This document contains a federal contract solicitation for engineering services and related support to NASA's Goddard Space Flight Center. The MIST II contract will primarily provide engineering support for mechanical systems and instrument systems and technology divisions for the formulation, design, development, fabrication, integration, testing, and operations of space flight and ground system hardware. Key engineering areas include multidisciplinary mechanical, materials, structural analysis, electromechanical design, thermal, contamination coatings, manufacturing, integration, testing, optics, cryogenics, detector systems, lasers, electronics, and microwave technologies. The final RFP is expected to release in January 2020. Offerors must monitor the electronic library for solicitation updates and direct all contractual or technical questions in writing to the email address provided.
View the file
Other files for this federal contract opportunity
Show all 50
MECHANICAL INTEGRATED SERVICES AND TECHNOLOGIES (MIST II) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MIST II Final RFP Questions Rev. 1
34. Enclosure BB, RTO 4, Subtask
(a), pg. 13
The introduction to Subtask (a) states that contractor support shall be required to generate an integrated mission CAD model and generate a deployed CAD model. SOW 1 states that the “Contractor shall develop and maintain an integrated stowed 3D CAD model.” No other CAD models are mentioned in the SOW items.
Please clarify. Is the Contractor required to develop a stowed CAD model, deployed CAD model, or both?
Only “an integrated stowed 3D CAD model of the GROX spacecraft” is required per RTO 4
Subtask (a), SOW 1.
The reference to the deployed CAD model is not required and can be assumed not to be relevant to the
Subtask.
35. Enclosure BB, RTO 3, Subtask
(b), SOW 1, Pg. 11
The RFP states that the Contractor shall support mission level PER and mission-level PSR.
Both of those reviews are outside the stated period of performance for RTO
3.
Will the government please remove or modify this requirement?
This question was answered in Question
#8 of the MIST II
Q&A posted on April
7, 2020.
“The period of performance for RTO
4 has been extended beyond the 30 months of the instruments (as stated on Pg. 13) because it is GROX observatory mission level related.
The additional milestone requirements are listed in RTO 4. The final deliverables and the end of task (EOT) are at the completion of the Mission pre-ship review (MPSR).
All task plans for
RTO 4 subtasks should include mission-level work as described in the subtask SOWs and deliverables up to
MPSR.
36. PPQ Change Change to the MIST II Past
Performance Questionnaire:
As a result of Amendment 1 to the
MIST II RFP, the Government will not take into consideration the response to question 13 (“Ability to meet Small
Business Subcontracting Plan Goals”) of the MIST II Past Performance
Questionnaire.
Correct, the
Government will not evaluate past performance related to question 13 and an
Offerors performance in achieving small business subcontracting goals, since this is a set-aside procurement and a small business subcontracting plan is not applicable to this procurement.
37. Sections I and L Is this contract subject to 52.222-41
Service Contract Labor Standards? If it is, will the Government include FAR
51.222-41 and applicable Wage
Determination?
This question was addressed previously in Draft RFP Q&A
#6. There is no SCA
Wage Determination applicable to this requirement.
38. Section L.29(b)(3)
Government
Pricing Model
The RFP states, “Exhibit 1A individual
GPM-Specified Non-Management
Direct Labor Categories and respective
Direct Labor Hours, populated from
Enclosure CC, are based on a 40-hour work week with no uncompensated overtime.”
Because of this, will the government exclude the use of direct labor rates that account for uncompensated overtime? If not, how will the
Government evaluate uncompensated overtime direct labor hourly rates that could be proposed by Offeror’s to be used in the GPM? Specifically, would the Government increase the hours in
Exhibit 1 to account for the uncompensated overtime factored into the rates? If the Government does not exclude the use of uncompensated overtime in the development of direct labor rates, how will Offerors know
Offerors should propose GPM labor rates assuming no uncompensated overtime hours. The
SEB will evaluate the basis for each
Offeror’s proposed labor rates.
how much, if any, uncompensated overtime was factored into the
“weighted average unburdened hourly rates” specified in Enclosure DD
(Contract Historical Data Direct Labor
Incumbent Rates)?
39. L.28 Subfactor B, B.10;
L.29(b)(14)
Management
Approach - Total
Compensation
Plan (TCP)
The RFP indicates in L.29(b)(14) that
Exhibits 10A and 10B satisfy the TCP requirement at FAR 52.222-46 for the
Non-Significant subcontractors.
Please confirm that Exhibits 10A and
10B also satisfy the TCP requirement for non-significant subcontractors under RFP L.20 NFS 1852.231-71(d) which requires a TCP from all service subcontractors provide, as part of their proposal, the information identified in
(a) through (c) of this provision for cost reimbursement or non-competitive fixed-price type subcontracts having a total potential value of $2M for service contracts submitting certified cost or pricing data.?
That is correct.
This question was previously addressed in question 29 of the
MIST II DRFP
Q&As posted on
1/24/2020.
40. Enclosure DD
Contract Historical
Data Direct Labor
Incumbent Rates
Enclosure DD (Contract Historical
Data Direct Labor Incumbent Rates) contains weighted average unburdened hourly rates that include projected escalation to December 2020. Should these rates be escalated to account for the February 2021 contract start date?
Yes, the rates should be escalated to account for February
2021 contract start date.
41. Enclosure CC
GPM-Specified
Non-Management
Direct Labor
Categories and
Direct Labor
Hours by Site
Location
The Contamination Engineer SME, Contamination Engineer, and Jr
Contamination Engineer labor categories all require a BS or equivalent.
The Senior Contamination Engineer requires a BS. Should the Senior
Contamination Engineer requirement be BS or equivalent, similar to the rest of the job family?
Yes, the Senior
Contamination
Engineer requires a
BS or equivalent.
Enclosure CC will be updated to add BS or equivalent.
42. Enclosure CC
Direct Labor
Categories and
The Electro-Optical SME and the
Electro-Optical Engineer require BS or equivalent however the Sr Electro-
Optical Engineer requires a BS. Should the Senior Electro-Optical Engineer
Yes, the Senior
Electro-Optical
Engineer requires a
BS or equivalent.
Enclosure CC will be
Direct Labor
Hours by Site
Location requirement be BS or equivalent, similar to the rest of the job family?
updated to add BS or equivalent.
43. Enclosure CC
Direct Labor
Categories and
Direct Labor
Hours by Site
Location
The Senior Optical Analyst position description requires a BS or equivalent.
The Optical Analyst requires a BS.
Should the Optical Analyst requirement be BS or equivalent, similar to the
Senior Optical Analyst?
Yes, the Optical
Analyst requires a BS or equivalent.
Enclosure CC will be updated to add BS or equivalent.
44. Section I Should FAR 52.222-17 Non-displacement of Qualified Workers which applies to Service Contract labor be removed in Section I since MIST II does not contain FAR 52.222-41
Service Contract Labor Standards?
No, the Clause
52.222-17 is required for all Service contracts.
45. L.25 (a) (1)
Proposal Format and Organization
The FRFP states: “Offerors shall submit proposals in four volumes as specified below:
I Offer Volume
II Mission Suitability Volume
III Cost Volume
IV Past Performance Volume
Will the Government clarify if one file only is required for each volume or can separate files be submitted? For example, does the Vol II Mission
Suitability volume file include both
Subfactors A and B and all Plans?
Will the Government confirm that the
Subfactors can be separate files from the Phase In Plan, Total Compensation
Plan, Safety and Health Plan, and
Quality Assurance Plan?
Offerors are to submit proposals in accordance with the instructions in L.25.
Proposal Volumes should be consistent with the proposal content chart in
L.25(b). Offerors are permitted to provide content via multiple electronic files, as desired. Mission
Suitability Subfactors and required Plans may be submitted via separate files, as long as all file names and contents are clear and all RFP requirements are met.
46. Answer to
Question 25
Are Offeror’s required to propose mission assurance categories in Cost
Exhibit 2B, Offeror Management and
Administrative Labor although this function is more technical than
Management and Administrative?
Since mission assurance should not be
Because general mission assurance and quality assurance work is covered under a separate
Goddard contract, all
MIST II Mission proposed in RTOs and because there are no missions assurance or quality position descriptions within the GPM
(Enclosure CC) and taking into consideration the QASP requires “the contractor to maintain a QA lead,” how are Offerors to reflect these costs in the
GPM?
Assurance and QA
Lead labor costs should be included in management and administration costs associated with the
GPM.
47. LFT Once we receive our invitation email and register for our account, how long does our account remain active?
Per the instructions in
L.25, Proposal
Delivery, once access is granted to offerors, the site will be open for 7 days or 168 hours.
48. LFT For our subcontractors submitting separate pricing files, should they include the name of the Prime Offeror in the subject line of the Send File tab, or their own company name? Should they include any other information in the subject line to indicate that they are a subcontractor to a submitting Prime?
Subcontractors are encouraged to clearly indicate both the name of the Prime offeror and the subcontractor in the subject line in the send tab. All proposal documents should be appropriately marked with
Prime/Significant
Subcontractor identifiers.
49. LFT Should our follow-up email to the CO listing all the documents that were submitted via LFT contain ONLY the documents that we submitted as the
Prime, or all the document submitted by the Prime and subs that constitute our entire proposal?
Follow-up email to the CO should list all proposal documentation that make up the offeror’s entire proposal.
50. Enclosure BB The RFP response for RTOs must address 4 RTOs that include 10
Subtasks and 73 SOW items, along with other items defined in Section L.
Section L states that the response “must be sufficiently specific, detailed, and complete to demonstrate a clear and full understanding of the objectives…”
No.
To properly comply with the instructions, will the government provide an additional five (5) pages to the Mission Suitability Volume?