B05 Amendment A00006 (75H70125R00001).pdf
PDF 362 KB Posted
- Attached to
- PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms in Phoenix, AZ, Maricopa, County
- Solicitation number
- 75H701-25-R-00001
About this file
This is Amendment A00006 to solicitation 75H701-25-R-00001 for PIMC Mechanical Projects at the Phoenix Indian Medical Center, providing responses to pre-proposal inquiries #15-26. The amendment addresses technical questions about manufacturer specifications, above-ceiling obstructions, wall penetrations, exterior pipe support requirements, waste disposal, phasing, medical gas systems, and equipment installation details.
Key clarifications include: concrete pads are required below duct supports, contractors are responsible for waste disposal and MedGas inspection costs, furniture/equipment will remain in place and must be protected during construction, and specific phasing requirements must be followed for isolation rooms. The proposal due date remains February 7, 2025 at 2:00 PM MST. The project involves HVAC system alterations in the Pediatric and Dental Clinics, plus Central Plant improvements including cooling tower valve replacements, medical air system updates, and isolation room modifications.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A00006
KELLY J. BRITTON
Project: PIMC Mechanical Projects: HVAC, Central Plant, & Isolation Rooms (Project #s: PH23PH04H6 & PH22PH03H6)
Amendment A00006 provides responses to pre-proposal inquires #15-26 (6 pages). The proposal due date of Friday, February 7, 2025 at 2:00 PM MST remains unchanged.
Indian Health Service Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104
See Block 6
75H701-25-R-00001
See Block 14
1 7
01/29/2025
12/04/2024
Amendment of Solicitation Amendment A00006 under Solicitation 75H701-25-R-00001 Project PH23PH04H6 & PH22PH03H6, PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00001
PROJECT:
PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
LOCATION: Phoenix, AZ
PROJECT NO: PH23PH04H6 & PH22PH03H6
DOCUMENT
OWNER: Kelly Britton PHONE: (602) 364-5081 & (602) 245-2206 DOCUMENTS:
DATE: 1/29/2025 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference Drawing, Spec, Page COMMENTS POC IHS Approved Response
Amendment A00006 dated 1/29/2025
15. 230900 J01a Specifications - PIMC HVAC - Spec 230900, para 2.1.C. lists
Acceptable Manufacturers as 1. Automated Logic: Automated Logic West, Erik Olson. Phone: (602) 721-8379, Email:
erik.olson@carrier.com
J01c Specifications - PIMC CP and IR - Spec 230900, para 2.1.C.
lists Acceptable Manufacturers as “Automated Logic – Integrated Control Systems (602) 454-6310”
CO/COR Attachments J01a and J01c, Spec Section 230900, paragraph 2.1.C is changed to read as follows:
“C. Acceptable Manufacturers:
1. Automated Logic, a Carrier Company”
No point of contact is provided.
See Addendum 1
16. Mech
Project 1 Above ceiling obstructions
In the field walk there were indications of above ceiling obstructions that would affect the duct work installation as drawn.
Obstructions include but are not limited to steal trusses and engineered wood beams that are nearly the full height of the space between the roof and the drop ceiling.
1. Please provide locations and details of these above ceiling obstructions and direction on how the design will coordinate with these.
2. Or, please provide direction to price the drawings as shown now and coordinate design changes with the EOR once awarded.
COR/BWS Zona field verified the existing conditions during the site visits and coordinated main ventilation air duct routing in coordination with the modular beams.
Zona will work with the successful bidder to resolve routing conflicts for unseen conditions during construction.
Project PH23PH04H6 & PH22PH03H6, PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00001
PROJECT:
PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
LOCATION: Phoenix, AZ
PROJECT NO: PH23PH04H6 & PH22PH03H6
DOCUMENT
OWNER: Kelly Britton PHONE: (602) 364-5081 & (602) 245-2206 DOCUMENTS:
DATE: 1/29/2025 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference
17. Mech Project 1
Full Height Walls
In the field walk there were indications of full height walls in multiple locations throughout the buildings.
1. Is there any drawing showing which walls are full height?
2. Can the walls be penetrated are there any requirements for sealing or fire caulking any penetrations?
COR/BWS 1. No additional drawings are available for review.
2. Where wall penetrations occur, refer to the specifications for sealing.
18. Mech Project 1
Exterior Pipe and Duct Support Foundations
Large portions of the exterior ductwork and VRF piping for the Pediatric Building are routed over dirt, and the plan drawings and details indicate that the use of Dura-Block type supports sitting on the ground.
1. Normally Dura-Block Supports would need to be sitting on a solid/stable surface.
2. What are engineering’s expectations for a base for these supports? Likely solutions are to either extend the equipment pad to include the footprint of the exterior duct and piping, or add individual concrete pads at the base of each individual support.
COR/BWS Provide individual concrete pads below duct support.
Project PH23PH04H6 & PH22PH03H6, PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00001
PROJECT:
PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
LOCATION: Phoenix, AZ
PROJECT NO: PH23PH04H6 & PH22PH03H6
DOCUMENT
OWNER: Kelly Britton PHONE: (602) 364-5081 & (602) 245-2206 DOCUMENTS:
DATE: 1/29/2025 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference
19. Mech Project 1
Material Disposal Requirements
1. Are there any special disposal requirements for any on the existing pieces of equipment, including but not limited to being returned to the owner or stored on-site.
2. Are there any requirements to sort and separate construction waste streams?
3. GC QUESTION: Will construction waste bins be provided at each building by the GC? Our expectation would be to dispose of items in an as demoed condition, and would not plan on cutting or breaking down equipment or materials into smaller components.
COR/BWS Disposal of any materials or equipment should follow any federal, state, and local ordinances.
Construction waste bins are to be provided by the Contractor.
Project PH23PH04H6 & PH22PH03H6, PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00001
PROJECT:
PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
LOCATION: Phoenix, AZ
PROJECT NO: PH23PH04H6 & PH22PH03H6
DOCUMENT
OWNER: Kelly Britton PHONE: (602) 364-5081 & (602) 245-2206 DOCUMENTS:
DATE: 1/29/2025 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference
20. Mech Project 1
Phasing The phasing plan for the pediatric building shows that the south portion of the open office space is included in Phase 1. Please confirm that the phase boundary is actually the existing exterior wall.
COR/BWS The intent is to stub ductwork from the ventilation air unit through the exterior wall into the Phase 2 portion of the building. The approach was to seal all wall penetrations at one time.
Project PH23PH04H6 & PH22PH03H6, PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00001
PROJECT:
PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
LOCATION: Phoenix, AZ
PROJECT NO: PH23PH04H6 & PH22PH03H6
DOCUMENT
OWNER: Kelly Britton PHONE: (602) 364-5081 & (602) 245-2206 DOCUMENTS:
DATE: 1/29/2025 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference
21. Mech Project 1
Construction Access and Management of Existing Office Furniture, Supplies, Etc.
1. Please identify any equipment that will not be able to be removed for the construction effort
2. Please identify who will be responsible for packing, moving, and managing getting the office furniture and supplies out of the construction space and then back into the construction space.
COR/BWS Most of the work in the dental and pediatric building is above ceiling. No equipment or furniture will be relocated. The intent of the project is for the contractor to cover and protect the furniture and equipment while work is being completed.
22. Mech Project 2
Dust collector scope Is there an expectation for contractor to provide any dust collector drops beyond the overhead round taps that are shown.
COR/BWS No.
23. Mech Project 2
MedGas Inspections
1. Which MedGas inspector is servicing this site?
2. Does the owner cover the contract for and costs associated with any MedGas inspections?
3. Please confirm that the Medical Air system can be shutdown long enough to cut over
COR/BWS 1. The contractor is responsible for facilitating the MedGas inspector.
2. No. The contractor is responsible for this cost.
3. The contractor will need to request a shutdown of the medical air in advance. Information will need to be submitted such as how long the shutdown is intended to last.
Project PH23PH04H6 & PH22PH03H6, PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00001
PROJECT:
PIMC Mechanical Projects: HVAC and Central Plant & Isolation Rooms
LOCATION: Phoenix, AZ
PROJECT NO: PH23PH04H6 & PH22PH03H6
DOCUMENT
OWNER: Kelly Britton PHONE: (602) 364-5081 & (602) 245-2206 DOCUMENTS:
DATE: 1/29/2025 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference
24. Mech Project 2
Medical Air Skid Placement Concerns Medical Air Skids cannot be installed in areas that could get flooded. Has the new location in the lower level been vetted against those requirements
COR/BWS There is no specific reference in NFPA 99, 2021 Edition – Chapter 5 – Gas and Vacuum Systems that specifically references flooding for the medical air source.
PIMC has confirmed that there are floor drains installed on the lower level of central plant. PIMC already has measures in place to address any potential flooding occurrences.
25. Mech Project 2
Heat Exchanger Shutdown Please confirm that the Plant can operate without the use of the plate frame heat exchanger. There is no good phasing option that will allow for full time use.
COR/BWS PIMC does not use the heat exchanger during the summer. However, PIMC will still need to know how long the heat exchanger will be offline.
26. Mech Project 2
AIIR Room Phasing Is there any opportunity to have all isolation rooms shutdown at once. With a common exhaust header, phasing without at least a short period with all rooms out of use will be very difficult, if not impossible.
COR/BWS Please reference the phasing plan in the construction documents. Any phasing plan different than what was stated in the construction documents will need to be requested and approved by the COR prior to shut down.