This document contains an infection control risk assessment and federal contract opportunity notice. The infection control risk assessment provides guidance for construction and renovation projects at the Edward Hines Jr. VA Hospital in Hines, Illinois based on the scope of work and risk levels. It outlines infection control requirements and actions for different project classes.

The federal contract opportunity notice is for solicitation 36C25221B0023 to renovate the GU Clinic at the Edward Hines Jr. VA Hospital. The project involves redesigning the layout to add two exam rooms and a dedicated HVAC system, with a period of performance of 570 calendar days. The solicitation will be posted on SAM.gov with a pre-bid conference scheduled. The NAICS code is 236220 and it is set aside for SDVOSB firms. The estimated price range is between $1-2 million, with the solicitation to be issued on July 8, 2021 and bids due on August 12, 2021. The Department of Veterans Affairs Veterans Health Administration VISN 12 is the agency.

View the file

Other files

File Type Posted
36C25221B0023 0007.docx DOCX document
36C25221B0023 0006.docx DOCX document
36C25221B0023 0005.docx DOCX document
RAULAND - BORG. MODEl NCS4010.jpg JPG image
Attachment203.jpg JPG image
Attachment202.jpg JPG image
36C25221B0023 0004.docx DOCX document
Attachment201.jpg JPG image
Abatement survey.docx DOCX document
PD 101 P2 - PLUMBING BASEMENT DEMOLITION PLAN PHASE 2.pdf PDF
PP 101 P2 - PLUMBING BASEMENT PIPING PLAN PHASE 2.pdf PDF
PD 101 P1 - PLUMBING BASEMENT DEMOLITION PLAN PHASE 1.pdf PDF
36C25221B0023 0003.docx DOCX document
PD 100 P1 - PLUMBING EXISTING SUB BASEMENT WASTE PLAN.pdf PDF
RFI 3 1ST FLOOR ELEVATOR LOCATIONS 2021.07.21.pdf PDF
RFI 2 Elevator Locations 2021.07.21.pdf PDF
36C25221B0023 0002.docx DOCX document
S04 sign in sheet 578-15-037 GU Clinic site visit 2021.07.15.pdf PDF
36C25221B0023 0001.docx DOCX document
19) 578-15-037 100_ Combined DWGS Set 2021.03.23.pdf PDF
18) 578-15-037 GU Clinic 100_ Combined Specs 2021.03.23.pdf PDF
11) AE Design Checklist.pdf PDF
Photo 1.jpg JPG image
3) Safety and Health During Construction Activities.pdf PDF
2) Pre-Construction Checklist.pdf PDF
Photo 7.jpg JPG image
7) Interim Life Safety Measures (ILSM).docx DOCX document
Photo 10.jpg JPG image
12) OIT Horizontal Cable Requirements.pdf PDF
Photo 5.jpg JPG image
1) Hines VA Campus Site Plan.pdf PDF
9) Contractor PIV Instructions and Form.pdf PDF
Photo 2.jpg JPG image
Photo 3.jpg JPG image
36C25221B0023_1.docx DOCX document
4) Cutting Welding and Other Hot Work.pdf PDF
15) Floor plans_GU clinic.pdf PDF
0) P01 SOW 578-15-037 Construction 5-27-21 EDITED.docx DOCX document
Photo 9.jpg JPG image
Photo 11.jpg JPG image
10) Contractor Parking.pdf PDF
16) statement of condision.pdf PDF
P07 Wage Determination.txt 7.7.21.txt TXT text file
Photo 8.jpg JPG image
Photo 6.jpg JPG image
13) Fire Protection Code Reviews.pdf PDF
Photo 4.jpg JPG image
5) Above Ceiling Entry and Wall Construction Permits.pdf PDF
6) Pre-Construction Risk Assessment (PCRA).docx DOCX document
14) 200_BASEMENT Floor plan.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Infection Control Risk Assessment for Construction / Renovation Projects

Project Name: GU Clinic Renovation
Project/ Work-Order Number: 578-15-037
Project Planner or Technician:
Extension:
Building Number: 200
Floor(s)/Room(s):
Start date: TBD
Projected completion date: / /
Construction Activity
Infection control risk group

TYPE A: Non-invasive activity, low noise, no vibration

DUST LEVEL Low

GROUP 1: Low office areas, FMS areas, all non-patient care areas.

TYPE B: Small scale, short duration, low-moderate noise, low-moderate vibration

DUST LEVEL: Moderate to High

GROUP 2: Medium All other patient care areas including general medicine floors, ultrasound, Rehab, Occupational Therapy.

TYPE C: Requires more than one work shift to complete, low-moderate noise, moderate–high vibration

DUST LEVEL Moderate to High

GROUP 3: Medium/High ED, Radiology/MRI, admissions, food service areas, laboratories.

TYPE D: Major demolition and construction activities Requiring consecutive work shifts, moderate-high noise, moderate-high vibration

DUST LEVEL High

GROUP 4: Highest Operating rooms, SPS, ICU’s, Outpatient areas, oncology, anesthesia, post anesthetic recovery, all endoscope areas, Pharmacy, Renal Dialysis

Project Class Determination Matrix

Construction Activity ( Risk Level ( Type

“A” Type

“B” Type

“C” Type

“D”

Group 1
I
II
II
III
Group 2
I
II
III
IV
Group 3
I
III
III
IV
Group 4
III
IV
IV
IV

Contractors Actions by Project Class

CLASS

I

1. Execute work by methods to minimize raising dust from construction operations.

2. Immediately replace any ceiling tile displaced for visual inspection.

3. Contain construction waste before transport in tightly-covered containers.

4. Emergency Preparedness training/posting/ID card.

CLASS

II

1. Provide active means to prevent air-borne dust from dispersing into atmosphere.

2. Water mist work surfaces to control dust while cutting.

3. Seal unused doors with duct tap

4. Block off and seal air vents.

5. Wipe surfaces with disinfectant.

6. Contain construction waste before transport in tightly-covered containers.

7. Emergency Preparedness training/posting/ID card.

CLASS

III

1. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.

2. Complete all critical barriers before any work begins.

3. Maintain negative air pressure within work area utilizing HEPA-equipped air filtration units.

4. Provide dust mat at entrance and exit of work area.

5. Contain construction waste before transport in tightly-covered containers.

6. Wet mop or vacuum with HEPA-filtered vacuum before leaving work area.

7. Cover transport receptacles or carts. Tape covering.

8. Emergency Preparedness training/posting/ID card.

CLASS

IV

1. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.

2. Complete all critical barriers before any work begins.

3. Maintain negative air pressure within work area utilizing HEPA-equipped air filtration units.

4. Provide adhesive walk-off mat at entrance and exit of work area.

5. Seal holes, pipes, conduits and punctures appropriately.

6. Vacuum the entire work area with HEPA vacuums or wet mop with disinfectant at the completion of project.

7. Do not remove barriers from work area until completed project is thoroughly cleaned by housekeeping and inspected by the Infection Control Department, Safety Section, and Engineering Service.

8. Remove barrier materials carefully to minimize spreading dust and debris associated with construction.

9. Contain construction waste before transport in tightly-covered containers.

10. Cover transport receptacles or carts. Tape covering.

11. Remove isolation of HVAC system in areas where work was performed at the end of the project.

12. Emergency Preparedness training/posting/ID card.

Risk Assessment for TB exposure: Does the project involve the building’s: a) HVAC Yes No ; b) HEPA filters Yes No____ ; c) Negative Pressure Room (s) Yes No ? If any checked yes, an N95 mask will be required.

Classification ___________

Contractor’s signature (for Projects only)

Project Planner or Technician Signature__________________________

Supervisor signature _________________________________________

Date_________________ FAX to Infection Control x22481 and to Safety x25613 or scan & attach via e-mail to “Hines Infection Control Service”

File details come from the government source that posted it. Updated .