8-Bidding and Project Timeline - Addendum 1.pdf
PDF 44 KB Posted
- Solicitation number
- TB2708-EX
- Issued by
- Salt Lake County, Salt Lake City, Utah
About this file
This is a bidding and project timeline addendum for the East High School Baseball Field Perimeter Landscape/Xeriscape Project issued by the Salt Lake City School District in Utah. The project requires contractors to provide all labor, materials, and equipment for xeriscape upgrades to the perimeter area of the East High School baseball field. A mandatory pre-bid site visit is scheduled for September 4, 2026 at 9:00 A.M., with attendance required for bid eligibility. The final addendum is posted September 11, with written questions due by 2:00 P.M. on September 16. Bids are due September 23 at 2:00 P.M., followed by board approval on October 6. Phase 1 of the project is available to commence October 7 with completion targeted for October 30, while Phase 2 is available to start July 15, 2027 with full project completion by June 1, 2027.
Bid security equal to at least 5% of the total bid amount is required, with bid bonds or securities to be scanned and uploaded to Bonfire/U3P or emailed prior to the bid deadline. The selected contractor must obtain a 100% Performance/Payment bond and maintain an active S330 or B100 contractor's license or equivalent, with a current copy of the license and any licensure limit documentation required with the bid submission. Liquidated damages of $500.00 per calendar day will apply for completion delays past the project deadline. All questions must be submitted in writing through Bonfire/U3P or asked at the pre-bid site visit, with official answers provided only through the Bonfire/U3P system or authorized addenda issued by the Salt Lake City School District.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Auxiliary Services 995 West Beardsley Place
Salt Lake City, UT 84119
Excellence and Equity: every student, every classroom, every day slcschools.org
EAST HIGH BASEBALL PERIMETER LANDSCAPE/XERISCAPE PROJECT
Bidding and Project Timeline
Aug 26 Post bid on Bonfire/U3P
Sept 4 Pre-bid/Site Walk at 9:00 AM at the project site
Sept 11 Final Addendum posted
Sept 16 Question due date at 2:00 PM
Sept 23 Bid due date at 2:00PM
Oct 6 Board approval
Oct 7 Phase 1 of Project - Available start date for contractor
Oct 30 Phase 1 completion
June 1, 2027 Phase 2 of Project – Available start date for contractor
July 15, 2027 Full Project completion