6) Pre-Construction Risk Assessment (PCRA).docx

DOCX document 29 KB Posted

Attached to
Z1DA--578-15-037-(Construction) GU Clinic Renovation
Solicitation number
36C25221B0023
Issued by

About this file

This document contains a pre-construction risk assessment form and a pre-solicitation notice for a federal contract opportunity. The pre-construction risk assessment form is for a project at the Edward Hines Jr. VA Hospital involving the redesign of the GU clinic layout to allow for more efficient patient care, adding two exam rooms and dedicated HVAC system. The form addresses various safety and environmental risks and mitigation plans for the construction project. The related pre-solicitation notice is for solicitation 36C25221B0023 for the GU clinic renovation project at the Hines VA Hospital. The construction period of performance is 570 calendar days with an estimated price range of $1-2 million. The solicitation will be issued on July 8, 2021 with bid opening on August 12, 2021. The North American Industry Classification Code is 236220 and it is set aside for Service-Disabled Veteran-Owned Small Businesses. The agency is the Department of Veterans Affairs Veterans Health Administration VISN 12.

View the file

Other files

File Type Posted
36C25221B0023 0007.docx DOCX document
36C25221B0023 0006.docx DOCX document
36C25221B0023 0005.docx DOCX document
RAULAND - BORG. MODEl NCS4010.jpg JPG image
Attachment203.jpg JPG image
Attachment202.jpg JPG image
36C25221B0023 0004.docx DOCX document
Attachment201.jpg JPG image
Abatement survey.docx DOCX document
PD 101 P2 - PLUMBING BASEMENT DEMOLITION PLAN PHASE 2.pdf PDF
PP 101 P2 - PLUMBING BASEMENT PIPING PLAN PHASE 2.pdf PDF
PD 101 P1 - PLUMBING BASEMENT DEMOLITION PLAN PHASE 1.pdf PDF
36C25221B0023 0003.docx DOCX document
PD 100 P1 - PLUMBING EXISTING SUB BASEMENT WASTE PLAN.pdf PDF
RFI 3 1ST FLOOR ELEVATOR LOCATIONS 2021.07.21.pdf PDF
RFI 2 Elevator Locations 2021.07.21.pdf PDF
36C25221B0023 0002.docx DOCX document
S04 sign in sheet 578-15-037 GU Clinic site visit 2021.07.15.pdf PDF
36C25221B0023 0001.docx DOCX document
19) 578-15-037 100_ Combined DWGS Set 2021.03.23.pdf PDF
18) 578-15-037 GU Clinic 100_ Combined Specs 2021.03.23.pdf PDF
11) AE Design Checklist.pdf PDF
Photo 1.jpg JPG image
3) Safety and Health During Construction Activities.pdf PDF
2) Pre-Construction Checklist.pdf PDF
8) Infection Control Risk Assessment (ICRA).doc DOC document
Photo 7.jpg JPG image
7) Interim Life Safety Measures (ILSM).docx DOCX document
Photo 10.jpg JPG image
12) OIT Horizontal Cable Requirements.pdf PDF
Photo 5.jpg JPG image
1) Hines VA Campus Site Plan.pdf PDF
9) Contractor PIV Instructions and Form.pdf PDF
Photo 2.jpg JPG image
Photo 3.jpg JPG image
36C25221B0023_1.docx DOCX document
4) Cutting Welding and Other Hot Work.pdf PDF
15) Floor plans_GU clinic.pdf PDF
0) P01 SOW 578-15-037 Construction 5-27-21 EDITED.docx DOCX document
Photo 9.jpg JPG image
Photo 11.jpg JPG image
10) Contractor Parking.pdf PDF
16) statement of condision.pdf PDF
P07 Wage Determination.txt 7.7.21.txt TXT text file
Photo 8.jpg JPG image
Photo 6.jpg JPG image
13) Fire Protection Code Reviews.pdf PDF
Photo 4.jpg JPG image
5) Above Ceiling Entry and Wall Construction Permits.pdf PDF
14) 200_BASEMENT Floor plan.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Construction/Safety Risk Assessment

Location of Construction (Bldg. No. /Room No.):200
Project No.: 578-15-037

Project Title: GU Clinic Renovation

Project Coordinator: David Simon
Project Start Date: TBD
Contractor Performing Work: TBD
Estimated Duration:
Supervisor:
Telephone:

Description of Project: The A/E shall conduct a feasibility study of the current conditions and provide recommendations for expansion of GU clinic, with design options/layout for review of end users integrated team’s approval.

Construction Activities

The following projects do not require completion of the Pre-Construction/Safety Risk Assessment form:

1. Painting and installation of new wallpaper in business offices and non-patient areas.

2. Painting in a patient room, if closed for painting and less than 3 square feet of wall area is to be patched and painted. Contractor shall replace the air filter for the room’s air conditioning unit upon completion of painting.

3. Installation of a soap dispenser/needle box/paper towel holder in a patient room

4. Repair of a window blind.

5. Ceiling tile replacement for areas less than ten (10) 2’ x 2’ tiles, if not in business offices and non-patient areas.

6. Ceiling tile replacement for areas less than five (5) 2’ x 2’ tiles in a patient area, if patient is out of the immediate area and clean up can be accomplished before patient returns.

7. Minimal repair of Nurse Call System/TV/Bed/Telephone.

8. Checking or replacing of electric outlet.

9. Replacing a light bulb.

10. Unstopping sink/commode with no water on floor.

11. Unstopping commode when water on floor requires maintenance to have Housekeeping clean area immediately.

12. Repair of a medical gas outlet. (Front Body)

13. Taking air balance measurement readings.

14. Checking air conditioning unit/system.

15. Intermediate jobs that create a moderate amount of dust inside the room with negative air pressure maintained in the room via use of HEPA-equipped unit with minimum 10 ACH and all air discharged outside. The HEPA unit must continue running 2 hours after completion of job and Housekeeping must clean room before the HEPA unit is removed from room. All work and use of HEPA unit must be documented and copies forwarded to Infection Prevention and Safety. NOTE: All duct vents to be sealed off during work!

Yes
No
Will there be noise generated that will impact a department adjacent to, above, or below the construction area?

a. If so, these departments must be notified.

b. How are you going to reduce the noise to an acceptable level?

Yes
No
Will there be vibration generated that will impact a department adjacent to, above, or below the construction area?

a. If so, these departments must be notified each time this type of work will be performed.

b. How are you going to reduce the vibration to an acceptable level?

Policy Memorandum 578-12-138A-076 (R1) April 11, 2014 Attachment A

Yes
No
Are Emergency Procedures in place and posted on each job for accidental events that could

greatly impact Patient Care or Life Safety to the facility?

Typically included items in these procedures are:

· Emergency telephone numbers of key departments.

· A contingency plan describing the location of main valves, switches, and controls.

· A contingency plan for unexpected outages.

Environment

Yes
No
Are any of the following environmental hazards present?

Will hazardous chemicals be used on this project? How will fumes and odors be controlled? Material Safety Data Sheets (MSDS) are required.

Reference: Hazard Communication Program 578-03-001-034 (R-1) dated January 13, 2012

Is asbestos abatement required on this job? If so, notify Safety at the Pre-Construction Meeting.

Reference: Asbestos Management Program 578-03-001-046 (R-1) dated January 30, 2012

Will there be hot work (welding, brazing, soldering) done on this project? If so, then a Hot Work Permit must be posted on the job site. All hot work must have a fire watch assigned to each area while the hot work is being performed.

Reference: Cutting, Welding, and other Hot work Policy 578-03-001-089 (R-2)

Will there be work performed above the ceiling? Will repair/construction activities involve penetration in to existing walls, ceilings, door frames, or doors? If so, must apply for an Above Ceiling Entry and Wall Construction Permit.

Reference: Above Ceiling Entry and Wall Construction Permits 578-07-001-102 (R-2) dated December 27, 2011

Will confined space entry be required on this project? If so, the VAMC Confined Space Entry Program must be followed.

Reference: Confined Space Program 578-12-138S-047 dated May 2, 2012

Utility Failures

Yes
No
Will any of the following systems be out of service at any time during the project?

· Fire alarm (For outages greater than 4 hours, Interim Life Safety Measures must be implemented.)

· Sprinkler (For outages greater than 4 hours, Interim Life Safety Measures must be implemented.)

· Electrical

· Domestic water (For outages greater than 2 weeks, affected domestic water systems will be flushed 5 times the plumbing volume to ensure no residual contaminants i.e. Legionella.)

· Oxygen

· Sewage

· HVAC

* The contractor must provide the COR a minimum of 3 weeks’ notice prior to a scheduled utility outage.

Yes
No

Will there be any work that will require activation of the Interim Life Safety Measures (ILSM) during this project? Other work may require ILSMs, but typical work requiring ILSM implementation are:

· Any construction that impacts an exit or stairs

· Any construction that impacts major breaches in a fire or smoke wall

· Taking the main fire protection system out of service (sprinkler)

· Taking the main fire alarm system out of service

· Taking the “area” fire or fire alarm systems out of service for more than 4 hours within a 24- hour period Implementation of the ILSM requires a fire watch and the ILSM forms to be completed.

Additional Safety Concerns

Yes
No

Will construction affect exit routes from occupied areas adjacent to construction site?

Will the project affect traffic patterns in area? If yes, explain plan.

Will the project involve the deployment of a crane to deliver equipment over occupied facilities?

· Must submit a Lift Safety Plan and the Hines VA Hospital Planned Critical Lift Plan & Crane Permit to the Safety Office for approval a minimum of 3 weeks prior to the arrival of the crane on Hines VA Hospital. Follow the Safety Office’s Lift Safety Plan format and include the following information: crane specifications, crane inspection list, and crane staff training record/certification. Contractors shall maintain and present the following items prior to crane start (items can be kept in crane cab): crane certifications, crane registration, fire extinguisher, and crane operating and safety manual.

The following must be completed prior to any construction activities:

· Construct separation walls prior to project start.

· Fire protection systems must remain intact.

· Provide extra fire extinguishers in work areas.

· Maintain exit lights in work area.

· Maintain negative air pressure in construction area (24/7) throughout project duration.

· Maintain means to monitor and ensure negative pressure via barometer / magnahelix.

· There cannot be any return air from within the construction area to the rest of the building.

· Redirect egress routes; do not allow egress routes to pass through construction areas.

· Provide and maintain “Construction Area-Do No Enter” signs on doors leading into the construction area.

· Maintain up-to-date daily logs and maintain a current Hot Work Permit.

· Provide and install no-slip mats at doors exiting construction area.

· All debris removal must be by covered cart.

· Maintain a clean and orderly work area.

· Determine how, if at all, this project will affect the departments above, below, and adjacent to this project?

Air Quality and Infection Prevention

Construction activity types are defined by the amount of dust that is generated, the duration of the activity, and the amount of shared HVAC systems. Contact Hines VA’s Safety and Infection Prevention Departments if any activity is questionable under these guidelines.

Yes
No

Will dust be generated during this project?

If yes, explain location of and plan for interim dust barriers or attach floor plan with barriers clearly marked.

Is work occurring in an area defined by Infection Control as being at risk for Tuberculosis?

If yes, explain location of and plan for notification of floor staff and PPE for assigned contractors, attach floor plan with barriers clearly marked.

Will debris removal be necessary? If yes, explain plan for debris removal and control.

Negative airflow ventilation and filtration in place and assessed for effectiveness.

Exhaust fans in-place and functioning.

Air supply duct to area closed and HEPA filtration unit in-place and functioning in adjacent patient care area?

Will work be done in a sterile area? If so, how will sterile atmosphere be maintained (to include access in/out of the work area)?

Type A
Inspections and Non-Invasive Activities or Small Scale/Short Duration Activities. (Refer to

Infection Control Risk Assessment for Type Selection)

Yes
No

Removal of ceiling tiles for visual inspection (limited to 1 tile per 50 square feet)

Painting (excludes sanding)

Wall covering—Describe work to be done:

Electrical trim work. Describe:

Minor plumbing. Describe:

Type B
Small Scale, Short Duration Activities that create minimal dust. ( Refer to Infection Control Risk Assessment for Type Selection)
Yes
No

Installation of telephone and computer cabling

Access to chase spaces

Sanding of walls for painting or wall covering (minor repairs—excludes sanding for drywall finishing)

Type C
Any work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies. (Refer to Infection Control Risk Assessment for Type

Selection)

Yes
No

Sanding of walls--drywall finishing

Removal of floor coverings ceiling tiles casework Describe:

Cutting of walls or ceiling. Describe:

New wall construction

Minor ductwork or electrical work above ceilings

Major cabling activities

Activity cannot be completed within a single work shift

Type D
Major demolition and Construction Projects. (Refer to Infection Control Risk Assessment for Type Selection)
Yes
No

Will require heavy demolition or removal of a complete ceiling system

New construction

Contractor Signature
COR / CSO Signature
Safety Signature
Date:
Date:
Date:

Safety Service Recommendations (as needed):

File details come from the government source that posted it. Updated .