Attachment C- Financial M. Reporting FINAL.pdf

PDF 256 KB Posted

Attached to
MECHANICAL INTEGRATED SERVICES AND TECHNOLOGIES (MIST II) Federal contract opportunity
Solicitation number
80GSFC20R0006
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This attachment provides the financial reporting requirements for a NASA contract. The contractor must submit NASA Form 533 reports on a monthly and quarterly basis with detailed direct labor hours and costs by labor category and subcontractor. Variances exceeding 10% between estimated and actual hours and costs require a narrative explanation. Reports are due by the 10th day of each month for the prior month and the 15th day preceding the quarter for the quarterly report. The reports must include direct labor hours and costs by labor category and subcontractor for onsite, offsite, and computer telecommunications facility work, as well as overhead, other direct costs, and fee information. This attachment defines the data elements and formatting requirements for cost and task data files the contractor must submit to NASA's CORTS application on a monthly basis.

View the file

Other files for this federal contract opportunity

Other files attached to MECHANICAL INTEGRATED SERVICES AND TECHNOLOGIES (MIST II), newest first.
File Type Posted
MIST II Amendment 3.pdf PDF
MIST II Amend 2 Summary C.._.pdf PDF
MIST II Amend 1 Summary Changes.pdf PDF
MIST II FRFP QA.pdf PDF
MIST II-Amendment-1.pdf PDF
Final MIST II Questions Rev.2.pdf PDF
ENCLOSURE EE- Cover pg IT Security Management Plan.pdf PDF
Exhibits 2-11 Cover Page FRFP.pdf PDF
Attachment K Government Furnished Property FRFP.pdf PDF
Attachment G-OCI Plan Cover Page FRFP.pdf PDF
MIST II FINAL RFP.pdf PDF
MIST II SF33-14a FINAL.pdf PDF
MIST II Cover Letter on Letterhead.pdf PDF
Attachment D - DD form 254 FRFP.pdf PDF
Attachment B-IDIQ Cost-Type Rate Matrix FRFP.pdf PDF
Exhibits 1A-1C Cover Page FRFP.pdf PDF
Enclosure DD - Contract Historical Data FRFP.pdf PDF
Exhibit 12 - Past Perfomance Cover Page FINAL.pdf PDF
ENCLOSURE CC - MIST II CC - GPM FRFP.pdf PDF
Enclosure AA MIST II QASP FRFP.pdf PDF
Attachment H- Contract Historical Data FRFP.pdf PDF
ENCLOSURE BB - Representative Task Orders Final 02-06-2020-.pdf PDF
Exhibit 12 - Past Performance Questionaire FRFP.pdf PDF
Final MIST II Questions Rev.1.pdf PDF
Final MIST II Questions.pdf PDF
MIST II DRFP 12-16-2019.pdf PDF
Enclosure DD - Contract Historical Data FINAL.pdf PDF
Enclosure AA MIST II QASP FINAL.pdf PDF
Attachment D - DD form 254 FINAL.pdf PDF
MIST II-DRFP GPM Exhibits 1A-1C FINAL.pdf PDF
EXHIBIT 12 Cover Page FINAL.pdf PDF
MIST II COVER LETTER FINAL.pdf PDF
Attachment I PIV Attachment FINAL.pdf PDF
Attachment F- Quality Assurance Plan Cover Page FINAL.pdf PDF
MIST II SF33 DRFP.pdf PDF
Exhibits 2-11 Cover Page FINAL.pdf PDF
Attachment E Safety and Health Plan Cover Page FINAL.pdf PDF
Attachment K Government Furnished Property FINAL.pdf PDF
Enclosure BB Combined RTOs FINAL.pdf PDF
Exhibits 1A-1C Cover Page FINAL.pdf PDF
Attachment A- Statement of Work FINAL.pdf PDF
Attachment B-IDIQ Cost-Type Rate Matrix FINAL.pdf PDF
Attachment L.- IT Security M. Plan Cover Page FINAL.pdf PDF
Attachment K- Government Furnished Property Cover Page FINAL.pdf PDF
ENCLOSURE CC - MIST II CC - GPM FINAL.pdf PDF
Attachment G-OCI Plan Cover Page FINAL.pdf PDF
EXHIBIT 12 - Past Performance Questionaire FINAL.pdf PDF
MIST II DRFP GPM Exhibits 2-11 FINAL.pdf PDF
Attachment H- Contract Historical Data FINAL.pdf PDF
Attachment J - IT Security Applicable Docs List FINAL.pdf PDF
Show all 50

MECHANICAL INTEGRATED SERVICES AND TECHNOLOGIES (MIST II) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

80GSFC20R0006

SEPTEMBER 2019

ATTACHMENT C

FINANCIAL MANAGEMENT REPORTING

REQUIREMENTS

DRFP

CONTRACT TBD

Contract TBD

Attachment C

(06/2014) 2

FINANCIAL MANAGEMENT REPORTING REQUIREMENTS

Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA

Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial

Management Reporting,” dated May 27, 2011, and additional instructions issued by the

Contracting Officer.

a. Level of Detail

An individual 533 Report shall be provided for each Task Order in addition to a cumulative 533 Report summarizing all Task Orders issued. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.

b. Variance Narrative Reporting

In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 10%, (+/- 10%) between the Total

Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total

Cost amount shown in the current month for each individual task order. (For example, the Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)

Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the individual task order, and (3) specific corrective action(s) being taken or to be taken.

c. Distribution

The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.

After the initial report, the NF 533M reports shall be distributed not later than the tenth

(10th) working day following the close of the contractors' monthly accounting period.

The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.

Submit To Contract RA: .txt upload files monthly (see attached sheets) not later than the tenth (10th) working day following the close of the contractors' monthly accounting period.

d. Reporting Requirements

(06/2014) 3

Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:

1. Prime Direct Labor Hours:

Prime Direct Labor Hours – Onsite

(List applicable labor categories)

Prime Direct Labor Hours – Offsite

Prime Direct Labor CTF – Offsite hours

Total Prime Direct Labor Hours

2. Subcontractor Direct Labor Hours:

Subcontractor A Direct Labor Hours – Onsite

Subcontractor A Direct Labor Hours – Offsite

(List applicable labor categories)

Subcontractor A CTF – Offsite hours

Subcontractor B Direct Labor Hours – Onsite

Subcontractor B Direct Labor Hours – Offsite

(List applicable labor categories)

Subcontractor B CTF – Offsite hours

Subcontractor C Direct Labor Hours – Onsite

Subcontractor C Direct Labor Hours – Offsite

(List applicable labor categories)

Subcontractor C CTF – Offsite hours

Total Subcontractors Direct Labor Hours – Onsite

Total Subcontractors Direct Labor Hours – Offsite

Total Subcontractors Direct Labor Hours – CTF Offsite

Total Subcontractors Direct Labor Hours

(06/2014) 4

3. Total Prime and Subcontractors Direct Labor Hours:

Total Prime and Subcontractors Hours – Onsite

Total Prime and Subcontractors Hours – Offsite

Total Prime and Subcontractors Hours – CTF Offsite

Total Prime and Subcontractors Direct Labor Hours

4. Prime Direct Labor Costs:

Prime Direct Labor Costs - Onsite

Prime Direct Labor Costs – Offsite

Prime Direct Labor CTF – Offsite Costs

Total Prime Direct Labor Costs

5. Prime Overhead Expenses:

Onsite Overhead

Offsite Overhead

Total Prime Overhead

Total Loaded Prime Direct Labor Cost

6. Other Direct Costs (ODCs):

a. Subcontracts (list separately, Subcontractor A, B, C, etc.)

To be broken down by Onsite, Offsite, CTF Offsite and a Total for each

Subcontractor

Total Subcontractors Direct Costs

Total Labor Hours = Prime Total + Sub Total

b. Material – broken out by Each Sub

c. Travel – broken out by Each Sub

d. Other (specify) – broken out by Each Sub

(06/2014) 5

Sample: Subcontractor A – Materials

Subcontractor A – Travel

Subcontractor A – Other ODCs

Total Subcontractor A – ODCs

Total ODCs

7. Subtotal (Direct Labor, Overhead & ODCs)

8. G&A Cost

9. Total Estimated Cost

10. Fixed Fee

11. Total Cost-Plus-Fixed-Fee (CPFF)

(06/2014) 6

Requirements for Contractor Cost Import File with Task Value

The contractor cost data for import into the CORTS application will come from the contractor as a comma-delimited text file. The layout of this import file is shown in the table below.

Only one contract can be included in one import file.

Two types of data will be included in the import file: column title and column data.

Column titles must be provided in the first row for each data column in the import file. The name and order of each column title must be exactly the same as illustrated in the “Column

Title in File” column in the table below, with a comma as a delimiter. NOTE: Do not use the names in the “Data Element Name” column as the column titles for the data columns in the file being sent for import.

Column data will be provided beginning with the second row. A data element must be in each column/row in the import file. The order of each column data must be exactly the same as illustrated in the “Column Title in File” column in the table below, with a comma as a delimiter.

All columns are mandatory and must have a value.

The Report Ending Date is in the MM/YYYY format and must be the previous month of the current import date.

Two tables will be updated in CORTS: Subtask and Subtask Detail.

When a task/subtask number exists, the subtask will be treated as an existing subtask and the associated subtask accrued cost amount fields will be overwritten with the corresponding amounts in the import file. The pro-rate rules will then be applied to all subtask detail records

When a subtask number does not exist, a new subtask record and associated subtask detail record will be created with a default value of ‘999999999’ for both fund and WBS.

No deletion will be performed in this process.

(06/2014) 7

Data Element Name Column Title In File Type Size Value

(0-optional, 9-mandatory)

Comments

Report Ending Date ReportDate Text 7 99/9999 Must be the previous month of the current import date.

Contract Number ContractNo Text 10 XXXXXXXXXX NNG07CA18C

Task Number TaskNumber Text 6 XXXXXX Must be the same as it’s defined in CORTS Web.

Subtask Number SubTask Text 6 XXXXXX Must be the same as it’s defined in CORTS Web.

Cumulative Cost CumCost Numeric 13.2 0000000000009.00

Accrued Cost AccruedCost Numeric 13.2 0000000000009.00

Cost Estimate CostEstimate Numeric 13.2 0000000000009.00

Hours Estimated EstHours Numeric 7.2 0000009.00

On Site Hours OnSiteHours Numeric 7.2 0000009.00

Off Site Hours OffSiteHours Numeric 7.2 0000009.00

Task Value TaskValue Numeric 13.2 0000000000009.00