About this file

This notice announces a Multiple Award Construction Contract solicitation for general construction services at the National Institutes of Health. The National Institutes of Health Office of Research Facilities seeks to award up to sixteen indefinite-delivery, indefinite-quantity contracts for ongoing facilities construction, alterations, repair of buildings and structures. Work may include architectural, mechanical, electrical, plumbing, civil and other construction disciplines. The total program value for all IDIQ contracts is not to exceed $2 billion over an eight-year ordering period.

The solicitation will utilize full and open competition as well as various small business set-asides. Up to twelve awards are reserved for small businesses, including HUBZone, 8(a), and service-disabled veteran-owned small businesses. A pre-proposal site visit is scheduled for a seed project. The anticipated release date of the solicitation is February 11, 2019, with an offer due date of March 14, 2019. Task orders will be on a firm-fixed price basis with all awardees receiving a minimum $1,000 task order.

Amendment 0006

View the file

Other files

File Type Posted
MACC_Awardee_List.docx DOCX document
MACC_Questions-_Amendment_6.pdf PDF
IMG_2462.JPG JPG image
Bldg_4_Rm_115_LAN_Rm.pdf PDF
IMG_2481.JPG JPG image
Example_Door_Security_Detail_Dwg_E1-05_pg_2.JPG JPG image
Amendment_0005.pdf PDF
MACC_Technical_Questions.pdf PDF
IMG_2482.JPG JPG image
0322191318a.jpg JPG image
IMG_2467.JPG JPG image
Bldg_4_2010_Rm_115_LAN_Rm.pdf PDF
0322191310.jpg JPG image
0322191318.jpg JPG image
IMG_2463.JPG JPG image
IMG_2484.JPG JPG image
IMG_2465.JPG JPG image
IMG_2460.JPG JPG image
Bldg_4_1985_Elec.pdf PDF
IMG_2466.JPG JPG image
Bldg_4_2010_2nd_fl_LAN_Rm.pdf PDF
0322191316b.jpg JPG image
B4-1_Line_Dwg..pdf PDF
0322191309a.jpg JPG image
IMG_2464.JPG JPG image
0322191317b.jpg JPG image
IMG_2483.JPG JPG image
IMG_2461.JPG JPG image
0322191315c.jpg JPG image
Amendment_0004_MACC.pdf PDF
Amendment_0003_MACC.pdf PDF
MACC_Contracting_Questions_3-14-19.pdf PDF
NIH_Capital_Project_Forecast.pdf PDF
Amendment_0002_MACC.doc.pdf PDF
Amendment_0001.pdf PDF
MACC_Site_Visit_Signin_Sheets.pdf PDF
NIH_MACC-IDIQ_Site_Visit_Presentation_.pptx PPTX presentation
Attachment_9-Davis_Bacon_Wage_Determination.pdf PDF
Attachment_6-MACC_hhs_subk_plan_template.docx DOCX document
Attachment_2_Past_Performance_Information_Sheet-_11_18.pdf PDF
Attachment_5-NIH_Division_50_Construction_Cost_Template.xlsx XLSX spreadsheet
Attachment_8c_Seed_Project_Bldg_4_Exist_Generator_Tank_Photo.JPG JPG image
Attachment_4-RFI-QUESTION_ANSWER_Sheet.docx DOCX document
Attachment_8_Seed_Project_Bldg_4_Replace_Emergency_Generator.pdf PDF
Attachment_7_Social_Economic_Category_Selection_Sheet.pdf PDF
Attachment_10-Definitions_and_Acronyms.pdf PDF
75N99019R00001.pdf PDF
Attachment_8a_Seed_Project_Bldg_4_Vivarium_Generator_final_Drawings.pdf PDF
Attachment_1_MACC_Construction_Experience_11_18.pdf PDF
Attachment_3_MACC_PAST_PERFORMANCE_QUESTIONNAIRE_for_Offeror.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers X is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to:

1. Change the proposal due date FROM: 2 April 2019 at 2 PM Local TO: 5 April 2019 at 2 PM Local.

2. Revise response to Amendment 0005, Technical Questions #67 and 76 answer 1. Baseline schedule will not be required as part of the MACC IDIQ proposal submission; rather the awardee of the seed project will have to submit as part of the submittal process for that task order award.

/////////////////////////////////////PLEASE SEE PAGE 2 FOR ADDITIONAL CHANGES//////////////////////////////////////////////////

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

2. AMENDMENT/MODIFICATION NUMBER

PAGE OF PAGES

1 2

5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE ORF 7. ADMINISTERED BY (If other than Item 6) CODE ORF National Institutes of Health NIH/ORF/OA Contracting Officer Building 13, Room 2E-47 OD - Office of Research Facilities Building 13, Room 2E-47 9000 Rockville Pike 9000 Rockville Pike Bethesda, MD 20892-5711 Bethesda, MD 20892-5711

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NUMBER

75N99019R00001

9B. DATED (SEE ITEM 11)

02/12/2019

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

(X)

4. REQUISITION/PURCHASE REQUISITION NUMBER 3. EFFECTIVE DATE

03/27/2019

1. CONTRACT ID CODE

3. The below responses replace in entirety the Government’s responses to Amendment 5, Questions 67 and 76 (1):

QUESTION #67 CONSTRUCTION SCHEDULE, SOW PAGE 6-PARA 10A

Paragraph 10.A of the Statement of Work calls for a Baseline Construction Schedule to be submitted with our proposal.

As it will not be possible to get firm delivery dates for the new equipment until after award of subcontracts can we provide a Preliminary Construction Schedule in lieu of a Base Line Schedule?

ANSWER: Baseline schedule will not be required as part of the MACC IDIQ proposal submission; rather the awardee of the seed project will have to submit the schedule as part of the submittal process for their awarded task order.

QUESTION #76 SOLICITATION DOCUMENT

1. Seed project SOW paragraph 10A calls for a baseline construction schedule to be included. Does the Government have any preferred format for the schedule to be provided in, as well as in which Volume and Subfactor it should be included?

ANSWER: MS Project shall be used. Baseline schedule will not be required as part of the MACC IDIQ proposal submission; rather the awardee of the seed project will have to submit the schedule as part of the submittal process for their awarded task order.

4. Incorporate Questions and Answers into the solicitation. Please see attachment to this amendment titled: MACC Questions- Amendment 6. The Government anticipates this to be the last Q&A posted.

File details come from the government source that posted it. Updated .