This document is the Design and Readiness Review Requirements and Criteria for the USCG Homeland Security Cutter – Light Icebreaker (HSC-L) program, serving as Attachment J-2 to the contract. The document establishes entrance criteria, demonstration requirements, and exit criteria for four major technical reviews spanning the design through testing phases: Preliminary Design Review (PDR), Critical Design Review (CDR), Production Readiness Review (PRR), and Test Readiness Review (TRR).

The PDR entrance criteria require the contractor to present proposed design changes, demonstrate a balanced and convergent design incorporating vendor-furnished information for mission-critical equipment, and submit contract deliverables 15 days prior to review. The contractor must provide engineering descriptions covering 22 subjects including general arrangement, hull structure, propulsion systems, stability analyses, electrical systems, HVAC, fire suppression, electronics, and habitability. During PDR, the contractor must conduct an Integrated Master Schedule (IMS) review, discuss software and cyber requirements, present Integrated Logistics Support and Human Systems Integration strategies, assess the top 10 critical risks, and establish a 3D Product Model review process. PDR exit criteria confirm the design meets HSC-L System Specifications, is producible per the contractor's build strategy, incorporates proven technology, and demonstrates achievable management plans and sufficient engineering resources.

The CDR entrance criteria require PDR completion, closure of prior action items, developed mockups with Coast Guard feedback incorporated, and contract deliverables submitted 15 days prior to CDR. Engineering descriptions must address any design changes across the same 22 subject areas as PDR. The contractor must demonstrate the 3D Product Model at appropriate maturity to verify no equipment interferences and that HSI requirements are met, complete speed power analysis, document technical risks in the CRMP database with acceptable mitigation plans, and show progress preparing the production facility. CDR exit criteria confirm equipment and systems incorporate proven mature technology, the design satisfies contract requirements, risk mitigation plans provide confidence for PRR, and human engineering and safety requirements are integrated into the design.

The PRR entrance criteria require completion and closure of prior action items, successful CDR completion with approved resolution plans for any open exit criteria, establishment of the Developmental Configuration Baseline (DCB), and submission of contract deliverables 15 days prior to PRR. The 3D Product Model and construction drawings supporting the initial 90 days of production must be accepted by USCG with all compliance comments resolved. The contractor must demonstrate progress on production facility preparation, including updated reports on major project milestones and risk/opportunity registers submitted no later than 7 days prior to PRR. PRR exit criteria require detailed work instructions, 3D Product Model output, and drawings supporting the initial 90 days of production to be reviewed and accepted without comments by the Government, with required contractor staffing levels established and facility preparedness assessments completed with Government participation.

The TRR entrance criteria require HSC-L construction completion with all systems groomed, full design integration and baseline with ECPs and RFVs resolved, submission of all test plans (Acceptance Tests and One-Time Tests), test cases, and test procedures 60 days prior to TRR, full test environment setup and verification, generated and validated test data, and identified and trained test personnel. TRR demonstrations include walkthroughs of all approved test plans and confirmation of test environment availability and personnel training. The TRR exit criterion requires resolution of all critical action items, discrepancies, and risks identified during the review or formal approval of mitigation plans. Table 1 provides a comprehensive list of 67 Contract Data Requirements List (CDRL) deliverables and their applicability across the four review phases.

View the file

Other files

File Type Posted
Section J-07 Pricing Schedule_A00008.xlsx XLSX spreadsheet
RFP_70Z02326R93280004_HSC-L_Conformed_A00008.pdf PDF
SF-30 Amendment A00008.pdf PDF
Attachment 5 - Government Responses to Solicitation Questions_A00008.pdf PDF
Section J-02 Design and Readiness Review Requirements and Criteria_A00007.pdf PDF
Section J-54 Hose Log_A00007.xlsx XLSX spreadsheet
Section J-08_Insurance_Spares_List_A00007.pdf PDF
Section J-07 Pricing Schedule_A00007.xlsx XLSX spreadsheet
Section J-01 HSC-L System Specification_A00007.pdf PDF
Section J-09B Tech DataTables_A00007.xlsx XLSX spreadsheet
SF-30 Amendment A00007.pdf PDF
RFP_70Z02326R93280004_HSC-L_Conformed_A00007.pdf PDF
Attachment 4 - Government Responses to Solicitation Questions_A00006.pdf PDF
SF-30 Amendment A00006.pdf PDF
Section J-13I DD Form 1692 Engineering Change Proposal.pdf PDF
Section J-13D ATCH 085-002 3D TDP.pdf PDF
Section J-13B ATCH 083-001-2 ESWBS WORKBOOK.xlsx XLSX spreadsheet
Section J-09B Tech Data Tables.xlsx XLSX spreadsheet
Section J-13H COMDTINST M10360_3D Colors and Coatings Manual.pdf PDF
Section J-09A Technical Data Rights Table Instructions.pdf PDF
Section J-13L COMDTINST 9085_1D Naval Engineering Computer Aided Design Standards.pdf PDF
Section J-13E SFLC Std Spec 6310 Requirements for Preservation of Ship Structures.pdf PDF
Section J-13M COMDTINST M5260_6A Directives System Program.pdf PDF
Section J-13K ATCH 085-005-2 2D TDP.pdf PDF
Section J-13J ATCH 086-001 2025-04-04 PROMULGATION FRONT MATTER WITH COPYRIGHT (IPW).pdf PDF
Section J-13C ATCH 083-004-1 PPL Template.xlsx XLSX spreadsheet
Section J-06 Notice for Filing Agency Protest.pdf PDF
Section J-10 Section 508 Contract Language for HSC-L.pdf PDF
Section J-11 MIL-HDBK-61B.pdf PDF
Section J-52 Outfitting List.pdf PDF
Section J-07 Pricing Schedule_A00005.xlsx XLSX spreadsheet
Section J-13A ATCH 083-001-1 MECL.xlsx XLSX spreadsheet
Section J-08_Insurance_Spares_List_A00005.pdf PDF
SF-30 Amendment A00005.pdf PDF
Section J-01 HSC-L System Specification_A00005.pdf PDF
Section J-13G COMDTINST M5260_6A Management of Scientific and Technical Information (STINFO).pdf PDF
Section J-53 Sand Chart Template_A00005.xlsx XLSX spreadsheet
RFP_70Z02326R93280004_HSC-L_Conformed_A00005.pdf PDF
Section J-02 Design and Readiness Review Requirements and Criteria_A00005.pdf PDF
Section J-13N DD Form 1694 Request for Deviation-Waiver.pdf PDF
Section J-13F SFLC Std Spec 6341 Interior Deck Covering.pdf PDF
SF-30 Amendment A00004.pdf PDF
Attachment 3 - Government Responses to Solicitation Questions_A00003.pdf PDF
RFP_70Z02326R93280004_HSC-L_Conformed_A00003.pdf PDF
SF-30 Amendment A00003.pdf PDF
Attachment 2 - Government Responses to Solicitation Questions_A00002.pdf PDF
SF-30 Amendment A00002.pdf PDF
RFP_70Z02326R93280004_HSC-L_Conformed_A00002.pdf PDF
SF-30 Amendment A00001.pdf PDF
RFP_70Z02326R93280004_HSC-L_Conformed_A00001.pdf PDF
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCG HOMELAND SECURITY

CUTTER – LIGHT ICEBREAKER

(HSC-L)

DESIGN AND READINESS REVIEW

REQUIREMENTS AND CRITERIA

ATTACHMENT J-2

Version: [ORIG]

Prepared by:

COMMANDANT (CG-SEA-A8)

UNITED STATES COAST GUARD STOP 7800

2703 MARTIN LUTHER KING JR AVE SE

WASHINGTON DC 20593-7800

Distribution Statement A: Approved for public release; distribution is unlimited.

Homeland Security Cutter – Light Icebreaker (HSC-L) 70Z02326R93280004

Readiness Review Requirements and Criteria ORIG

Scope: This attachment defines the entrance, demonstration and exit criteria for the major

Technical Reviews for the HSC-L program.

A. Preliminary Design Review (PDR)

A.1 The Contractor shall demonstrate successful completion of the following Entrance

Criteria:

A.1.1 Present any proposed changes to the contract design that are technically feasible and consistent with a product that can meet the HSC-L System

Specifications.

A.1.2 The revised contract design is balanced with internally consistent and convergent design characteristics of the Principal Dimensions, Arrangements, Area / Volume, Structures, Weight, Stability, Propulsion

Power and Electric Power from a common design baseline with minimal risk of subsequent adverse changes.

A.1.3 The revised contract design incorporates vendor furnished information (VFI) for equipment identified for mission critical functional areas.

A.1.4 [A00001] Contract deliverables per Table 1 have been submitted to the

Government per Attachment J-4 CDRL timeframe. 15 days prior to PDR or earlier and have been approved or accepted as applicable, and comments provided by the Government have been resolved.

A.1.5 Engineering descriptions of the ship system and subsystems and associated architecture are complete, as demonstrated by Government concurrence of the design changes to the following subjects:

A.1.5.1 General arrangement

A.1.5.2 Hull and deckhouse structure and scantlings

A.1.5.3 Propulsion system and bow thruster, including resistance, powering, and maneuvering (i.e., station keeping for ATON)

A.1.5.4 Control surfaces, rudder sizing, and turning performance

A.1.5.5 Weight estimate, intact stability, damage stability, and towing stability

A.1.5.6 Details of the production design for the electrical power generation, storage, and distribution system

A.1.5.7 Interior lighting system

A.1.5.8 Exterior lighting system

A.1.5.9 Pilothouse arrangement and seating

A.1.5.10 Machinery space(s) arrangement

A.1.5.11 Details of the heating, ventilation, and air conditioning systems

A.1.5.12 Mast and antenna configuration

A.1.5.13 Fire detection and suppression system

A.1.5.14 Installation details of the electronics, communications, and navigation systems

A.1.5.15 Propulsion controls, steering system, bow thruster, and autopilot

A.1.5.16 Human-machine interfaces

A.1.5.17 Aft deck arrangement including ATON and towing tackle equipment, configuration and controls

A.1.5.18 Galley, berths, and habitability details.

A.1.5.19 Human factors engineering for operators and maintainers

A.1.5.20 System reliability

A.1.5.21 Noise and vibration

A.1.5.22 Coating system, including a preservation plan in accordance with SFLC

Std Spec 6310.

A.1.6 Verification Planning efforts have been established, to include:

A.1.6.1 Modeling and Simulation support efforts.

A.1.6.2 Test and Integration approach.

A.1.6.3 Inspection and Certification approach.

A.1.7 Design margins and service life allowances are documented and are in compliance with the HSC-L System Specifications.

A.1.8 Requests for Action (RFAs), Action Items, and deficiencies documented from prior review (i.e. kick-off meeting) have been resolved.

A.2 During the PDR, the Contractor shall:

A.2.1 Conduct an IMS Review

A.2.1.1 The Contractor shall provide a description of the process by which the

IMS is assembled and updated, logical linkages are established, resources are applied, and the level of fidelity for the various types of work contained in the IMS, including the following efforts:

A.2.1.2 Design and Production schedule (Including PDR, CDR and PRR acceptance of contract deliverables by the Government)

A.2.2 Discuss any System Software and Cyber-related Requirements updates

A.2.3 Integrated Logistics Support (ILS) strategy development plan of action with milestones.

A.2.4 Human Systems Integration (HSI) and Human Factors Engineering (HFE), and System Safety approach and planning.

A.2.4.1 Report on approach and planning for meeting manning constraints.

A.2.4.2 Report and review HSI efforts and risks by each domain, including usability.

A.2.5 Risk assessment that includes descriptions of the top 10 critical risks, including details and status of the proposed risk mitigation actions.

A.2.6 The 3D Product Model review process is established, and reviews have been conducted, including:

A.2.6.1 The 3D Product Model Working group has been founded.

A.2.6.2 The first model review has been held.

A.2.6.3 The model data structure and elements are established.

A.2.6.4 A method for determining the model’s percent complete is agreed upon and implemented.

A.2.6.5 The method for exchanging and resolving Government comments is established.

A.2.6.6 The schedule for 3D Model System reviews is established and review timelines agreed.

A.3 The PDR will be closed after the Contractor provides data and narrative in sufficient detail for the Government to verify that the Contractor has met the following Exit Criteria:

A.3.1 The revised design is a complete engineering description of a ship that meets the requirements of the HSC-L System Specification in its entirety.

A.3.2 The design is producible per the Contractor’s build strategy.

A.3.3 The design’s equipment, systems, and subsystems incorporate proven technology reflecting a high level of maturity proven in a representative HSC-

L operating environment with demonstrated functional performance.

A.3.4 HSI analyses to confirm the following:

A.3.4.1 The design supports safe, timely, and efficient human performance to meet mission needs.

A.3.5 The Management Plan and IMS are achievable.

A.3.6 Design tools and engineering resources are available and sufficient to support design maturation and production.

A.3.7 Required Delivery Dates (RDD) and labor support for GFE and GFI are acceptable.

A.3.8 Long Lead Time Material (LLTM) items are identified with in-yard need dates per Attachment J-7 “Pricing Schedule”

A.3.9 Closed Action Items are documented and acknowledged by both the

Contractor and Government.

A.3.10 All supplemental entrance criteria contract deliverables listed in A.1.4 shall be either accepted or approved, as applicable.

B. Critical Design Review (CDR)

B.1 The Contractor shall demonstrate successful completion of the following Entrance

Criteria:

B.1.1 PDR has been successfully completed.

B.1.2 Action items from previous reviews identified for completion prior to CDR have been successfully addressed and closed out, or a resolution plan has been defined by the Contractor and determined by the Government to be sufficient to proceed with CDR.

B.1.3 Mockups have been developed and Coast Guard feedback incorporated into the design.

B.1.4 [A00001] Contract deliverables per Table 1 have been submitted to the

Government per Attachment J-4 CDRL timeframe.15 days prior to CDR or earlier have been approved or accepted as applicable, and comments provided by the Government have been resolved.

B.1.5 Engineering descriptions of the ship system and subsystems and associated architecture are complete, as demonstrated by Government concurrence of any design changes to the following subjects:

B.1.5.1 General arrangement

B.1.5.2 Hull and deckhouse structure and scantlings

B.1.5.3 Propulsion system and bow thruster, including resistance, powering, and maneuvering (i.e., station keeping for ATON)

B.1.5.4 Control surfaces, rudder sizing, and turning performance

B.1.5.5 Weight estimate, intact stability, damage stability, and towing stability

B.1.5.6 Details of the production design for the electrical power generation, storage, and distribution system

B.1.5.7 Interior lighting system

B.1.5.8 Exterior lighting system

B.1.5.9 Pilothouse arrangement and seating

B.1.5.10 Machinery space(s) arrangement

B.1.5.11 Details of the heating, ventilation, and air conditioning systems

B.1.5.12 Mast and antenna configuration

B.1.5.13 Fire detection and suppression system

B.1.5.14 Installation details of the electronics, communications, and navigation systems

B.1.5.15 Propulsion controls, steering system, bow thruster, and autopilot

B.1.5.16 Human-machine interfaces

B.1.5.17 Aft deck arrangement including ATON and towing tackle equipment, configuration and controls

B.1.5.18 Galley, berths, and habitability details.

B.1.5.19 Human factors engineering for operators and maintainers

B.1.5.20 System reliability

B.1.5.21 Noise and vibration

B.1.5.22 Coating system, including a preservation plan in accordance with SFLC

Std Spec 6310.

B.1.6 Government concurrence that the 3-D Product Model is at a maturity level that allows for verification of the following:

B.1.6.1 Arrangements meet HSC-L Design Artifacts and System

Specification requirements, and that there are no equipment interferences.

B.1.6.2 Virtual walkthroughs and analyses to confirm that HSI requirements are met by the design.

B.1.7 The design incorporates Vendor Furnished Information (VFI) for all selected equipment for mission critical functional areas.

B.1.8 Speed power analysis is complete and results have been incorporated into the design.

B.1.9 Design margins and service life allowances are documented in compliance with the HSC-L Specification.

B.1.10 Identified technical risks have been documented in the CRMP database and acceptable mitigation plans developed. Mitigation steps scheduled for completion prior to CDR have been completed.

B.1.11 C5I system and component materials have been identified.

B.1.12 Mitigations for safety and HSI risks, identified and agreed upon at PDR, have been incorporated into the design.

B.1.13 The Contractor shall demonstrate progress of activities to prepare the production facility for execution of the Contractor’s build strategy.

B.1.13.1 Submit a list of major project milestones with scheduled start and completion dates for each activity relevant to the Contractor’s build strategy at the facility, and a risk and opportunity register outlining planned mitigations to prepare the facility and workforce to support the start of construction based on the Contractor’s IMS.

B.2 During the CDR, the Contractor shall:

B.2.1 Provide an update to the IMS

B.2.2 Update the status of system Software and Cyber-related requirements

B.2.3 Provide an update to the ILS strategy.

B.2.4 Provide an update to the HSI and HFE, and System Safety approach.

B.2.4.1 Report on update to meeting manning constraints.

B.2.4.2 Report and review HSI efforts and risks by each domain, including usability.

B.2.5 Risk assessment that includes descriptions of the top 10 critical risks, including details and status of the proposed risk mitigation actions.

B.2.6 The 3D Product Model reviews have been conducted.

B.3 The Contractor shall provide data and narrative in sufficient detail for the

Government to verify that the Contractor has met the following Exit Criteria:

B.3.1 The design’s equipment, systems, and subsystems incorporate proven technology reflecting a high level of maturity proven in a representative HSC-

L operating environment with demonstrated functional performance.

B.3.2 The ship design satisfies contract requirements.

B.3.3 Progress against risk mitigation plans provides confidence that the risks will be acceptable at PRR.

B.3.4 C5I Functional Interface Diagram demonstrates acceptable cost and performance risk.

B.3.5 Risk mitigation has been established for any Contractor schedule issues from Preliminary C5I System Requirements Traceability and Verification

Matrix allocation to Hardware Configuration Items (HWCIs) and Computer

Software Configuration Items (CSCIs).

B.3.6 The Contractor has demonstrated that human engineering, manpower, and safety requirements have been integrated into the design, and demonstrated that the design supports safe, timely, and efficient human performance to meet mission needs.

B.3.7 Identified safety and HSI risks from analysis, modeling, and testing, have been documented and tracked in the Hazard Tracking System and HSI

Issues and Design Decisions databases. The Contractor has developed mitigation plans, and the mitigation plans are acceptable to the Government.

B.3.8 Identified technical risks have been documented in the CRMP database and acceptable mitigation plans developed. Mitigation steps scheduled for completion prior to CDR have been completed.

B.3.9 IDDs and updated SSDDs for Contractor responsible software / middleware have been submitted.

B.3.10 C5I System Requirements Traceability and Verification Matrix shows allocation to HWCIs and CSCIs.

B.3.11 C5I system and component material selections meet contract performance requirements.

B.3.12 CSCI requirements are defined and accepted as stable.

B.3.13 Interfaces between the CSCI and other configuration items both internal and external to the system are defined and stable.

B.3.14 Software user interfaces are identified, including critical formats and interactions.

B.3.15 Action items from the CDR have been successfully addressed and closed out, or a resolution plan has been defined by the Contractor and determined by the Government to be sufficient to exit CDR.

B.3.16 Closed Action Items are documented and acknowledged by the Contractor and

Government.

B.3.17 Demonstrate the IMS, inclusive of Detail Design and Production scope, incorporates major project milestones, with scheduled start and completion dates and relationships to production related tasks, for each activity related to the Contractor’s production strategy.

B.3.18 Government concurrence that the 3D Product Model and review process is at a maturity level that allows for verification of the following:

B.3.18.1 80% of the entire 3D Product Model is complete and Model

Review Meetings held.

B.3.18.2 3D Product Model and comments made through the Model Review

Meetings have been resolved.

B.3.18.2B.3.19 [A00001] All supplemental entrance criteria contract deliverables listed in B.1.4 shall be either accepted or approved, as applicable.

C. Production Readiness Review (PRR)

C.1 Prior to conducting the PRR the Contractor shall demonstrate successful completion of the following Entrance Criteria:

C.1.1 Action items from previous reviews identified for completion prior to PRR have been successfully addressed and closed out, or a resolution plan has been defined by the Contractor and determined by the Government to be sufficient to proceed with PRR.

C.1.2 CDR has been successfully completed. All exit criteria from CDR are complete or has Government approved resolution plan.

C.1.3 The Developmental Configuration Baseline (DCB) has been established.

C.1.4 [A00001] Contract deliverables submitted to the Government 15 days prior to PRR or earlier have been approved or accepted as applicable, and comments provided by the Government have been resolved. per

Attachment J-4 CDRL timeframe.

C.1.5 3D Product Model and associated Construction Drawings required to support the initial 90 days of production have been accepted by USCG and all compliance comments have been resolved.

C.1.6 Identified technical risks have been documented in the Contractor’s Risk

Management Plan (SOW C.3.040.1.2) database and acceptable mitigation plans developed. Mitigation steps scheduled for completion prior to PRR have been completed.

C.1.7 Confirmation that mitigations for safety and HSI risks, identified and agreed upon at CDR, have been incorporated into the design.

C.1.8 The Contractor shall demonstrate progress of activities to prepare the production facility for execution of the Contractor’s build strategies.

C.1.8.1 Not later than 7 days prior to PRR submit an updated report detailing progress of all major project milestones identified at CDR for each activity relevant to the Contractor’s build strategy at the production facility, as well as an updated risk and opportunity register outlining the status of mitigations to prepare the facility and workforce to support the start of construction based on the Contractor’s IMS.

C.1.8.2 Not later than 7 days prior to PRR submit a list of major project milestones with scheduled start and completion dates for each activity relevant to the Contractor’s build strategy at the facility, and a risk and opportunity register outlining planned mitigations to prepare the facility and workforce to support the start of construction based on the

Contractor’s IMS.

C.1.9 Government concurrence that the 3D TDP’s 3D Product Model and review process is at a maturity level that allows for verification of the following:

C.1.9.1 The entire 3D Product Model is complete and a Model Review

Meeting held.

C.2 During the PRR, the Contractor shall provide data and narrative in sufficient detail for the Government to verify that the Contractor has met the following Exit Criteria:

C.2.1 Detailed work instructions, 3D Product Model output, drawings and processes attached to the Build Strategy and Producibility Report to support the start of construction and initial 90 days of production have been reviewed and accepted without comments by the Government. The Contractor shall identify all changes planned and/or that may occur prior to production for work instructions and processes during this period.

C.2.2 Required Contractor staffing levels (with proper qualifications) are established and available for Program Management, Engineering and

Production (by Trade) for the initial 90 days of production.

C.2.3 A facility preparedness and utilization assessment has been conducted

(including other on-going and future scheduled work) with Government participation demonstrating that facilities, e.g., temporary and/or new fabrication buildings, erection/outfitting canopies, transporters, cranes, jigs, special fixtures, and fixed and/or temporary infrastructure required to support the Contractor’s build strategy are in place to support production.

C.2.4 The IMS has been submitted and reviewed, and includes all activities specific to preparing and outfitting the production facility and workforce to start of construction, and accounts for supplier/vendor timelines if the

Contractor chooses to outsource manufacture of assemblies, sub-assemblies, etc.

C.2.5 Identified safety and HSI risks from analyses, modeling, and testing, have been documented and tracked in the Hazard Tracking System and HSI

Issues and Design Decisions databases. The Contractor has developed mitigation plans and the mitigation plans are acceptable to the Government.

C.2.6 Demonstrated that human engineering, manpower, and safety requirements have been integrated into the design, and demonstrated that the design supports safe, timely, and efficient human performance to meet mission needs.

C.2.7 Government concurrence that the 3D TDP’s 3D Product Model and review process is at a maturity level that allows for verification of the following:

C.2.7.1 3D Product Model comments made through Model Review Meeting have been adjudicated.

C.2.7.2 Comments against model elements that are part of the initial 90 days of production have been resolved.

C.2.7.3 All systems shall have been submitted and completed Government 3D

Product Model review.

C.2.7.3C.2.8 [A00001] All supplemental entrance criteria contract deliverables listed in C.1.4 shall be either accepted or approved, as applicable.

D. Test Readiness Review (TRR)

D.1 Prior to conducting the TRR, the Contractor shall demonstrate successful completion of the following Entrance Criteria:

D.1.1 The HSC-L construction has been completed and all systems have been groomed to verify they perform as intended.

D.1.2 The design is fully integrated, baselined, and placed under formal configuration control, and all ECPs and RFVs have been resolved or have completed mitigation plans established.

D.1.3 No later than 60 days prior to TRR, all test plans (Acceptance Tests and One-

Time Tests), test cases, and test procedures are fully drafted, reviewed, and approved.

D.1.4 The test environment is fully set up, verified, and available.

D.1.5 Any and all required test data have been generated, staged, and validated for use.

D.1.6 All test execution personnel are identified, fully trained on the test procedures, and available.

D.2 During the TRR, the Contractor shall:

D.2.1 Walk through all approved test plans, test cases, and test procedures

D.2.2 Confirm that the test environment is fully setup and available

D.2.3 Confirm that test personnel are trained on the test procedures and are available to conduct the tests.

D.3 The TRR will be closed after the Contractor provides data and narrative in sufficient detail for the Government to verify that the Contractor has met the following Exit Criteria:

D.3.1 All critical action items, discrepancies, and risks identified during the TRR are resolved or have formally approved mitigation plans.

E. Summary Table

Table 1 provides guidance regarding what the Government considers CDRLs to be completed as entrance criteria for each design review.

Table 1: Deliverables

CDRL CDRL Name PDR CDR PRR TRR

040-001 Meeting Agenda, Presentation

Materials and Action Items

X X X X

040-002 Integrated Master Schedule (IMS) X X X

041-001 Configuration Status Accounting

Data

X

041-003 Engineering Change Proposal X X X X

041-004 Request for Variance X X X X

073-001 Airborne Noise Control and

Vibration Analysis

X X

073-002 Torsional Vibration Analysis &

Report

X X

074-001 Welding Schedule and Details X

074-002 Non-Destructive Testing (NDT)

Report

X

079-001 Intact and Damage Stability

Analyses

X

083-003 List of Special Tools and Test

Equipment (LST&TE)

X

085-001 Drawing Number Assignment

Report

X X X

CDRL CDRL Name PDR CDR PRR TRR

085-002 3-Dimensional Technical Data

Package (3D TDP)

X X

085-004 3D System Model Reviews X X X

092-001 Acceptance Test Plan X

092-002 Acceptance Test Procedures X

092-003 Acceptance Test Schedule X

096-001 Weight Control Plan X

096-002 Allocated Baseline Weight

Estimate (ABWE)

X

100-001 Structural Foundations Report and

Calculations

X

100-002 Mast Structural Analysis X

100-003 Standard Structural Details X

100-004 Foundations Drawing X

101-001 Tank Arrangements and Detail

Drawing

X

201-001 Machinery Arrangement Drawings X X X

202-001 Machinery Controls Network

Architecture Report

X

243-001 Propulsion Shafting Plans and

Particulars

X

243-002 Propulsion Shafting Alignment

Calculations and Procedures

X X

245-001 Propeller Drawing X

252-001 Failure Modes and Effects

Analysis for Electric/Electronic

Control System for Propulsion and

Steering

X X

300-001 Booklet of Standard Wiring

Practice

X X

300-002 Electrical One Line Diagram X X X

300-003 Electric Plant Load Analysis

(EPLA)

X X

300-004 Electrical Plant X X

300-005 Easy Power Model Reports X X X

324-001 Switchboards and Power Panel

Drawings

X X

400-001 Electronics Systems Schematic

Block Diagrams

X X X

400-002 Electronics Systems Elementary

Wiring Diagrams

X X

401-001 Topside Arrangements and Detail

Drawing

X

402-001 Interface Design Description

(IDD)

X

402-002 System/Subsystem Design

Description (SSDD)

X

435-001 Electronics System Architecture X X

CDRL CDRL Name PDR CDR PRR TRR

Report

436-001 Electric Alarms, Safety &

Warning Systems

X

504-001 Instrument and Gauge Calibration

Report

X

508-001 Insulation Schedule for

Machinery, Equipment and Piping

X X

512-001 HVAC System Diagram, Equipment List, Heating and

Cooling Load Calculations

X

512-002 HVAC System Duct Pressure Loss

Calculations

X

580-001 Working Deck Arrangement and

Detail Drawings

X

582-001 Mooring, Towing and Anchor

Equipment and Systems

X

589-001 Crane Assembly and Detailed

Drawings

X

601-001 General Arrangement Drawings X X

612-001 Walkways, Handrails, Gratings and Floor Plates

X

620-001 Doors, Hatches & Manholes

Schedule

X

625-001 Window Schedule and Drawing X

631-001 Paint Schedule X

633-001 (Anode Certification) Cathodic

Protection System Drawing and

Computational Analysis

X

634-001 Deck Covering Schedule and

Drawing

X

635-001 Insulation and Sheathing Schedule and Drawing

X X

640-001 Space Arrangements Drawings X