Section J-02 Design and Readiness Review Requirements and Criteria_A00007.pdf

PDF 293 KB Posted

Attached to
Homeland Security Cutter - Light Icebreaker (HSC-L) Solicitation
Solicitation number
70Z02326R93280004
Issued by
Not on record

About this file

This document is a Design and Readiness Review Requirements and Criteria attachment for the USCG Homeland Security Cutter – Light Icebreaker (HSC-L) program, establishing entrance, demonstration, and exit criteria for major technical reviews throughout the design and production phases. The document defines requirements across four primary review gates: Preliminary Design Review (PDR), Critical Design Review (CDR), Production Readiness Review (PRR), and Test Readiness Review (TRR). Each review phase specifies detailed entrance criteria that must be met before proceeding, activities to be conducted during the review, and exit criteria that demonstrate successful completion and readiness to advance to the next phase.

The PDR entrance criteria require presentation of technically feasible design changes, a balanced and internally consistent design baseline, incorporation of vendor-furnished information for mission-critical equipment, submission of contract deliverables per established timelines, and engineering descriptions across 22 technical domains including general arrangement, structures, propulsion, stability, electrical systems, fire detection, communications, and human factors. CDR entrance criteria build on successful PDR completion and require mockup development, incorporation of Coast Guard feedback, speed-power analysis completion, risk documentation in a CRMP database, and demonstration of production facility preparation activities. PRR entrance criteria mandate successful CDR closure, establishment of a Developmental Configuration Baseline, acceptance of 3D Product Model and construction drawings for the initial 90-day production phase, and updated facility preparedness assessments. TRR entrance criteria require completion of construction, grooming of all systems, full integration under configuration control, and approval of all test plans, procedures, and test environments. Table 1 provides a comprehensive matrix of contract data requirements (CDRLs) mapped to each review phase, specifying which deliverables are required at PDR, CDR, PRR, and TRR milestones.

View the file

Other files

File Type Posted
Section J-07 Pricing Schedule_A00008.xlsx XLSX spreadsheet
RFP_70Z02326R93280004_HSC-L_Conformed_A00008.pdf PDF
SF-30 Amendment A00008.pdf PDF
Attachment 5 - Government Responses to Solicitation Questions_A00008.pdf PDF
Section J-54 Hose Log_A00007.xlsx XLSX spreadsheet
Section J-08_Insurance_Spares_List_A00007.pdf PDF
Section J-07 Pricing Schedule_A00007.xlsx XLSX spreadsheet
Section J-01 HSC-L System Specification_A00007.pdf PDF
Section J-09B Tech DataTables_A00007.xlsx XLSX spreadsheet
SF-30 Amendment A00007.pdf PDF
RFP_70Z02326R93280004_HSC-L_Conformed_A00007.pdf PDF
Attachment 4 - Government Responses to Solicitation Questions_A00006.pdf PDF
SF-30 Amendment A00006.pdf PDF
Section J-13I DD Form 1692 Engineering Change Proposal.pdf PDF
Section J-13D ATCH 085-002 3D TDP.pdf PDF
Section J-13B ATCH 083-001-2 ESWBS WORKBOOK.xlsx XLSX spreadsheet
Section J-09B Tech Data Tables.xlsx XLSX spreadsheet
Section J-13H COMDTINST M10360_3D Colors and Coatings Manual.pdf PDF
Section J-09A Technical Data Rights Table Instructions.pdf PDF
Section J-13L COMDTINST 9085_1D Naval Engineering Computer Aided Design Standards.pdf PDF
Section J-13E SFLC Std Spec 6310 Requirements for Preservation of Ship Structures.pdf PDF
Section J-13M COMDTINST M5260_6A Directives System Program.pdf PDF
Section J-13K ATCH 085-005-2 2D TDP.pdf PDF
Section J-13J ATCH 086-001 2025-04-04 PROMULGATION FRONT MATTER WITH COPYRIGHT (IPW).pdf PDF
Section J-13C ATCH 083-004-1 PPL Template.xlsx XLSX spreadsheet
Section J-06 Notice for Filing Agency Protest.pdf PDF
Section J-10 Section 508 Contract Language for HSC-L.pdf PDF
Section J-11 MIL-HDBK-61B.pdf PDF
Section J-52 Outfitting List.pdf PDF
Section J-07 Pricing Schedule_A00005.xlsx XLSX spreadsheet
Section J-13A ATCH 083-001-1 MECL.xlsx XLSX spreadsheet
Section J-08_Insurance_Spares_List_A00005.pdf PDF
SF-30 Amendment A00005.pdf PDF
Section J-01 HSC-L System Specification_A00005.pdf PDF
Section J-13G COMDTINST M5260_6A Management of Scientific and Technical Information (STINFO).pdf PDF
Section J-53 Sand Chart Template_A00005.xlsx XLSX spreadsheet
RFP_70Z02326R93280004_HSC-L_Conformed_A00005.pdf PDF
Section J-02 Design and Readiness Review Requirements and Criteria_A00005.pdf PDF
Section J-13N DD Form 1694 Request for Deviation-Waiver.pdf PDF
Section J-13F SFLC Std Spec 6341 Interior Deck Covering.pdf PDF
SF-30 Amendment A00004.pdf PDF
Attachment 3 - Government Responses to Solicitation Questions_A00003.pdf PDF
RFP_70Z02326R93280004_HSC-L_Conformed_A00003.pdf PDF
SF-30 Amendment A00003.pdf PDF
Attachment 2 - Government Responses to Solicitation Questions_A00002.pdf PDF
SF-30 Amendment A00002.pdf PDF
RFP_70Z02326R93280004_HSC-L_Conformed_A00002.pdf PDF
Section J-02 Design and Readiness Review Requirements and Criteria_A00001.pdf PDF
SF-30 Amendment A00001.pdf PDF
RFP_70Z02326R93280004_HSC-L_Conformed_A00001.pdf PDF
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCG HOMELAND SECURITY

CUTTER – LIGHT ICEBREAKER

(HSC-L)

DESIGN AND READINESS REVIEW

REQUIREMENTS AND CRITERIA

ATTACHMENT J-2

Version: [A00007]

Prepared by:

COMMANDANT (CG-SEA-A8)

UNITED STATES COAST GUARD STOP 7800

2703 MARTIN LUTHER KING JR AVE SE

WASHINGTON DC 20593-7800

Distribution Statement A: Approved for public release; distribution is unlimited.

Homeland Security Cutter – Light Icebreaker (HSC-L) 70Z02326R93280004 Readiness Review Requirements and Criteria ORIG

Scope: This attachment defines the entrance, demonstration and exit criteria for the major Technical Reviews for the HSC-L program.

A. Preliminary Design Review (PDR)

A.1 The Contractor shall demonstrate successful completion of the following Entrance Criteria:

A.1.1 Present any proposed changes to the contract design that are technically feasible and consistent with a product that can meet the HSC-L System Specifications.

A.1.2 The revised contract design is balanced with internally consistent and convergent design characteristics of the Principal Dimensions, Arrangements, Area / Volume, Structures, Weight, Stability, Propulsion Power and Electric Power from a common design baseline with minimal risk of subsequent adverse changes.

A.1.3 The revised contract design incorporates vendor furnished information (VFI) for equipment identified for mission critical functional areas.

A.1.4 [A00001] Contract deliverables per Table 1 have been submitted to the Government per Attachment J-4 CDRL timeframe.

A.1.5 Engineering descriptions of the ship system and subsystems and associated architecture are complete, as demonstrated by Government concurrence of the design changes to the following subjects:

A.1.5.1 General arrangement

A.1.5.2 Hull and deckhouse structure and scantlings

A.1.5.3 Propulsion system and bow thruster, including resistance, powering, and maneuvering (i.e., station keeping for ATON)

A.1.5.4 Control surfaces, rudder sizing, and turning performance

A.1.5.5 Weight estimate, intact stability, damage stability, and towing stability

A.1.5.6 Details of the production design for the electrical power generation, storage, and distribution system

A.1.5.7 Interior lighting system

A.1.5.8 Exterior lighting system

A.1.5.9 Pilothouse arrangement and seating

A.1.5.10 Machinery space(s) arrangement

A.1.5.11 Details of the heating, ventilation, and air conditioning systems

A.1.5.12 Mast and antenna configuration

A.1.5.13 Fire detection and suppression system

A.1.5.14 Installation details of the electronics, communications, and navigation systems

A.1.5.15 Propulsion controls, steering system, bow thruster, and autopilot

A.1.5.16 Human-machine interfaces

A.1.5.17 Aft deck arrangement including ATON and towing tackle equipment, configuration and controls

A.1.5.18 Galley, berths, and habitability details.

A.1.5.19 Human factors engineering for operators and maintainers

A.1.5.20 System reliability

A.1.5.21 Noise and vibration

A.1.5.22 Coating system, including a preservation plan in accordance with SFLC Std Spec 6310.

A.1.6 Verification Planning efforts have been established, to include:

A.1.6.1 Modeling and Simulation support efforts.

A.1.6.2 Test and Integration approach.

A.1.6.3 Inspection and Certification approach.

A.1.7 Design margins and service life allowances are documented and are in compliance with the HSC-L System Specifications.

A.1.8 Requests for Action (RFAs), Action Items, and deficiencies documented from prior review (i.e. kick-off meeting) have been resolved.

A.2 During the PDR, the Contractor shall:

A.2.1 Conduct an IMS Review

A.2.1.1 The Contractor shall provide a description of the process by which the IMS is assembled and updated, logical linkages are established, resources are applied, and the level of fidelity for the various types of work contained in the IMS, including the following efforts:

A.2.1.2 Design and Production schedule (Including PDR, CDR and PRR acceptance of contract deliverables by the Government)

A.2.2 Discuss any System Software and Cyber-related Requirements updates

A.2.3 Integrated Logistics Support (ILS) strategy development plan of action with milestones.

A.2.4 Human Systems Integration (HSI) and Human Factors Engineering (HFE), and System Safety approach and planning.

A.2.4.1 Report on approach and planning for meeting manning constraints.

A.2.4.2 Report and review HSI efforts and risks by each domain, including usability.

A.2.5 Risk assessment that includes descriptions of the top 10 critical risks, including details and status of the proposed risk mitigation actions.

A.2.6 The 3D Product Model review process is established, and reviews have been conducted, including:

A.2.6.1 The 3D Product Model Working group has been founded.

A.2.6.2 The first model review has been held.

A.2.6.3 The model data structure and elements are established.

A.2.6.4 A method for determining the model’s percent complete is agreed upon and implemented.

A.2.6.5 The method for exchanging and resolving Government comments is established.

A.2.6.6 The schedule for 3D Model System reviews is established and review timelines agreed.

A.3 The PDR will be closed after the Contractor provides data and narrative in sufficient detail for the Government to verify that the Contractor has met the following Exit Criteria:

A.3.1 The revised design is a complete engineering description of a ship that meets the requirements of the HSC-L System Specification in its entirety.

A.3.2 The design is producible per the Contractor’s build strategy.

A.3.3 The design’s equipment, systems, and subsystems incorporate proven technology reflecting a high level of maturity proven in a representative HSC- L operating environment with demonstrated functional performance.

A.3.4 HSI analyses to confirm the following:

A.3.4.1 The design supports safe, timely, and efficient human performance to meet mission needs.

A.3.5 The Management Plan and IMS are achievable.

A.3.6 Design tools and engineering resources are available and sufficient to support design maturation and production.

A.3.7 Required Delivery Dates (RDD) and labor support for GFE and GFI are acceptable.

A.3.8 Long Lead Time Material (LLTM) items are identified with in-yard need dates per Attachment J-7 “Pricing Schedule”

A.3.9 Closed Action Items are documented and acknowledged by both the Contractor and Government.

A.3.10 All supplemental entrance criteria contract deliverables listed in A.1.4 shall be either accepted or approved, as applicable.

B. Critical Design Review (CDR)

B.1 The Contractor shall demonstrate successful completion of the following Entrance Criteria:

B.1.1 PDR has been successfully completed.

B.1.2 Action items from previous reviews identified for completion prior to CDR have been successfully addressed and closed out, or a resolution plan has been defined by the Contractor and determined by the Government to be sufficient to proceed with CDR.

B.1.3 Mockups have been developed and Coast Guard feedback incorporated into the design.

B.1.4 [A00001] Contract deliverables per Table 1 have been submitted to the Government per Attachment J-4 CDRL timeframe.

B.1.5 Engineering descriptions of the ship system and subsystems and associated architecture are complete, as demonstrated by Government concurrence of any design changes to the following subjects:

B.1.5.1 General arrangement

B.1.5.2 Hull and deckhouse structure and scantlings

B.1.5.3 Propulsion system and bow thruster, including resistance, powering, and maneuvering (i.e., station keeping for ATON)

B.1.5.4 Control surfaces, rudder sizing, and turning performance

B.1.5.5 Weight estimate, intact stability, damage stability, and towing stability

B.1.5.6 Details of the production design for the electrical power generation, storage, and distribution system

B.1.5.7 Interior lighting system

B.1.5.8 Exterior lighting system

B.1.5.9 Pilothouse arrangement and seating

B.1.5.10 Machinery space(s) arrangement

B.1.5.11 Details of the heating, ventilation, and air conditioning systems

B.1.5.12 Mast and antenna configuration

B.1.5.13 Fire detection and suppression system

B.1.5.14 Installation details of the electronics, communications, and navigation systems

B.1.5.15 Propulsion controls, steering system, bow thruster, and autopilot

B.1.5.16 Human-machine interfaces

B.1.5.17 Aft deck arrangement including ATON and towing tackle equipment, configuration and controls

B.1.5.18 Galley, berths, and habitability details.

B.1.5.19 Human factors engineering for operators and maintainers

B.1.5.20 System reliability

B.1.5.21 Noise and vibration

B.1.5.22 Coating system, including a preservation plan in accordance with SFLC Std Spec 6310.

B.1.6 Government concurrence that the 3-D Product Model is at a maturity level that allows for verification of the following:

B.1.6.1 Arrangements meet HSC-L Design Artifacts and System Specification requirements, and that there are no equipment interferences.

B.1.6.2 Virtual walkthroughs and analyses to confirm that HSI requirements are met by the design.

B.1.7 The design incorporates Vendor Furnished Information (VFI) for all selected equipment for mission critical functional areas.

B.1.8 Speed power analysis is complete and results have been incorporated into the design.

B.1.9 Design margins and service life allowances are documented in compliance with the HSC-L Specification.

B.1.10 Identified technical risks have been documented in the CRMP database and acceptable mitigation plans developed. Mitigation steps scheduled for completion prior to CDR have been completed.

B.1.11 C5I system and component materials have been identified.

B.1.12 Mitigations for safety and HSI risks, identified and agreed upon at PDR, have been incorporated into the design.

B.1.13 The Contractor shall demonstrate progress of activities to prepare the production facility for execution of the Contractor’s build strategy.

B.1.13.1 Submit a list of major project milestones with scheduled start and completion dates for each activity relevant to the Contractor’s build strategy at the facility, and a risk and opportunity register outlining planned mitigations to prepare the facility and workforce to support the start of construction based on the Contractor’s IMS.

B.2 During the CDR, the Contractor shall:

B.2.1 Provide an update to the IMS

B.2.2 Update the status of system Software and Cyber-related requirements

B.2.3 Provide an update to the ILS strategy.

B.2.4 Provide an update to the HSI and HFE, and System Safety approach.

B.2.4.1 Report on update to meeting manning constraints.

B.2.4.2 Report and review HSI efforts and risks by each domain, including usability.

B.2.5 Risk assessment that includes descriptions of the top 10 critical risks, including details and status of the proposed risk mitigation actions.

B.2.6 The 3D Product Model reviews have been conducted.

B.3 The Contractor shall provide data and narrative in sufficient detail for the Government to verify that the Contractor has met the following Exit Criteria:

B.3.1 The design’s equipment, systems, and subsystems incorporate proven technology reflecting a high level of maturity proven in a representative HSC- L operating environment with demonstrated functional performance.

B.3.2 The ship design satisfies contract requirements.

B.3.3 Progress against risk mitigation plans provides confidence that the risks will be acceptable at PRR.

B.3.4 C5I Functional Interface Diagram demonstrates acceptable cost and performance risk.

B.3.5 Risk mitigation has been established for any Contractor schedule issues from Preliminary C5I System Requirements Traceability and Verification Matrix allocation to Hardware Configuration Items (HWCIs) and Computer Software Configuration Items (CSCIs).

B.3.6 The Contractor has demonstrated that human engineering, manpower, and safety requirements have been integrated into the design, and demonstrated that the design supports safe, timely, and efficient human performance to meet mission needs.

B.3.7 Identified safety and HSI risks from analysis, modeling, and testing, have been documented and tracked in the Hazard Tracking System and HSI Issues and Design Decisions databases. The Contractor has developed mitigation plans, and the mitigation plans are acceptable to the Government.

B.3.8 Identified technical risks have been documented in the CRMP database and acceptable mitigation plans developed. Mitigation steps scheduled for completion prior to CDR have been completed.

B.3.9 IDDs and updated SSDDs for Contractor responsible software / middleware have been submitted.

B.3.10 C5I System Requirements Traceability and Verification Matrix shows allocation to HWCIs and CSCIs.

B.3.11 C5I system and component material selections meet contract performance requirements.

B.3.12 CSCI requirements are defined and accepted as stable.

B.3.13 Interfaces between the CSCI and other configuration items both internal and external to the system are defined and stable.

B.3.14 Software user interfaces are identified, including critical formats and interactions.

B.3.15 Action items from the CDR have been successfully addressed and closed out, or a resolution plan has been defined by the Contractor and determined by the Government to be sufficient to exit CDR.

B.3.16 Closed Action Items are documented and acknowledged by the Contractor and Government.

B.3.17 Demonstrate the IMS, inclusive of Detail Design and Production scope, incorporates major project milestones, with scheduled start and completion dates and relationships to production related tasks, for each activity related to the Contractor’s production strategy.

B.3.18 Government concurrence that the 3D Product Model and review process is at a maturity level that allows for verification of the following:

B.3.18.1 80% of the entire 3D Product Model is complete and Model Review Meetings held.

B.3.18.2 3D Product Model and comments made through the Model Review Meetings have been resolved.

B.3.19 [A00001] All supplemental entrance criteria contract deliverables listed in B.1.4 shall be either accepted or approved, as applicable.

C. Production Readiness Review (PRR)

C.1 Prior to conducting the PRR the Contractor shall demonstrate successful completion of the following Entrance Criteria:

C.1.1 Action items from previous reviews identified for completion prior to PRR have been successfully addressed and closed out, or a resolution plan has been defined by the Contractor and determined by the Government to be sufficient to proceed with PRR.

C.1.2 CDR has been successfully completed. All exit criteria from CDR are complete or has Government approved resolution plan.

C.1.3 The Developmental Configuration Baseline (DCB) has been established.

C.1.4 [A00001] Contract deliverables submitted to the Government per Attachment J-4 CDRL timeframe.

C.1.5 3D Product Model and associated Construction Drawings required to support the initial 90 days of production have been accepted by USCG and all compliance comments have been resolved.

C.1.6 Identified technical risks have been documented in the Contractor’s Risk Management Plan (SOW C.3.040.1.2) database and acceptable mitigation plans developed. Mitigation steps scheduled for completion prior to PRR have been completed.

C.1.7 Confirmation that mitigations for safety and HSI risks, identified and agreed upon at CDR, have been incorporated into the design.

C.1.8 The Contractor shall demonstrate progress of activities to prepare the production facility for execution of the Contractor’s build strategies.

C.1.8.1 Not later than 7 days prior to PRR submit an updated report detailing progress of all major project milestones identified at CDR for each activity relevant to the Contractor’s build strategy at the production facility, as well as an updated risk and opportunity register outlining the status of mitigations to prepare the facility and workforce to support the start of construction based on the Contractor’s IMS.

C.1.8.2 Not later than 7 days prior to PRR submit a list of major project milestones with scheduled start and completion dates for each activity relevant to the Contractor’s build strategy at the facility, and a risk and opportunity register outlining planned mitigations to prepare the facility and workforce to support the start of construction based on the Contractor’s IMS.

C.1.9 Government concurrence that the 3D TDP’s 3D Product Model and review process is at a maturity level that allows for verification of the following:

C.1.9.1 The entire 3D Product Model is complete and a Model Review Meeting held.

C.2 During the PRR, the Contractor shall provide data and narrative in sufficient detail for the Government to verify that the Contractor has met the following Exit Criteria:

C.2.1 Detailed work instructions, 3D Product Model output, drawings and processes attached to the Build Strategy and Producibility Report to support the start of construction and initial 90 days of production have been reviewed and accepted without comments by the Government. The Contractor shall identify all changes planned and/or that may occur prior to production for work instructions and processes during this period.

C.2.2 Required Contractor staffing levels (with proper qualifications) are established and available for Program Management, Engineering and Production (by Trade) for the initial 90 days of production.

C.2.3 A facility preparedness and utilization assessment has been conducted (including other on-going and future scheduled work) with Government participation demonstrating that facilities, e.g., temporary and/or new fabrication buildings, erection/outfitting canopies, transporters, cranes, jigs, special fixtures, and fixed and/or temporary infrastructure required to support the Contractor’s build strategy are in place to support production.

C.2.4 The IMS has been submitted and reviewed, and includes all activities specific to preparing and outfitting the production facility and workforce to start of construction, and accounts for supplier/vendor timelines if the Contractor chooses to outsource manufacture of assemblies, sub-assemblies, etc.

C.2.5 Identified safety and HSI risks from analyses, modeling, and testing, have been documented and tracked in the Hazard Tracking System and HSI Issues and Design Decisions databases. The Contractor has developed mitigation plans and the mitigation plans are acceptable to the Government.

C.2.6 Demonstrated that human engineering, manpower, and safety requirements have been integrated into the design, and demonstrated that the design supports safe, timely, and efficient human performance to meet mission needs.

C.2.7 Government concurrence that the 3D TDP’s 3D Product Model and review process is at a maturity level that allows for verification of the following:

C.2.7.1 3D Product Model comments made through Model Review Meeting have been adjudicated.

C.2.7.2 Comments against model elements that are part of the initial 90 days of production have been resolved.

C.2.7.3 All systems shall have been submitted and completed Government 3D Product Model review.

C.2.8 [A00001] All supplemental entrance criteria contract deliverables listed in C.1.4 shall be either accepted or approved, as applicable.

D. Test Readiness Review (TRR)

D.1 Prior to conducting the TRR, the Contractor shall demonstrate successful completion of the following Entrance Criteria:

D.1.1 The HSC-L construction has been completed and all systems have been groomed to verify they perform as intended.

D.1.2 The design is fully integrated, baselined, and placed under formal configuration control, and all ECPs and RFVs have been resolved or have completed mitigation plans established.

D.1.3 [A00007] All test plans (Acceptance Tests and One-Time Tests), test cases, and test procedures are fully drafted, reviewed, and approved.

D.1.4 The test environment is fully set up, verified, and available.

D.1.5 Any and all required test data have been generated, staged, and validated for use.

D.1.6 All test execution personnel are identified, fully trained on the test procedures, and available.

D.2 During the TRR, the Contractor shall:

D.2.1 Walk through all approved test plans, test cases, and test procedures

D.2.2 Confirm that the test environment is fully setup and available D.2.3 Confirm that test personnel are trained on the test procedures and are available to conduct the tests.

D.3 The TRR will be closed after the Contractor provides data and narrative in sufficient detail for the Government to verify that the Contractor has met the following Exit Criteria:

D.3.1 All critical action items, discrepancies, and risks identified during the TRR are resolved or have formally approved mitigation plans.

E. Summary Table

Table 1 provides guidance regarding what the Government considers CDRLs to be completed as entrance criteria for each design review.

Table 1: [A00005] Deliverables CDRL CDRL Name PDR CDR PRR TRR 040-001 Meeting Agenda, Presentation

Materials and Action Items X X X X

040-002 Integrated Master Schedule (IMS) X X X 041-001 Configuration Status Accounting

Data X

041-003 Engineering Change Proposal X X X X 041-004 Request for Variance X X X X 073-001 Airborne Noise Control and

Vibration Analysis X X

073-002 Torsional Vibration Analysis & Report

X

074-001 Welding Schedule and Details X 074-002 Non-Destructive Testing (NDT)

Report X

079-001 Intact and Damage Stability Analyses

X X

083-003 List of Special Tools and Test Equipment (LST&TE)

X

085-001 Drawing Number Assignment Report

X

085-002 3-Dimensional Technical Data Package (3D TDP)

X X

085-004 3D System Model Reviews X X X 092-001 Acceptance Test Plan X 092-002 Acceptance Test Procedures X 092-003 Acceptance Test Schedule X 096-001 Weight Control Plan X 096-002 Allocated Baseline Weight X

CDRL CDRL Name PDR CDR PRR TRR Estimate (ABWE)

100-001 Structural Foundations Report and Calculations

X

100-002 Mast Structural Analysis X 100-003 Standard Structural Details X 100-004 Foundations Drawing X 101-001 Tank Arrangements and Detail

Drawing X X

201-001 Machinery Arrangement Drawings X X 202-001 Machinery Controls Network

Architecture Report X

243-001 Propulsion Shafting Plans and Particulars

X

243-002 Propulsion Shafting Alignment Calculations and Procedures

X

245-001 Propeller Drawing X X 252-001 Failure Modes and Effects

Analysis for Electric/Electronic Control System for Propulsion and Steering

X X

300-001 Booklet of Standard Wiring Practice

X

300-002 Electrical One Line Diagram X X 300-003 Electric Plant Load Analysis

(EPLA)

X X

300-004 Electrical Plant X 300-005 Easy Power Model Reports X 324-001 Switchboards and Power Panel

Drawings X X

400-001 Electronics Systems Schematic Block Diagrams

X X

400-002 Electronics Systems Elementary Wiring Diagrams

X X

401-001 Topside Arrangements and Detail Drawing

X

402-001 Interface Design Description

(IDD)

X X

402-002 System/Subsystem Design Description (SSDD)

X X

435-001 Electronics System Architecture Report

X

436-001 Electric Alarms, Safety & Warning Systems

X

504-001 Instrument and Gauge Calibration Report

X

508-001 Insulation Schedule for Machinery, Equipment and Piping

X

512-001 HVAC System Diagram, X

CDRL CDRL Name PDR CDR PRR TRR Equipment List, Heating and Cooling Load Calculations

512-002 HVAC System Duct Pressure Loss Calculations

X

580-001 Working Deck Arrangement and Detail Drawings

X

582-001 Mooring, Towing and Anchor Equipment and Systems

X

589-001 Crane Assembly and Detailed Drawings

X

601-001 General Arrangement Drawings X X 612-001 Walkways, Handrails, Gratings and Floor Plates X X

620-001 Doors, Hatches & Manholes Schedule

X

625-001 Window Schedule and Drawing X 631-001 Paint Schedule X X 633-001 (Anode Certification) Cathodic

Protection System Drawing and Computational Analysis

X

634-001 Deck Covering Schedule and Drawing

X X

635-001 Insulation and Sheathing Schedule and Drawing

X

640-001 Space Arrangements Drawings X