #4/0 AWG BARE TINNED COPPER WIRE INSTALLED IN THE

FOUNDATION AND AROUND THE STRUCTURE OR BUILDING PERIMETER, MINIMUM 30" BELOW FINISHED GRADE TO FORM A COMPLETE LOOP. SECONDARY

GROUND CONNECTIONS TO ALL METAL EQUIPMENT, HAND RAILS, STRUCTURAL STEEL, CONCRETE PADS, REBAR, ETC. SHALL HAVE A MINIMUM #4 STRANDED

BARE TINNED COPPER CONDUCTOR BONED USING APPROVED LUGS OR EXOTHERMIC CONNECTIONS. ALL EQUIPMENT GROUNDING CONDUCTORS PENETRATING

CONCRETE SLABS OR FINISHED GRADE SHALL HAVE A 72" CONDUCTOR PIGTAIL AT EACH LOCATION FOR CONNECTION TO EQUIPMENT.

ALL MATERIAL IN DESIGNATED CORROSIVE AREAS SHALL BE NEMA 4X 316 STAINLESS STEEL OR NON-METALLIC.

ALL OUTDOOR LIGHTING FIXTURE ENCLOSURES SHALL BE OF COPPER-FREE ALUMINUM CONSTRUCTION.

CONTRACTOR SHALL BALANCE PANELBOARD LOADS (WITHIN 5%) AT THE END OF THE PROJECT, WHERE POSSIBLE.

ALL REFERENCES TO SS OR STAINLESS STEEL MEAN 316 STAINLESS STEEL.

ALL VERTICAL CONDUIT PENETRATIONS FROM CONCRETE SLAB SHALL HAVE A MAINTENANCE PAD TO PREVENT CORROSION.

NO CONDUIT SHALL PENETRATE AN OUTDOOR ELECTRICAL PANEL FROM THE TOP. FOR OUTDOOR PANELS, ALL CONDUIT PENETRATIONS SHALL BE FROM

BOTTOM OR SIDE WITH APPROVED RAINTIGHT HUBS.

PROVIDE RECORD DRAWINGS, INCLUDING SINGLE LINE DIAGRAM AND FLOOR PLANS INDICATING LOCATION AND AREA SERVED FOR ALL DISTRIBUTION, TO THE

OWNER WITHIN 30 DAYS OF SYSTEM ACCEPTANCE AS REQUIRED BY FLORIDA BUILDING CODE.

PROVIDE OPERATING MANUALS TO THE OWNER AS REQUIRED BY FLORIDA BUILDING CODE . THE OPERATING MANUAL AND MAINTENANCE MANUAL SHALL

INCLUDE THE MINIMUM REQUIREMENTS AS STATED IN FLORIDA BUILDING CODE.

ALL SPARE CONDUITS SHALL BE SEALED WITH A CAP AT BOTH ENDS AND A PULL STRING INSTALLED WITH IDENTIFICATION ON BOTH ENDS, WHETHER INDICATED

OR NOT ON DRAWINGS.

PROVIDE CONDUIT DUCT SEAL AT ALL CONDUIT ENDS.

FLEXIBLE CONDUITS SHALL BE USED TO TERMINATE ALL MOTORS, OTHER VIBRATING EQUIPMENT, AND FREQUENTLY REMOVED EQUIPMENT AND SHALL BE

BETWEEN 18" AND 3' IN LENGTH.

DO NOT MOUNT ANY EQUIPMENT OR INSTRUMENT ON HANDRAIL.

DEMOLISH ALL ITEMS AS INDICATED ON DRAWINGS. TURN OVER TO THE OWNER AT THE OWNER'S DISCRETION AND PROPERLY DISPOSE OF ALL DEMOLITION

ITEMS NOT WANTED BY THE OWNER.

THE EXISTING ELECTRICAL INFORMATION IS OBTAINED FROM "RECORD DRAWINGS" AND OTHER "AS-BUILT DRAWINGS".

CONTRACTOR SHALL VERIFY THE INFORMATION PROVIDED IN THESE DRAWINGS AND ADJUST ACCORDINGLY. ANY CONFLICTS

SHALL BE BROUGHT TO THE ENGINEER'S ATTENTION BEFORE SUBMITTING HIS BID.

NOTE:

31.

37.

30.

36.

35.

34.

33.

32.

29.

28.

27.

38.

39.

40.

41.

42.

43.

44.

45.

46.

26.

47.

48.

Know what's below.

Call before you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

A-39 PUMP STATION

ELECTRICAL GENERAL NOTES

E-2

A-39 WASTEWATER PUMP STATION

VENTILATION IMPROVEMENTS

PREPARED FOR

TOWN OF PALM BEACH

Know what's below.

Call before you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

ELECTRICAL DEMOLITION PLAN

E-3

NORTH

NOTE:

A-39 PUMP STATION - ELECTRICAL DEMOLITION PLAN

ELECTRICAL RISER DIAGRAM - DEMOLITION

A-39 WASTEWATER PUMP STATION

VENTILATION IMPROVEMENTS

PREPARED FOR

TOWN OF PALM BEACH

T

T

S

S

Know what's below.

Call before you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

PROPOSED ELECTRICAL PLAN

E-4

NORTH

A-39 PUMP STATION - PROPOSED ELECTRICAL PLAN

KEYED NOTES:

A-39 WASTEWATER PUMP STATION

VENTILATION IMPROVEMENTS

PREPARED FOR

TOWN OF PALM BEACH

PUMP STATION A-39 ONE LINE DIAGRAM - PROPOSED

SERVICE CALCULATION @ 480V, 3-PHASE

PROPOSED RISER DIAGRAM

MODIFICATIONS OF EXISTING MCC

KEYED NOTES:

EXISTING MCC

Know what's below.

Call before you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

PROPOSED ONE LINE DIAGRAM

AND RISER DIAGRAMS

E-5

A-39 WASTEWATER PUMP STATION

VENTILATION IMPROVEMENTS

PREPARED FOR

TOWN OF PALM BEACH

EXISTING PANEL "LP-2"

EXISTING PANEL "LP-1"

Know what's below.

Call before you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

PROPOSED SCHEMATIC AND

MODIFIED PANEL SCHEDULES

E-6

KEYED NOTES:

A-39 WASTEWATER PUMP STATION

VENTILATION IMPROVEMENTS

PREPARED FOR

TOWN OF PALM BEACH

CONDUIT SUPPORT

MOUNTING DETAILS

CONDUIT PIPE STRAP

TRAPEZE ASSEMBLY

CONDUIT GROUNDING

CONDUIT HUB

Know what's below.

Call before you dig.

CALL 2 WORKING DAYS

BEFORE YOU DIG

IT'S THE LAW!

DIAL 811

SUNSHINE STATE ONE CALL OF FLORIDA, INC.

BID SET

ELECTRICAL DETAILS

E-7

A-39 WASTEWATER PUMP STATION

VENTILATION IMPROVEMENTS

PREPARED FOR

TOWN OF PALM BEACH

PREPARED FOR

TOWN OF PALM BEACH

A-42 ELECTRICAL SITE PLAN© E-8

SCALE

FEET

21 4

PREPARED FOR

TOWN OF PALM BEACH

A-43 ELECTRICAL SITE PLAN© E-9

SCALE

FEET

21 4

File details come from the government source that posted it. Updated .