8. Abatement IDIQ Liquidated Damages Letter 25 Feb 2026.pdf
PDF 242 KB Posted
- Attached to
- ABATEMENT 2026-2031
- Solicitation number
- Abatement-2026-2031
About this file
This memorandum establishes liquidated damage (LD) rates for the Abatement IDIQ construction contracts administered by the 75th Civil Engineer Squadron (CES) at Hill Air Force Base, Utah. The LD rates apply when contractors exceed the Period of Performance (PoP) specified in task orders and represent the additional administrative and oversight costs incurred by CES personnel to manage contract administration and resolve issues arising from schedule delays.
The total daily LD rate is $1,504 per calendar day, calculated as follows: Project Manager at $94.00 per hour for 8 hours per day equals $752.00, and Supervisor/Engineer at $94.00 per hour for 8 hours per day equals $752.00. These rates are based on the current CES shop rate of $78.00 per hour, and the 75 CES reserves the right to adjust rates as applicable. The memorandum notes that additional facility user and Contracting Office costs may be included as warranted and will be identified at the individual task order level. The document was issued on 25 February 2026 and concurred by Taylor Brimberry, Abatement IDIQ Project Manager, who can be contacted at (801) 586-7094 or taylor.brimberry@us.af.mil for questions.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
75TH CIVIL ENGINEER SQUADRON (AFMC)
HILL AIR FORCE BASE UTAH
CUI
CUI
25 February 2026
MEMORANDUM FOR OL:H/PZIOC
FROM: 75CES/CEOERM
SUBJECT: Liquidated Damage Rates for ABATEMENT IDIQ Contracts
1. The following is to substantiate liquidated damages (LDs) rates incurred by the 75 Civil Engineer Squadron (CES) Office for all projects contracted under the Abatement IDIQ construction contracts to be used when the Period of Performance (PoP) is exceeded by the contractor.
2. These rates represent the additional work required by CES personnel to administer the contract and resolve issues created by projects that have exceeded their allotted PoP. The current shop rate is $78.00 per hour. CES reserves the right to adjust these rates as applicable.
3. In addition, other facility user and Contracting Office costs may be included, as warranted, and shall be identified at the task order level. Total LDs are per calendar day.
Abatement IDIQ, Project Manager $94.00/hour X 8 hours/day $752.00
Abatement IDIQ, Supervisor/Engineer $94.00/hour X 8 hour/day $752.00
TOTAL LDs $1,504
If you have any questions, please contact Taylor Brimberry at (801) 586-7094 or by email at taylor.brimberry@us.af.mil
Concur:
Taylor Brimberry
Abatement IDIQ Project Manager
| 2026-02-25T13:50:53-0700 | |
| BRIMBERRY.TAYLOR.MIKE.1543589558 |