80KSC025R0009 - Attachment J-G PCN 99300 PCM Construction Schedule Tower C.pdf
PDF 600 KB Posted
- Attached to
- Vehicle Assembly Building (VAB) Power Phase I (Tower C), Project Control Number (PCN): 99300
- Solicitation number
- 80KSC025R0009
About this file
This is a detailed project schedule for the NASA Revitalize Power System VAB Tower C project, prepared by AECOM as a 100% design schedule. The project spans from October 6, 2025, to February 4, 2028, with a total duration of 610 days and encompasses comprehensive electrical infrastructure upgrades at NASA's Vehicle Assembly Building (VAB) Tower C facility.
The project includes a 420-day pre-construction phase involving hazmat abatement planning, shop drawing submissions and reviews for substations SS-804 and SS-874, transformers, and distribution panels, followed by equipment procurement activities lasting 250-300 calendar days. The 255-day field construction phase covers removal of existing electrical equipment including oil-filled transformers, substations, and associated infrastructure, installation of new power systems including unit substations, transformers, panelboards, conduits, and cable systems, along with communication infrastructure and electronic safety/security systems. Key milestones include contract award on October 6, 2025, notice to proceed on October 21, 2025, substantial completion on December 21, 2027, and project completion on February 4, 2028. The schedule incorporates mandatory inspection points, NETA ATS testing, power system studies, and a final turnover phase including as-built documentation and closeout submittals, with construction activities measured in work days and procurement/submittal durations in calendar days.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Original Duration
Start Finish Calendar
TotalTotal 610 06-Oct-25 04-Feb-28
NASA Revitalize Power- VAB Tower CNASA Revitalize Power- VAB Tower C 610 06-Oct-25 04-Feb-28
MilestoneMilestone 581 06-Oct-25 04-Feb-28 NASA- VAB
A1000 Contract Award 0 06-Oct-25* NASA- VAB
A1010 Kick-of-Meeting NTP- Notice To Proceed 0 21-Oct-25 NASA- VAB
A1190 Field Construction 255 15-Dec-26 21-Dec-27 NASA- VAB
A1990 Substaintial Completion 0 21-Dec-27 NASA- VAB
A2050 Project Completion 0 04-Feb-28 NASA- VAB
Period of PerformancePeriod of Performance 599 21-Oct-25 04-Feb-28
Pre-ConstructionPre-Construction 420 21-Oct-25 14-Dec-26 *Standard 7-day calendar A1020 Submit Hazmat Abatement Plan 30 21-Oct-25 19-Nov-25 *Standard 7-day calendar A1030 Submit Substation SS-804 Shop drawings 30 21-Oct-25 19-Nov-25 *Standard 7-day calendar
A1040 Submit Transformer T-SS804 Shop drawings 30 21-Oct-25 19-Nov-25 *Standard 7-day calendar
A1050 Submit Transformer T-SS874 Shop drawings 30 21-Oct-25 19-Nov-25 *Standard 7-day calendar
A1060 Submit Distribution Panel Shop drawings 30 21-Oct-25 19-Nov-25 *Standard 7-day calendar
A1070 Submit Site Specific Safety Plan 30 21-Oct-25 19-Nov-25 *Standard 7-day calendar
A1080 Review Hazmat Abatement Plan 30 20-Nov-25 19-Dec-25 *Standard 7-day calendar
A1090 Review Substation SS-804 Shop drawings 90 20-Nov-25 17-Feb-26 *Standard 7-day calendar
A1100 Review Transformer T-SS804 Shop drawings 90 20-Nov-25 17-Feb-26 *Standard 7-day calendar
A1110 Review Transformer T-SS874 Shop drawings 90 20-Nov-25 17-Feb-26 *Standard 7-day calendar
A1120 Review Distribution Panel Shop drawings 90 20-Nov-25 17-Feb-26 *Standard 7-day calendar
A1130 Review Site Specific Safety Plan 30 20-Nov-25 19-Dec-25 *Standard 7-day calendar
A1140 Equipment Procurement- Substation SS-804 250 18-Feb-26 25-Oct-26 *Standard 7-day calendar
A1150 Equipment Procurement- Transformer T-SS804 300 18-Feb-26 14-Dec-26 *Standard 7-day calendar
A1160 Equipment Procurement- Substation T-SS874 300 18-Feb-26 14-Dec-26 *Standard 7-day calendar
A1170 Equipment Procurement- Distribution Panel 30 18-Feb-26 19-Mar-26 *Standard 7-day calendar
Field ConstructionField Construction 255 15-Dec-26 21-Dec-27 NASA- VAB General RequirementsGeneral Requirements 49 15-Dec-26 25-Feb-27 NASA- VAB
A1200 Nuts and Bolts Meeting 1 15-Dec-26 15-Dec-26 NASA- VAB
A1210 Construction Mobilization 20 16-Dec-26 14-Jan-27 NASA- VAB
A1220 Scaffolding, steel tubular, regular, labor only to erect & dismantle, building exterior, wall face, 6'-4" x 5' frames
10 15-Jan-27 29-Jan-27 NASA- VAB
A1250 Install Steel plate, structural, for floor protection 11 01-Feb-27 16-Feb-27 NASA- VAB
A1260 Fall Protection Systems 10 01-Feb-27 12-Feb-27 NASA- VAB
A1270 Rigging & Safety Railings 5 01-Feb-27 05-Feb-27 NASA- VAB
A1280 Temporary Mats for floor slab protection 2 17-Feb-27 18-Feb-27 NASA- VAB
A1290 Woven wire partitions, Remove and reset 5 19-Feb-27 25-Feb-27 NASA- VAB
MIPs- Mandatory InspectionsMIPs- Mandatory Inspections 65 15-Jan-27 19-Apr-27 NASA- VAB A1230 Cable Idenification Prior To Cutting 2 15-Jan-27 19-Jan-27 NASA- VAB
A1240 Demonstration Splice/Termination 2 20-Jan-27 21-Jan-27 NASA- VAB
A1350 Verify New Equipment Location Prior To Installation 1 26-Feb-27 26-Feb-27 NASA- VAB
A1360 Inspect Concrete Equipment Pad Forms and Reinforcing 1 04-Mar-27 04-Mar-27 NASA- VAB
A1500 Concealed Conduit/Penetration Inspection 2 09-Apr-27 12-Apr-27 NASA- VAB
A1520 Cable Acceptance Testing 2 16-Apr-27 19-Apr-27 NASA- VAB
ConcreteConcrete 10 05-Mar-27 18-Mar-27 NASA- VAB A1380 Structural concrete, in place, equipment pad (3000 psi), 6" 7 05-Mar-27 15-Mar-27 NASA- VAB
A1390 Concrete core drilling, core, reinforced concrete slab, 6" diameter, 3 16-Mar-27 18-Mar-27 NASA- VAB
MetalsMetals 10 19-Mar-27 01-Apr-27 NASA- VAB A1410 Conduit Rack Assemblies 5 19-Mar-27 25-Mar-27 NASA- VAB
A1420 Conduit Trapeeze Assemblies 5 19-Mar-27 25-Mar-27 NASA- VAB
A1460 Tube Steel Enclosure Framing 5 26-Mar-27 01-Apr-27 NASA- VAB
Electrical EquipmentElectrical Equipment 215 15-Dec-26 21-Oct-27 NASA- VAB RemovalRemoval 166 26-Feb-27 21-Oct-27 NASA- VAB
A1310 Remove conduits, fittings and hangers 1 26-Feb-27 01-Mar-27 NASA- VAB
A1580 Utility Outage Request- SS804 1 12-May-27 12-May-27 NASA- VAB
A1600 Utility Outage Request -Approval- SS804 1 04-Jun-27 04-Jun-27 NASA- VAB
A1610 Remove/Intercept feeder to Substation SS-804 7 07-Jun-27 15-Jun-27 NASA- VAB
A1630 Remove Circuits 34 22-Jun-27 09-Aug-27 NASA- VAB
A1810 Remove Flourescent Light Fixtures 3 21-Jul-27 23-Jul-27 NASA- VAB
A1850 Remove substation SS-804 3 10-Aug-27 12-Aug-27 NASA- VAB
A1870 Utility Outage Request- SS874 1 27-Aug-27 27-Aug-27 NASA- VAB
A1890 Utility Outage Request- PD875 1 03-Sep-27 03-Sep-27 NASA- VAB
A1900 Utility Outage Approval- SS874 1 21-Sep-27 21-Sep-27 NASA- VAB
A1910 Remove/intercept feeder to substation SS874 3 22-Sep-27 24-Sep-27 NASA- VAB
A1930 Remove substation SS874 3 27-Sep-27 29-Sep-27 NASA- VAB
A1940 Utility Outage Approval- PD875 1 28-Sep-27 28-Sep-27 NASA- VAB
A1950 Remove/intercept feeder to substation SS875 7 29-Sep-27 07-Oct-27 NASA- VAB
A1960 Remove substation SS875 7 08-Oct-27 19-Oct-27 NASA- VAB
A1980 Remove Oil Filled Transformers 2 20-Oct-27 21-Oct-27 NASA- VAB
New PowerNew Power 209 15-Dec-26 14-Oct-27 NASA- VAB A1180 Transformer T-SS74 15 15-Dec-26 06-Jan-27 NASA- VAB
A1320 Rigid galvanized steel conduit 30 26-Feb-27 08-Apr-27 NASA- VAB
A1330 Dry type transformer,3 phase 480 v prmry 120/208 v secnd,112.5 kva,k-13 rated 1 26-Feb-27 26-Feb-27 NASA- VAB
A1510 Cable tray, trough, aluminum, vented 3 13-Apr-27 15-Apr-27 NASA- VAB
A1530 Pull boxes and cabin enclosed fiber, wall mounted 1 20-Apr-27 20-Apr-27 NASA- VAB
A1540 Pull Box, to 36" square x 6" 1 20-Apr-27 20-Apr-27 NASA- VAB
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 2026 2027 2028
Total
NASA Revitalize Power- VAB Tower C
Milestone
Contract Award
Kick-of-Meeting NTP- Notice To Proceed
Substaintial Completion
Project Completion
Period of Performance
Pre-Construction
Field Construction General Requirements
MIPs- Mandatory Inspections
Concrete
Metals
Electrical Equipment Removal
New Power
NASA Revitalize Power- VAB Tower C- Full Schedule
Remaining Work
Critical Remaining Work
Milestone
Summary Page 1 of 2
Project Start: 06-Oct-25
Project Finish: 04-Feb-28
Project Name: NASA REVITALIZE POWER SYSTEM VAB TOWER C
P6 Project ID: NASA VAB TOWER C-6
100% DESIGN Schedule
DURATION REPRESENTED FOR CONSTRUCTION ACTIVITIES ARE IN WORK DAY. DURATION
REPRESENTED FOR SUBMIITTALS/PROCUREMENT ARE IN CALENDAR DAYS.
PREPARED BY: AECOM
Activity ID Activity Name Original Duration
Start Finish Calendar
A1550 Pull Box, 96"x10"x10" 1 20-Apr-27 20-Apr-27 NASA- VAB
A1560 Unit Substation USS-804 switchgear 15 21-Apr-27 11-May-27 NASA- VAB
A1570 Transformer T-SS804 15 12-May-27 02-Jun-27 NASA- VAB
A1590 Standard Switchgear 13 03-Jun-27 21-Jun-27 NASA- VAB
A1620 Panelboards, 3 phase 4 wire, main lugs, 125A MCB/30 Circuit 250A MLO 5 22-Jun-27 28-Jun-27 NASA- VAB
A1640 Circuit breaker, 3 pole, 600 volt, 125 amp, enclosed (NEMA 1) 1 22-Jun-27 22-Jun-27 NASA- VAB
A1650 Panelboards, 3 phase 4 wire, main lugs, 277/480 V, 225 amp 2 22-Jun-27 23-Jun-27 NASA- VAB
A1660 Panelboards, 3 phase 4 wire, main lugs, 277/480 V, 300 amp 7 22-Jun-27 30-Jun-27 NASA- VAB
A1670 Panelboards, 3 phase 4 wire, main lugs, 277/480 V, 100 amp 7 22-Jun-27 30-Jun-27 NASA- VAB
A1680 1" Sch 40 PVC Conduit-Grounding 1 29-Jun-27 29-Jun-27 NASA- VAB
A1690 4/0 Bare Copper conductor-Grounding 1 29-Jun-27 30-Jun-27 NASA- VAB
A1700 Exothermic Weld-Grounding 2 30-Jun-27 02-Jul-27 NASA- VAB
A1710 Wire, copper, stranded in raceway 10 01-Jul-27 15-Jul-27 NASA- VAB
A1720 Wire, copper, stranded, 1/0 Concentric 1 01-Jul-27 01-Jul-27 NASA- VAB
A1730 Circuit ID tags for Conduits-Grounding 4 02-Jul-27 09-Jul-27 NASA- VAB
A1740 Connector clamp to Equipment 1 02-Jul-27 06-Jul-27 NASA- VAB
A1750 NEMA 12 24"x24"x10"d Comm Panel 5 06-Jul-27 13-Jul-27 NASA- VAB
A1760 Circuit breaker, 3 pole, 600 volt, 125 amp, enclosed (NEMA 1) 1 16-Jul-27 16-Jul-27 NASA- VAB
A1770 Outlet boxes, pressed steel, masonry, 1 gang, 2-1/2" deep-Lighting 1 16-Jul-27 16-Jul-27 NASA- VAB
A1780 Signs, Engraved Nameplates 3 16-Jul-27 21-Jul-27 NASA- VAB
A1790 Toggle switch, quiet type, single pole, 20 amp- Lighting 1 19-Jul-27 19-Jul-27 NASA- VAB
A1800 Fluorescent fixture,interior,strip,pendent mounted,industrial,white porcelain enamel,rs, 2-40 w,4'l- Lighting
1 20-Jul-27 20-Jul-27 NASA- VAB
A1820 Reconnect panelboard circuits 4 21-Jul-27 27-Jul-27 NASA- VAB
A1860 Switchboard PD-874 10 13-Aug-27 26-Aug-27 NASA- VAB
A1880 Switchboard PD-875 5 27-Aug-27 02-Sep-27 NASA- VAB
Commission and TestingCommission and Testing 55 27-Jul-27 14-Oct-27 NASA- VAB A1830 NETA ATS Testing 40 27-Jul-27 22-Sep-27 NASA- VAB
A1840 Grounding Testing 5 27-Jul-27 03-Aug-27 NASA- VAB
A1920 Power System Studies 15 22-Sep-27 14-Oct-27 NASA- VAB
CommunicationCommunication 10 26-Feb-27 11-Mar-27 NASA- VAB A1300 NEMA 12 24"x24"x10"d Comm Panel 5 26-Feb-27 04-Mar-27 NASA- VAB
A1370 KCCS Systems Infrastructure Allowance 5 05-Mar-27 11-Mar-27 NASA- VAB
Electronic Safety and SecurityElectronic Safety and Security 26 26-Feb-27 05-Apr-27 NASA- VAB A1340 Rigid galv steel conduit,3/4"diam,15'high,incl couplings only 14 26-Feb-27 18-Mar-27 NASA- VAB
A1400 Outlet boxes, pressed steel, 4" square 1 18-Mar-27 19-Mar-27 NASA- VAB
A1430 Wire, copper, solid, 600 volt, #14, type THWN-THHN, in raceway 3 19-Mar-27 24-Mar-27 NASA- VAB
A1440 Safety switches, general duty, 3 pole, fusible, 240 volt, 30 amp, NEMA 1 1 24-Mar-27 25-Mar-27 NASA- VAB
A1450 Modify FA Panels, Add terminal strip and reprogram 1 25-Mar-27 26-Mar-27 NASA- VAB
A1470 Air Sampling system, Interface, Tubing and Ports 2 26-Mar-27 30-Mar-27 NASA- VAB
A1480 FA Testing 3 30-Mar-27 02-Apr-27 NASA- VAB
A1335 FA Demolition 1 02-Apr-27 05-Apr-27 NASA- VAB
Project Final Punchlist- Final InspectionProject Final Punchlist- Final Inspection 40 22-Oct-27 21-Dec-27 NASA- VAB A2010 Punchlist 30 22-Oct-27 07-Dec-27 NASA- VAB
A2040 Demobilization 10 08-Dec-27 21-Dec-27 NASA- VAB
Turnover PhaseTurnover Phase 30 22-Dec-27 04-Feb-28 NASA- VAB A2000 As-Builts, O&M & Closeout Submittals 30 22-Dec-27 04-Feb-28 NASA- VAB
A2020 Initiate Turnover 1 22-Dec-27 22-Dec-27 NASA- VAB
A2030 Approve DD250 29 23-Dec-27 04-Feb-28 NASA- VAB
Downtime and Excavationm Hold PhaseDowntime and Excavationm Hold Phase 10 14-Oct-27 28-Oct-27 NASA- VAB A1970 NASA No-Work Down Days 10 14-Oct-27 28-Oct-27 NASA- VAB
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 2026 2027 2028
Commission and Testing
Communication
Electronic Safety and Security
Project Final Punchlist- Final Inspection
Turnover Phase
Downtime and Excavationm Hold Phase
NASA Revitalize Power- VAB Tower C- Full Schedule
Remaining Work
Critical Remaining Work
Milestone
Summary Page 2 of 2
Project Start: 06-Oct-25
Project Finish: 04-Feb-28
Project Name: NASA REVITALIZE POWER SYSTEM VAB TOWER C
P6 Project ID: NASA VAB TOWER C-6
100% DESIGN Schedule
DURATION REPRESENTED FOR CONSTRUCTION ACTIVITIES ARE IN WORK DAY. DURATION
REPRESENTED FOR SUBMIITTALS/PROCUREMENT ARE IN CALENDAR DAYS.
PREPARED BY: AECOM