This is a pricing schedule template for an Indefinite-Delivery, Indefinite-Quantity (IDIQ) contract covering abatement, repair, remediation, and minor construction projects at Hill Air Force Base (HAFB) and associated sites in Utah and Wyoming for the period 2026-2031. The schedule is structured as a five-year base contract with an optional six-month extension and requires contractors to provide unit costs for all line items across multiple categories.
The schedule contains three primary line item groups: Line Item Group 1 encompasses removal and demolition services including asbestos-containing materials (ACM), lead-based paint (LBP), insulation, roofing materials, transite pipes, and general demolition work measured in linear feet, square feet, hours, or each; Line Item Group 2 covers replacement and restoration services including pipe insulation, ceiling tiles, flooring, paint repair, and door replacement; Line Item Group 3 includes support services and specialized work such as emergency response, scaffolding, air and clearance sampling, laboratory analysis, licensed professionals (electricians, plumbers, architects), containment systems, heavy equipment rental (lifts, excavators, generators), waste disposal, mobilization/demobilization, certified industrial hygienist services, project management, and general labor. Contractors must enter unit costs for all line items and apply annual escalation rates as percentages. The template automatically calculates yearly totals and contract totals, with all formulas to remain intact. Unit of measure abbreviations include linear feet (LF), square feet (SF), each (EA), hours (HR), days (DA), weeks (WK), square yards (SY), pounds (LB), and jobs (JB).
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2026-2031
| Abatement IDIQ | ||||||||||||||||||||
| Schedule | ||||||||||||||||||||
| Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | 6 Month Extension | |||||||||||||||
| Item # | Item Description | Units | Amount | Unit cost | Totals | Amount | Unit cost | Totals | Amount | Unit cost | Totals | Amount | Unit cost | Totals | Amount | Unit cost | Totals | Amount | Unit cost | Totals |
| Escalation | Escalation | Escalation | Escalation | Escalation | ||||||||||||||||
| LINE ITEM GROUP 1 | 0% | 0% | 0% | 0% | 0% | |||||||||||||||
| A. | REMOVE PIPE INSULATION LT 8" DIA | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| B. | REMOVE PIPE INSULATION GT 8" DIA | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| C. | PIPE FITTINGS LT 8" DIA | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| D. | PIPE FITTINGS GT 8" DIA | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| E. | PIPE SADDLES ANY DIA | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| F. | REMOVE BOILER/TANK INSULATION | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| G. | REMOVE GASKET MATERIAL | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| H. | REMOVE DUCT INSULATION | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| I. | REMOVE VIBRATION COLLAR | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| J. | REMOVE ASBESTOS CEILING TILE | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| K. | REMOVE 12" ACCOUSTICAL TILES | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| L. | REMOVE ACCOUSTICAL TILE ADHESIVE | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| M. | REMOVE HEAVY PAINT | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| N. | REMOVE FIRE SPRAY ON FIREPRROFING | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| O. | REMOVE VINYL FLOOR TILES | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| P. | REMOVE FLOOR TILE MASTIC/ADHESIVE | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| Q. | REMOVE SHEET VINYL FLOOR COVERING | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| R. | REMOVE SHEET VINYL FLOOR ADHESIVE | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| S. | REMOVE ROOF FLASHING LT 300' | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| T. | REMOVE ROOF FLASHING GT 300' | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| U. | REMOVE GALBESTOS PANELS | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| V. | REMOVE TRANSITE PANELS | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| W. | DECONTAMINATE SOIL UP TO 3" | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| X. | REMOVE TRANSITE PIPE LT 12" DIA | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| Y. | REMOVE TRANSITE PIPE GT 12" DIA | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| Z. | DECONTAMINATE FINISHED AREAS | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| AA. | DECONTAMINATE HVAC DUCT WORK | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| BB. | DECONTAMINATE CABLE AND CONDUIT | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| CC. | REMOVE CEILING TRACK | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| DD | WET WIPE CEILING TRACK | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| EE | REMOVE SUB-FLOORING | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| FF | LOCKDOWN | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| GG | PRE-CLEAN TRANSITE ROOFING | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| HH | GLOVE BAG WITH NEGATIVE AIR | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| II | REMOVE ACM LT 10' DIA - WRAP & CUT | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| JJ | REMOVE ACM GT 10' DIA - WRAP & CUT | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| KK | REMOVE LBP/CHEMICAL STRIPPER | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| LL | REMOVE LBP/MECHANICAL | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| MM | REMOVE LBP/WET SCRAPE | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| NN | REMOVE LBP COMPONENTS | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| OO | CLEAN-UP HEAVY METALS | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| PP | CLEAN-UP RODENT/PIGEON EXCREMENT | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| REMOVE MOLD | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | ||
| RR | REMOVE FURNITURE/COMPONENTS | HR | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| SS | REMOVE ROLLED CARPET/SQUARES | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| TT | DRYWALL DEMOLITION | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| UU | LATH/PLASTER DEMOLITION | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| VV | BLOCK/BRICK DEMOLITION | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| WW | REMOVE ACM FUEL LINE | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| XX | REMOVE STEAM LINE RICKWELL | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | |
| YY | GENERAL DEMOLITION | HR | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| LINE ITEM GROUP 2 | |||||||||||||||||||
| A. | REPLACE PIPE INSULATION LT 8" DIA | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| B. | REPLACE PIPE INSULATION GT 8' DIA | LF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| C. | REPLACE PIPE FITTING INSULATION LT 8" | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| D. | REPLACE PIPE FITTING INSULATION GT 8" | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| E. | REPLACE PIPE SADDLES 3-8' DIA | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| F. | REPLACE PIPE SADDLES GT 8" DIA | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| G. | REPLACE BOILER/TANK INSULATION | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| H. | REPLACE DUCT INSULATION | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| I. | REPLACE BATT INSULATION | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| J. | REPLACE BATT INSULATION STICK PINS | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| K. | REPLACE 2' X 2' CEILING TILES | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| L. | REPLACE 2' X 4' CEILING TILES | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| M. | REPLACE WOOD/PLYWOOD SUB-FLOOR | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| N. | CONSTRUCT TEMPORARY HARD WALLS/STRUCTURES | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| O. | PROVIDE PLYWOOD/OSB SHEETING | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| P. | REPAIR PAINT DAMAGE | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| Q. | REPAIR/REPLACE FLOOR TILE | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| R. | REPAIR/REPLACE EPOXY FLOORING | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| S. | REPAIR/REPLACE LVP | SY | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| T. | REPAIR/REPLACE CARPET | SY | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| U. | REPAIR/REPLACE DOOR | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| V. | INSTALL MISC. LABELING | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| LINE ITEM GROUP 3 | |||||||||||||||||||
| A. | EMERGENCY RESPONSE | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| B. | SCAFFOLDING SIMPLE SETUP | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| C. | SCAFFOLDING COMPLEX SETUP | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| D. | ASBESTOS AIR SAMPLES (PERSONAL/BACKGROUND) | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| E. | TAKE AIR CLEARANCE SAMPLES | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| F. | LBP SAMPLES (PERSONNAL/BACKGROUND) | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| G. | LBP CLEARANCE WIPE SAMPLES | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| H. | HEAVY METAL SAMPLES | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| I. | LAB ANALYSIS TEM TESTING | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| J. | LAB ANALYSIS PCM TESTING | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| K. | LAB ANALYSIS FOR LBP | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| L. | LAB ANALYSIS FOR LBP WIPES | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| M. | LAB ANALYSIS FOR HEAVY METAL | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| N. | TCLP LAB ANALYSIS | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| O. | LICENSED ELECTRICIAN | HR | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| P. | LICENSED PLUMBER | HR | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| Q. | LICENSED ARCHITECURAL FIRM | HR | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| R. | 3 STAGE DECON UNIT | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| S. | STANDARD SIZE CONTAINMENT | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| T. | CONTAINMENT GT THAN STANDARD | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| U. | CONTAINMENT ABOVE 20' | SF | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| V. | GENERATOR/COMPRESSOR | WK | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| W. | BACKHOE/EXCAVATOR | WK | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| X. | SCISSOR LIFT (ANY SIZE) | DA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| Y. | SCISSOR LIFT (ANY SIZE) | WK | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| Z. | BOOM LIFT (ANY SIZE) | DA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| AA. | BOOM LIFT (ANY SIZE) | WK | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| BB. | ISOLATED CONSTRUCTION DISPOSAL FEE | LB | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| CC. | MOBILIZATION AND DEMOBILZATION | EA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| DD | CIH: CONSULTING | JB | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| EE | CIH: ON SITE | DA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| FF | CIH: JOB SITE REP. | DA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| GG | SUPERINTENDENT/PROJECT MANAGEMENT | DA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| HH | GENERAL LABOR | HR | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| II | MOBILIZATION: Work at Little Mountain | DA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| JJ | MOBILIZATION: Work at UTTR/Wendover/Boulder WY | DA | 1 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 | 1 | $ - 0 | $ - 0 |
| Yearly Total | $ - 0 | Yearly Total | $ - 0 | Yearly Total | $ - 0 | Yearly Total | $ - 0 | Yearly Total | $ - 0 | Yearly Total | $ - | ||
| Contract Total | $ - 0 | ||||||||||||
| FOR OFFICIAL USE ONLY | W/ 6 Month Extension | $ - 0 |
| NOTES to Contractors: |
| 1. Contractor(s) shall enter a unit cost for every item (Column B) in the spreadsheet. The yearly totals should calculate automatically. **Please DO NOT delete any formulas and double‑check the totals update correctly.** 2. At the top of this excel sheet, contractors shall fill in yellow fields, this includes the yellow escalation box under the unit cost section. Enter your yearly escalation rate (as a percentage), which reflects your expected annual cost increase over the contract term. |
| Units Of Measure (UoM) |
| LF= Linear FooT |
| SF= Square Foot |
| EA= Each |
| HR=Hour |
| DA= Day |
| WK= Week |
| SY=Square Yard |
| LB- Pounds |
| JB- Job |