RESPONSE_TO_BIDDER_QUESTIONS_5-8-18.docx

DOCX document 19 KB Posted

Attached to
Upgrade Liquid Hydrogen (LH2) System, Launch Complex 39B Federal contract opportunity
Solicitation number
80KSC018R0016
Issued by
National Aeronautics and Space Administration Kennedy Space Center

About this file

80KSC018R0016 Bidder Questions and Answers 5/8/18

View the file

Other files for this federal contract opportunity

Other files attached to Upgrade Liquid Hydrogen (LH2) System, Launch Complex 39B, newest first.
File Type Posted
Sphere_Source_Selection_Statement_Final_Signed.pdf PDF
80KSC018R016_Amendment_9.pdf PDF
80KSC018R016_Amendment_8_SF30.pdf PDF
RESPONSE_TO_BIDDER_QUESTIONS_6-15-18.docx DOCX document
80KSC018R016_Amendment_7.pdf PDF
RESPONSE_TO_BIDDER_QUESTIONS_6-14-18.docx DOCX document
Solicitation_KSC018R0016_SF1442_C.2__Change_Page.pdf PDF
80KSC018R016_Amendment_6_SF30.pdf PDF
Solicitation_KSC018R0016_SF1442_J-B-26_Change_Page.pdf PDF
80KSC018R016_Amendment_6_Continuation.docx DOCX document
RESPONSE_TO_BIDDER_QUESTIONS_6-11-18.docx DOCX document
80KSC018R016_Amendment_5_SF30.pdf PDF
RESPONSE_TO_BIDDER_QUESTIONS_6-5-18.docx DOCX document
RESPONSE_TO_BIDDER_QUESTIONS_6-4-18.docx DOCX document
80KSC018R016_Amendment_4.pdf PDF
RESPONSE_TO_BIDDER_QUESTIONS_5-31-18.docx DOCX document
80KSC018R016_Amendment_3.pdf PDF
RESPONSE_TO_BIDDER_QUESTIONS_5-30-18.docx DOCX document
RESPONSE_TO_BIDDER_QUESTIONS_5-23-18.docx DOCX document
PCN_98985_Geotechnical_Report.pdf PDF
PCN_98985_Environmental_Report.pdf PDF
RESPONSE_TO_BIDDER_QUESTIONS_5-9-18.docx DOCX document
80KSC018R016_Amendment_2.pdf PDF
Pre-Bid_Attendee_List.docx DOCX document
80KSC018R016_Amendment_1.pdf PDF
Brand_Name_Justification_PLC.pdf PDF
Solicitation_80KSC018R0016_SF1442_Continuation.pdf PDF
80KSC018R0016__Attachment_J1C_DOL_Area_Wage_Determination.pdf PDF
80KSC018R0016_SF1442.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

80KSC018R0016

QUESTION & ANSWERS 5/8/18

RESPONSE TO BIDDER QUESTIONS:

1. REFERENCE: RFP General QUESTION: Since the contractor is carrying the design for the Liquid Hydrogen Sphere we would like to request a 5-week extension in order to complete a partial design and price the work aggressively.

ANSWER: As of this date, the proposal due date remains unchanged.

2. REFERENCE: RFP General

QUESTION: Will the craft be able to park within the jobsite or need to be bused in?

ANSWER: Assuming “craft” is referred to as “craft labor”; Refer to 80KSC018R0016 SF1442 Continuation Clause J-B-84. Associated coordination is the responsibility of the contractor.

3. REFERENCE: RFP General QUESTION: How many days of training/screening will be required to get badged for the site?

ANSWER: Refer to 80KSC018R0016 SF1442 Continuation Clauses H.6, I.14, J-B-72, and J-B-76. These clauses reference badging and training required. SATERN courses available online typically take 1-hour. Course quizzes must be completed related to certain courses to verify retention of content. ELSA Training typically takes 1-hour in person on KSC and must be scheduled by coordination with the Contracting Officer.

4. REFERENCE: RFP General

QUESTION: Will all work be on straight-time or will night work be required?

ANSWER: Refer to 80KSC018R0016 SF1442 Continuation Clause F.2.

5. REFERENCE: RFP General QUESTION: What is the protocol for downtime when a launch is scheduled on-site?

ANSWER: For a launch from LC 39B, refer to 80KSC018R0016 SF1442 Continuation Clause J-B-79 for downtime requirements. For a launch from other than LC 39B, refer to 80KSC018R0016 SF1442 Continuation Clause F.4 for downtime requirements.

6. REFERENCE: RFP General

QUESTION: Is there a concrete batch plant on-site?

ANSWER: No, there is not a concrete batch plant on KSC.

7. REFERENCE: RFP Section L / Appendix 2.

QUESTION: Will all pre-proposal questions and responses be shared with all offerors?

ANSWER: Yes, and any changes or clarifications resulting from bidder questions will be addressed in a solicitation amendment. If the questions are general and do not amend the solicitation, a Question & Answer sheet will be posted.

File details come from the government source that posted it.