Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

CONSTRUCT FRC HOMEPORT ASTORIA, ASTORIA, OR; Task Order Announcement 70Z05022RABCD0001; Amendment 0009: See Continuation Pages.

USCG FDCC DET SEATTLE

915 SECOND AVE, RM 2664

SEATTLE, WASHINGTON 98174-1011

70Z05022RABCD0001

1 15

04/08/2022

01/20/2022

SOLICITATION NO. 70Z05022RABCD0001 IS AMENDED AS FOLLOWS:

I. CHANGES TO SPECIFICATIONS AND APPENDICES

SPECIFICATIONS SECTION 01110 1.4.2

INSERT:

Section 01110 – 1.4.2 The Contractor may perform in-water dredging activities outside of normal work hours, provided the notification requirements of Section 01800 – 1.19 are met.

SPECIFICATIONS SECTION 01800 1.8.3.1.1

INSERT:

01800- 1.8.3.1.1 Design classification per ASCE 61 Chapter 2 shall be “Moderate”.

SPECIFICATIONS SECTION 01800 1.16.12

INSERT:

01800 - 1.16.12.3 The contractor shall make all arrangements for, and incur costs of installation by the local provider of access cabling and pathways for both data (internet) and voice (telephone) services between the TELCO facilities (street or property point of presence), and TELCO demarcation within the new facility.

01800 - 1.16.12.4 For voice services a minimum of 25-pair OSP telephone cable is required.

SPECIFICATIONS SECTION 01800 1.16.13

INSERT

01800 - 1.16.13.1 For data services an OSP fiber optic cable capable of minimum of 100 Megabytes per second bandwidth is required.

SPECIFICATIONS SECTION 01800 1.16.17.5

INSERT:

01800 - 1.16.17.5 The basis of design product is Bogen speakers, or equivalent. The Contractor provided PA System must be fully compatible with Bogen products used by the US Coast Guard at other shore side Public Address Systems.

Amendment 0009 2

SPECIFICATIONS SECTION 01800 1.16.8

INSERT:

01800 - 1.16.8.1.4 Install one duplex 20A outlet within 36 inches of each planned wireless access point location in the new building above the ceiling.

01800 - 1.16.8.3 Provide and install one APC rack-mounted 1200VA uninterruptible power supply (UPS) at the base of each rack.

01800 - 1.16.8.4 Intrusion detection system (IDS), closed circuit television (CCTV), and cable television (CATV) cabling in interior locations shall be run in conduit or pathway systems separate from telecommunications CAT6A systems. Exceptions are CAT5, CAT5e, CAT6, CAT6A, and fiber optic cabling.

SPECIFICATIONS SECTION 01900 1.4.2

01900 - 1.4.2 The ISCDS provided as Appendix B is applicable to the Permanent Building shown on Appendix A – Sheet A1 & A2.

SPECIFICATIONS SECTION 01800 1.19.1.7

DELETE:

Section 01800 – 1.19.1.7 The dredge area shall be subject to deductions because of excessive over-depth, dredging outside or authorized areas, or disposal of material in an unauthorized manner.

SECTION 1.3.1 TABLE ITEM 5. METERING.

DELETE:

Install building-level meters for electricity, natural gas, and steam; install advanced or standard meters as appropriate.

INSERT:

Install building-level meters for electricity, and steam; install advanced or standard meters as appropriate.

SPECIFICATIONS SECTION 01800 1.11.1.3

DELETE

The domestic water heating system shall be selected based on energy efficiency and a 40-year lifecycle cost comparison. A minimum of 30% of the annual domestic hot water load shall be provided by solar

Amendment 0009 3 collectors if this is lifecycle cost-effective. Life-cycle costs shall include maintenance and replacement costs. A Life Cycle Cost Analysis (LCCA) shall be performed using the latest version of the Building Life Cycle Cost (BLCC) computer program developed by NIST and available for download at:

https://energy.gov/eere/femp/building-life-cycle-cost-programs EISA 2007 and EPACT-2005 requirements shall be incorporated. At a minimum, solar, gas, fuel oil, and electric energy sources shall be compared for the domestic water heating equipment. The LCCA of each system compared shall incorporate systems utilizing renewable energy resources.

INSERT:

The domestic water heating system shall be selected based on energy efficiency and a 40-year lifecycle cost comparison. A minimum of 30% of the annual domestic hot water load shall be provided by solar collectors if this is lifecycle cost-effective. Life-cycle costs shall include maintenance and replacement costs. A Life Cycle Cost Analysis (LCCA) shall be performed using the latest version of the Building Life Cycle Cost (BLCC) computer program developed by NIST and available for download at:

https://energy.gov/eere/femp/building-life-cycle-cost-programs EISA 2007 and EPACT-2005 requirements shall be incorporated. At a minimum, solar, fuel oil, and electric energy sources shall be compared for the domestic water heating equipment. The LCCA of each system compared shall incorporate systems utilizing renewable energy resources.

SPECIFICATIONS SECTION 01800 1.11.1.9

GAS DISTRIBUTION SYSTEM (PERMANENT MWD BUILDING)

The gas distribution system shall be complete with a smart meter connected to the existing main distribution system. The smart meter shall be capable of wireless reporting and shall have a Modbus protocol compatible with Obvius DAS system. See the Civil section for additional smart meter requirements. The smart meter shall comply with the requirements of the local gas company and shall be monitored by the local building's direct digital controls (DDC) system. Metering shall meet all requirements of the Advanced Metering Infrastructure CSTO (03 Jul 2018). Ensure that the main distribution system is adequate for the new gas loads or provide new to suit. Ensure that the gas distribution system is designed in accordance with NFPA 54, local codes, utility company requirements, and installation requirements. Connection to the existing gas distribution system shall be made at the location as shown on the site plan unless directed otherwise by the Contracting Officer. The Contractor shall bear the cost of installation of all utilities. When connecting to existing steel piping systems, provision shall be made to ensure that the integrity of the cathodic protection is not compromised.

Shutoff valves shall be polyethylene (Rockwell) and shall be provided on the exterior of the building. A gas regulator shall be provided at the smart meter. The building service entrance shall be installed at a height sufficient to allow for installation of the gas meter. Installation of gas piping shall be in accordance with ANSI B31.8, Gas Transmission and Distribution Piping Systems. Provide a seismic shutoff valve for the gas distribution system. Gas service shall be sized to accommodate the total connected equipment load.

1.11.9.1 Dirt legs shall be installed at the low points, immediately following reduction from high pressure to medium pressure (at supply points), and at occasional low points throughout the system to provide for blowing out the lines.

Amendment 0009 4

1.11.9.2 Plug valves shall be installed so that interruptions to service can be confined to the building.

1.11.9.3 In addition to providing a main system regulator at the service entrance to the building, provide gas regulators at each piece of gas-fired equipment, sized for the inlet pressure of the equipment being served.

1.11.9.4 Demonstrate that the entire system of gas mains and service lines is gas-tight by performing an air test in accordance with ASME B31.8, Gas Transmission and Distribution Piping Systems. The test shall continue for at least 24 hours between initial and final readings of pressure and temperature.

NOT USED

SPECIFICATIONS SECTION 01800 1.16.11.1.1

1.16.11.1.1 Provide all telecommunications OSP cabling, underground conduits, pathways, and access holes between the new MWD building and pier. OSP pathways and cabling shall conform to the requirements of the TIA-758 standard, National Electrical Code (NEC), the National Electrical Safety Code (NESC). All OSP conduits shall have a minimum diameter of 4 inches.

INSERT:

1.16.11.1.1 Provide all telecommunications OSP cabling, underground conduits, pathways, and access holes between the new facility and applicable outbuildings and piers. OSP pathways and cabling shall conform to the requirements of the TIA-758 standard, the NFPA 70, and the National Electrical Safety Code (NESC). All OSP conduits shall have a minimum diameter of 4 inches. All conduits shall be encased in concrete with a minimum 2500 lb/in² compressive strength and steel reinforcement where vehicular traffic is above the pathway.

SPECIFICATIONS SECTION 01800 1.12.1.2

HVAC systems shall be selected based on a 40-year life-cycle-cost comparison. Life Cycle Cost Analyses (LCCA's) shall include maintenance and replacement costs. Each LCCA shall be performed using the latest version of the Building Life Cycle Cost (BLCC) computer program developed by NIST and available for download at:

http://www1.eere.energy.gov/femp/information/download_blcc.html.

At a minimum, chilled water and DX systems shall be compared for the cooling equipment, and gas, solar, and electric shall be compared for the heating equipment. The LCCA of each system compared shall incorporate systems utilizing renewable energy resources.

Equipment efficiencies shall meet or exceed the requirements of ASHRAE 189.1 Tables C-1 through C- 8.

Amendment 0009 5

HVAC systems shall be selected based on a 40-year life-cycle-cost comparison. Life Cycle Cost Analyses (LCCA's) shall include maintenance and replacement costs. Each LCCA shall be performed using the latest version of the Building Life Cycle Cost (BLCC) computer program developed by NIST and available for download at:

http://www1.eere.energy.gov/femp/information/download_blcc.html.

At a minimum, chilled water and DX systems shall be compared for the cooling equipment, and solar, and electric shall be compared for the heating equipment. The LCCA of each system compared shall incorporate systems utilizing renewable energy resources.

Equipment efficiencies shall meet or exceed the requirements of ASHRAE 189.1 Tables C-1 through C- 8.

SPECIFICATIONS SECTION 01800 1.12.1.10

Laundry dryers shall be vented to the exterior utilizing sheet metal ducting able to compensate for the length of run and weather per manufacturer’s recommendations and IMC. Provide exhaust duct, vent hood, and back-draft damper to prevent wind-driven rain from entering duct. Provide manufacturer’s recommended makeup air for the dryers when in operation. If gas dryers are used, combustion air shall be provided by either direct ducting to the outdoors with an interlocked damper or by means of transfer/supply air from adjacent spaces.

Laundry dryers shall be vented to the exterior utilizing sheet metal ducting able to compensate for the length of run and weather per manufacturer’s recommendations and IMC. Provide exhaust duct, vent hood, and back-draft damper to prevent wind-driven rain from entering duct. Provide manufacturer’s recommended makeup air for the dryers when in operation.

SPECIFICATIONS SECTION 01800 1.19.20

1.19.20 As soon as practicable and no later than five (5) days after the completion of the entire work, the area will be examined by sounding or sweeping or both. Remove shoals and lumps by dragging the bottom or by dredging. However, if the bottom is soft and the shoal areas form no material obstruction to navigation, removal may be waived at the discretion of the Contracting Officer. When areas are found to be in satisfactory condition, the work therein will be accepted as complete. Final volume for payment will be subject to deductions for excessive overdepth, dredging outside of authorized areas, or disposal of material in an unauthorized manner.

Amendment 0009 6

1.19.20 As soon as practicable and no later than five (5) days after the completion of the entire work, the area will be examined by sounding or sweeping or both. Remove shoals and lumps by dragging the bottom or by dredging. However, if the bottom is soft and the shoal areas form no material obstruction to navigation, removal may be waived at the discretion of the Contracting Officer. When areas are found to be in satisfactory condition, the work therein will be accepted as complete. Final volume for payment must not include charges or costs associated with excessive overdepth, dredging outside of authorized areas, or disposal of material in an unauthorized manner.

APPENDIX A

Appendix A – Sheet A-103 and Sheet A-106

INSERT

Appendix A – Sheet A-103 REV2 and Sheet A-106 REV2

Appendix A – Sheet CD101 REVISED Appendix A - Sheet CD100

Appendix A – Sheet CD100 REVISED

Appendix A – Sheet A-102

Appendix A – Sheet A-102 REV

Appendix A – Sheet CU101

Appendix A – Appendix A – Sheet CU101 REV (as attached)

Amendment 0009 7

II. THE FOLLOWING QUESTIONS/PRE-PROPOSAL INQUIRIES WERE RECEIVED IN

RESPONSE TO THE SOLICITATION AND ARE BEING REVISED IN THIS

AMENDMENT 0009:

131. Drawing CU-101 indicates in dashed boxes the two upland locations receiving Ground Improvements. The area where new building(s) are to be constructed has a single underground power ductbank shown. Please confirm if contractors can rely on this to be abandoned? If not, shall a new line (not shown in drawings) be installed to re-establish service to this location using a routing that goes around the building? At this time contractors do not have enough information to determine if any upstream or downstream impacts would occur if this utility were to be removed without re-routing.

Revised Response (Supersedes Response from Amendment 008): Intercept and reroute the existing waterline and power ductbank, serving the existing “L” shaped building, that crosses the NW corner of the “Zone of Ground Improvements Boundary” on CU-101, to avoid this boundary area. Confirm ductbank raceways and cabling in the field. The revised Sheet CD101 file provided with Amendment 008 was mislabeled, and should have been titled, "Appendix A - Sheet CD100 REVISED." Original RFP Appendix A - Sheet CD101 remains unchanged. Replace "Appendix A - Sheet CD101 REVISED" and Appendix A - Sheet CD100 with "Appendix A - Sheet CD100 REVISED" which is attached.

144. Reference Section 01800, Paragraph 1.4.6 and CD101. Drawing CD101 does not show the two existing water lines running north-south within the work area to be removed or abandoned in place. Will these utilities need to be preserved? Can these utilities be abandoned in place with plugs on each end if they are not required to be preserved?

Revised Response (Supersedes Response from Amendment 008): The intent is to abandon the existing water lines after completion of the proposed water main loop system. The existing water mains may need to stay online if adjacent buildings require servicing from these existing mains. The revised Sheet CD101 file provided with Amendment 008 was mislabeled, and should have been titled, "Appendix A - Sheet CD100 REVISED." Original RFP Appendix A - Sheet CD101 remains unchanged. Replace "Appendix A - Sheet CD101 REVISED" and Appendix A - Sheet CD100 with "Appendix A - Sheet CD100 REVISED" which is attached.

215. Reference Drawing sheet CU101 - On drawing CU101 there is, what appears to be, an underground power line feeding the L shaped building/property east of the project site. Please advise if proposers need to relocate this power line as part of this project.

Revised Response (Supersedes Response from Amendment 008): Intercept and reroute the existing waterline and power ductbank, serving the existing “L” shaped building, that crosses the NW corner of the “Zone of Ground Improvements Boundary” on CU-101, to avoid this boundary area. Confirm ductbank raceways and cabling in the field. The revised Sheet CD101 file provided with Amendment 008 was mislabeled, and should have been titled, "Appendix A - Sheet CD100 REVISED." Original RFP Appendix A - Sheet CD101 remains unchanged. Replace "Appendix A - Sheet CD101 REVISED" and Appendix A - Sheet CD100 with "Appendix A - Sheet CD100 REVISED" which is attached.

Amendment 0009 8

III. THE FOLLOWING ANSWERS TO QUESTIONS/PRE-PROPOSAL INQUIRIES ARE

PROVIDED:

13. Your section A on Drawing C-001 shows us placing a 6-foot thick layer of Riprap for the slope revetment repair. We are to utilize the existing riprap in this section and per note 1 place new additional riprap materials to complete this section thickness. Can you tell us what we are supposed to assume for the thickness of the existing riprap thickness, or possibly assign a quantity of riprap for bid assumptions that we all can use for the purchase of the new riprap?

Answer: Per Note 2 on A/C-007, the concept for the revetment repair is provided. Design calculations and construction are to be completed as required per the RFP specifications. Reference Appendices S, T, and U for existing riprap information.

37. Water 01800, Paragraph 1.4.6 and Drawing CU101. There is a callout note at Plan Grid B/3 "Point Of Connection for Pier Water Service" which references Drawing "CU102," which has not been provided. Is this drawing available? Or was the note intended to reference C-008 "Pier & Float Utility Plan" ?

Answer: There is no C-008. There is a CU102 provided with the solicitation. The intent is to reference CU102 Pier & Float Utility Plan.

47. Design/Build Criteria Paragraph 1.19 “Dredging,” and Paragraph 1.19.19 “Deposit in Non-Approved Area” states: “Any material that is deposited elsewhere than in the disposal area shown on the Site Plan will be required to be removed and deposited in the approved area at no additional expense to the Government.” There is no disposal area shown on the Site Plan. Please advise.

Answer: See response to PPI 45 provided with Amendment 06.

66. Plumbing - Per Plan A-103, provide Hazmat Room and Flammable Storage space. These types of spaces typically require a piped or portable eyewash unit, yet none was called for in the body of the RFP. Does the USCG require an emergency fixture servicing these spaces in the corridor, adjacent to the rooms?

Answer: Provide one portable emergency eyewash unit w/ electric immersion heater where indicated on the floor plans. See attached revised floor plan A-103 REV2 & A-106 REV2 issued with this amendment. Install eye wash unit outside the rooms in a niche clear of the egress travel path. Provide floor drain to prevent spill into the travel path.

Amendment 0009 9

67. Plumbing - Per Plan A 1 MWD Plan 3 Stacked washer/Dryer Combo units are indicated. Per RFP Equipment sheets, 2 stacked washer/dryer units and one individual washer and individual dryer is to be provided. Which arrangement is preferred?

Answer: Revised RFP 1800 1.17 paragraph 2.17.79 was provided with Amendment 04; For permanent facilities: “Provide one stacked washer dryer unit, one ADA compliant washer, and one ADA compliant dryer.” For modular facilities: Provide one ADA compliant washer and one ADA compliant dryer.

106. 01800 1.19.1.7 "Specification section 1.19.1.7 - The dredge area shall be subject to deductions because of excessive over-depth, dredging outside or authorized areas, or disposal of material in an unauthorized manner.

Specification section 1.19.20 FINAL EXAMINATION AND ACCEPTANCE - As soon as practicable and no later than five (5) days after the completion of the entire work, the area will be examined by sounding or sweeping or both. Remove shoals and lumps by dragging the bottom or by dredging.

However, if the bottom is soft and the shoal areas form no material obstruction to navigation, removal may be waived at the discretion of the Contracting Officer. When areas are found to be in satisfactory condition, the work therein will be accepted as complete. Final volume for payment will be subject to deductions for excessive overdepth, dredging outside of authorized areas, or disposal of material in an unauthorized manner. Please clarify deductions and how they are determined."

Answer: Paragraph 1.19.1.7 has been removed in its entirety and references to deductions have been removed from paragraph 1.19.20. See revised section included with this amendment. Payment for dredging will be made in accordance with 1.19.6. Should the Government incur fines or costs related to dredging outside authorized areas, dredging deeper than the allowable overdepth, or disposal of dredged materials in an unauthorized manner, the Government may exercise its right to retain payment in accordance with FAR 52.232-5.

122. ASCE 61 What is the ASCE 61 seismic design classification assigned to the pier: high, medium or low?

Answer: Design classification per ASCE 61 Chapter 2 shall be “Moderate”. See inserted Section 01800-

1.8.3.1.1 with this amendment.

169: PLUMBING - Per Plan A-103, provide Hazmat Room and Flammable Storage space. These types of spaces typically require a piped or portable eyewash unit, yet none was called for in the body of the RFP. Does the USCG require an emergency fixture servicing these spaces in the corridor, adjacent to the rooms?

Answer: See response to PPI 66 provided with this amendment.

Amendment 0009 10

170. PLUMBING - Per Plan A 1 MWD Plan 3 Stacked washer/Dryer Combo units are indicated. Per RFP Equipment sheets 2 stacked washer/dryer units and one individual washer and individual dryer is to be provided. Which arrangement is preferred?

Answer: See response to PPI 67 provided with this amendment.

176. TELECOMMUNICATIONS - How many pairs of copper are required from the utility company?

Answer: 25-pair, see Inserted paragraph 1.16.12.4 with this Amendment.

177. TELECOMMUNICATIONS - Is there a fiber requirement (size, capability) from the utility company?

Answer: Minimum 100- megabytes per second, see inserted paragraph 1.16.13.1 with this amendment.

182. Spec 01800 - 1.13.7.2 - Grounding system states to provide a perimeter ground ring around the MWD building. Confirm grounding requirements for modular building option. Also confirm if a ground grid around outdoor electrical equipment is required for personnel protection.

Answer: For the modular buildings, provide grounding electrode systems per the National Electric Code.

Provide ground ring around the pad mounted main switchboard per UFC 3-550-01 as refernced in Section 01800-1.13.1.

183. ES101 - Confirm if the overhead (OH) and underground (UG) routing indicated on the drawing for extending the utility feed for the pad mounted transformer are for basis of design (prescriptive criteria) or for reference. Is there a requirement for the combination of OH and UG as indicated on the drawing, or can alternate routes be considered so long as the service requirements are met?

Answer: Routing may be either overhead or underground along the south side of the project area.

Overhead routing shall provide a minimum of 30 feet clearance above finished grade per

01800.1.13.2.2. Provide underground routing from the south side of the project area to the service equipment and facilities as indicated on drawing ES101.

205. Marine - Section 01800 1.8.7 Floating Docks – Currently, it is noted that the minimum length of pontoon segment is noted as 30 feet. However, this minimum length will likely cause segments to exceed the 140,000 lb. maximum weight. Please consider revising the minimum segment length to 20 feet or 25 feet to allow for more flexibility in construction and competition amongst suppliers.

Answer: See response to PPI 72 provided with Amendment 05.

Amendment 0009 11

210. 01800 – 1.19 Dredging / Appendix K – Environmental Assessment Report - Section 01800 1.19.17 directs that the contractor shall dispose of dredged materials only at approved sites.

The Preliminary Draft EA provided in the RFP as the basis for bid (App. K, 2.1.8.4 “Dredging and Disposal”, p. 14) states that “Disposal site(s) TBD (in-water sites or proposed/available upland disposal sites)” are to be utilized. The Preliminary Draft EA also states that “Dredged materials will be disposed of at an existing disposal site in the Columbia River, whereas the Sediment Characterization Report, also provided in the RFP, indicates that the ODMS located at the Mouth of the Columbia River Deep Water Site may be used. Please confirm the location of the offshore and onshore disposal site(s), and the material capacity of each to be used as the basis for bid.

Answer: See response to PPI 45 provided with Amendment 06.

224. 01801 – 2.6.2 - Section 2.6.2 of Specification 01801 specifies sheet vinyl flooring and resilient base throughout the modular buildings. Please confirm this requirement supersedes any floor finish requirements specified in the Space Criteria Sheets in Appendix B.

Answer: Follow Specification 01801-2.6.2 for flooring in the Option 1 modular buildings. The floor finish requirements from Appendix B are intended for the Option 2 Permanent Building. See Section 01800-01900-1.4.2 inserted with this Amendment.

226. CU101 - 01801 – 2.9.7 - CU101 shows to connect to existing natural gas line to provide gas to modular building. Specification 01801 Modular Facilities 2.9.7 reads that natural gas will not be required at Modular Facilities. Please confirm that natural gas is to be provided to modular building per CU101. Additionally, please provide point of contact information for the gas utility company serving the USCG Astoria base.

Answer: Natural gas is not required on this project. See revised Appendix A - Sheet CU101 REV2, Revised Spec Section 01800 - 1.3.1, 1.11.1.3, 1.11.9, 1.12.1.2, & 1.12.1.10 with this amendment.

231. 01_Appendix A_6135995_RFP - Drawings Sheet CU101: We reached out to NW Natural regarding costs to tie into the existing natural gas main shown on drawing CU101. They informed us that there is not a gas main located as shown on the drawings. There is no gas service at all on the west side of the railroad tracks. They noted that the nearest gas main to supply the project would come up from US30 to the south, cross railroad right-of-way, and up Railroad Ave. They also noted that they had estimated installing service for another property near the project site and the cost was going to be around $200,000. Please provide guidance as to where proposers should obtain gas service and update the existing gas service shown on drawing CU101 appropriately.

Answer: Natural gas is not required on this project. See revised Appendix A - Sheet CU101 REV2, Revised Spec Section 01800 - 1.3.1, 1.11.1.3, 1.11.9, 1.12.1.2, & 1.12.1.10 with this amendment.

Amendment 0009 12

240. Confirm that contaminated soil during the deep foundations (soil improvement) work can remain onsite.

Answer: Reference Appendices of Appendix D Geotechnical Report for additional information on field explorations, soil testing results, and the Phase II environmental Site assessment report.

The Contractor is not prohibited from repurposing soil as structural fill, if approved by the Contractor's Designer of Record and in accordance with all applicable regulatory requirements. The contractor must provide protection measures to prevent the mass soil mixing material from running into water.

241. RFP Specification 1.4.10.2 on sheet 72 of 1519 calls out for “…pavement shall be the greater of the geotechnical engineer‘s pavement design recommendation or existing pavement section being replaced.”

The existing concrete sections vary from 7”-16” in depth per borings attached with this TOA. Would the Government be accepting of a concrete section matching the lowest thickness (7”) given this section meets all UFC 3-250-01 “Pavement Design for Roads and Parking Areas” criteria? If not acceptable, will the Government confirm they expect concrete pavement patch back matching the existing section, of up to 16” thickness?

Answer: See response to PPI 225 provided with Amendment 08.

243. A-102 - 01800 – 1.7.1.4.1: Should pricing for insulation minimum R-Values be based on Zone 4 within 2019 ASHRAE 90.1 as listed within the RFP on drawing A-102? On the contrary, 1800 1.7.1.4.1 references ASHRAE 189.1 for building insulation. 2020 and 2017 ASHRAE 189.1 include insulation values which are more stringent than 90.1. Please confirm if ASHRAE 90.1 or ASHRAE 189.1 is required for pricing building insulation values

Answer: Provide insulation per ASHRAE 189.1 as required in RFP section 1800 1.7.1.4.1. The Energy Code Notes from Appendix A - Sheets A-102 and A-103 have been removed with this Amendment.

244. PPI #124 of AMD 0004 requested for work days / hours to be extended during the in-water construction season. The PPI response strictly followed the RFP criteria noted in 01110 – 1.4 (Work Hours 0730 – 1700, Mon thru Fri. NO work on weekends or Federal Holidays w/o Contracting Officer Approval.) Assuming only regular work hours during the in-water work seasons would represent significant costs and prolonged schedule durations. Can you clarify / confirm if the Contracting Officer will approve work taking place in multiple shifts outside of regular work hours? There are several in-water activities that would benefit both in cost and schedule if they could work in a 24/7 schedule, or at least beyond the work hours noted in the RFP. Please review and advise.

Answer: The Contractor may perform in-water dredging activities outside of normal work hours, provided the notification requirements of Section 01800 – 1.19 are met. See addition of Section 01110-

1.4.2 with this Amendment.

Amendment 0009 13

245. 01800 – 1.4.6.2- Part 1.4.6.2 requires that the water pipe under piers and at transition points from gangways to floats and piers is to be insulated along with a stainless steel jacket and heat traced. The standpipe is a dry standpipe. We assume that the insulation and heat trace is applicable to the domestic water piping and not the firewater standpipe. Please verify.

Answer: Confirmed. The insulation and heat trace is applicable to the domestic water piping and not the fire standpipe system (since the standpipe system is a dry system).

246. There is still some clarification needed as to where ground improvement costs should be allocated.

PPI #07 was submitted requesting a CLIN location for the costs for ground improvements for buildings under option item 1 or 2. US Gov response to this PPI stated only “See Section 1800-1.5.3.”

1800 para. 1.5.3 states that “bidding purpose, the Contractor shall assume that ground improvements are required at the site due to the presence of liquefiable soils”. But does not specifically call out anything about where costs are allocated between base bid or options.

It is understood transformed pad and abutment ground improvements are part of the base bid. The question bidders need answered, to ensure costs are allocated to either a base award or option items that may or may not be awarded are:

Should all ground improvements for both abutment, building, and transformer pad, with exception of Zone 2/3 which are specifically related to Option Item 004, be placed in Base bid?

-or- Are the ground improvements specific to the locations for the temporary or permanent buildings, Option 1 or 2 respectively, to be priced with the structures in Option item 1 and 2?

Answer: Ground Improvements, with the exception of Zone 2/3, are part of the Base Bid. See response to PPI 07 from Amendment 05.

247. RFI 99 of Amendment 0006 clarified that the 2019 revision of ASHRAE 90.1 shall be used as part of the bid proposal. This ASHRAE edition calls out for control of electrical receptacles. Please confirm if this is desired, and if so, advise on what specific equipment will require controlled wall outlets from wall switches or motion sensors.

Answer: Provide control of receptacles per ASHRAE 90.1 in office spaces as required by RFP Section 01800-1.13.5.1.5.

248. RFP Specification 1.4.10.2 on sheet 72 of 1519 calls out for “…pavement shall be the greater of the geotechnical engineer‘s pavement design recommendation or existing pavement section being replaced.”

The existing concrete sections vary from 7”-16” in depth per borings attached with this TOA. Would the Government be accepting of a concrete section matching the lowest thickness (7”) given this section meets all UFC 3-250-01 “Pavement Design for Roads and Parking Areas” criteria? If not acceptable, Amendment 0009 14 will the Government confirm they expect concrete pavement patch back matching the existing section, of up to 16” thickness?

Answer: See response to PPI 225 provided with Amendment 08.

249. Site Gas – we have reached out to the local gas provider regarding costs for the gas line install per the RFP documents. The local gas provider has communicated that the existing gas line shown on the drawings for tie-in to the new gas line no longer exists. As such, the new line will require a longer run for tie-in to an existing line. The cost provided by the local gas provider are approximately $250,000.

Please advise if the GOV remains committed to installing this gas service.

Answer: See response to PPI 231 provided with this amendment.

Amendment 0009 15

S30
Amendment 09 Continuation Sheet Final