Enclosure 2 (Phase-in SOW).pdf
PDF 138 KB Posted
- Attached to
- NASA Sounding Rocket Operations Contract (NSROC) IV - FINAL Request for Proposal Federal contract opportunity
- Solicitation number
- 80GSFC21R0037
About this file
This solicitation requests proposals for the NASA Sounding Rocket Operations Contract IV. The contractor will operate and maintain government-owned facilities at NASA's Wallops Flight Facility in Virginia and White Sands Missile Range in New Mexico. The contractor will conduct sounding rocket launch operations from multiple sites including Poker Flat Research Range in Alaska, Andoya Space Center in Norway, mobile sites in Kwajalein Atoll and Australia, and other potential mobile sites. The phase-in period will last 60 days for the contractor to review requirements and ensure staff have necessary certifications. During phase-in the contractor is expected to submit required plans and manuals within 90 days of award including quality, configuration management, training, IT security, risk management, systems engineering, and other plans. The full contract performance begins 60 days after phase-in start. Comments on the draft solicitation are due within 14 days of its release.
View the file
Other files for this federal contract opportunity
Show all 50
NASA Sounding Rocket Operations Contract (NSROC) IV - FINAL Request for Proposal has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NUMBER 80GSFC21R0037
NASA SOUNDING ROCKET OPERATIONS CONTRACT IV
(NSROC IV)
ENCLOSURE 2
PHASE-IN STATEMENT OF WORK
JULY 2021
Solicitation No. 80GSFC21R0037 NASA Sounding Rocket Operations Contract IV ENCLOSURE 2 – Phase-In Statement of Work
STATEMENT OF WORK
FOR
PHASE-IN ACTIVITIES
NASA SOUNDING ROCKET OPERATIONS CONTRACT IV
1. BACKGROUND INFORMATION
A complete description of the NASA Sounding Rocket Operations Contract IV (NSROC IV) is contained in solicitation number 80GSFC21R0037. The purpose of this Statement of Work
(SOW) is to conduct phase-in activities associated with NSROC IV. Phase-in will be conducted under this contract at the following locations: NASA’s Wallops Flight Facility, Wallops Island, Virginia (WFF) and at White Sands Missile Range, White Sands, New Mexico (WSMR). The contractor shall also be responsible for conducting sounding rocket operations from multiple launch sites, including remote launch campaigns. NASA sounding rocket launch sites include
Poker Flat Research Range in Fairbanks, Alaska (PFRR) and Andoya Space in Andenes, Norway which includes Svalbard. Mobile launch sites include Reagan Test Site in Kwajalein Atoll and
Equatorial Launch Australia (ELA) in Australia. Additional mobile launch sites could be established and utilized during the duration of the NSROC IV contract.
The contractor shall perform phase-in activities leading to readiness to assume full performance of NSROC IV 60 calendar days after phase-in start. During the phase-in period, the contractor shall not be responsible for performance of the effort described in the NSROC IV SOW, Attachment A, of solicitation number 80GSFC21R0037. The Government anticipates awarding a stand-alone firm-fixed price contract to accomplish this goal.
2. PURPOSE AND OBJECTIVES
During the phase-in period, the contractor shall review and become familiar with applicable
NASA regulations, policies, and procedures. The contractor shall take necessary action to submit deliverables and ensure staff has obtained all required licenses and certifications to begin full contract performance 60 calendar days after phase-in start, under the contract awarded pursuant to solicitation number 80GSFC21R0037. The contractor shall use the phase-in period to begin integrating the requirements and deliverables of the contract while obtaining knowledge of the facilities, grounds, and operations required to support the NASA Sounding Rocket Program.
During this period of time the incoming contractor shall work with the Government and the incumbent contractor to ensure a smooth and effective transition.
Upon completion of the phase-in period, the contractor shall be completely responsible for all services and operations required under NSROC.
3. REQUIREMENTS
The contractor shall develop and implement a phase-in plan to be approved by NASA that defines the contractor’s approach too fully and optimally transition management, operations, engineering, technical, and administrative functions from the incumbent contractor. The contractor shall assume full responsibility for all contractual obligations beginning with the effective date of the contract. The contractor shall coordinate and lead the transition team. The phase-in process shall not adversely affect work performed by the incumbent. The contractor is responsible for ensuring continuity of operations, technology development, program planning support, management and administrative support, pending procurements, and fulfillment of all contract deliverables pending from previous contract as well as those on the next contract in order to meet all of NASA’s mission schedules, requirements, and planned costs. A written weekly status report shall be submitted that identifies and summarizes new and ongoing major and critical activities, schedule, progress, risk, and contingency operations. Informal communications, including teleconferences, as needed, shall be conducted by the contractor with the Contracting Officer’s Representative (COR).
During the phase-in period the contractor is expected to begin and/or continue work on meeting contract deliverables required in the contract awarded pursuant to solicitation number
80GSFC21R0037. Table 1 identifies major contract deliverables that shall be submitted after contract effective date.
Deliverable Name Periodic Date or
Specific Due Date Comments
Contract
Ref.
Delivery method
Quality Manual 90 calendar days after contract effective date
Implementation of quality processes for all critical elements
2.1.3.7 Electronic
Copies to COR
Configuration
Management Plan
90 calendar days after contract effective date
Define the process for identification, control, and verification of the development, reconfiguration, and refurbishment of all mission and safety critical systems and processes
2.1.3.8 Electronic
Copies to COR
Training Plan 90 calendar days after contract effective date
How the contractor will identify, maintain, schedule, conduct, and document training, licensing, and certification for personnel and equipment
2.1.3.5 Electronic
Copies to COR
Information
Technology (IT)
Security Plan
30 calendar days after contract effective date
The security measures and program safeguards planned
2.1.3.4 Electronic
Copies to COR
Risk Management
Plan
90 calendar days after contract effective date
How the Contractor will collect, track, and mitigate significant
2.1.3.9 Electronic
Copies to COR
Deliverable Name Periodic Date or
Specific Due Date Comments
Contract
Ref.
Delivery method programmatic and technical risks to the Sounding Rockets
Program
Systems Engineering
Plan
90 calendar days after contract effective date
How the Contractor will ensure the complex subsystems integrated into sounding rocket vehicles and payloads function together to satisfy the objectives of the overall mission
2.1.3.10 Electronic
Copies to COR
4. PERIOD OF PERFORMANCE
The phase-in period for the NSROC will last 60 days beginning on the date the Phase-In purchase order is signed.
End of SOW