6991 Contract_Executed.pdf

PDF 283 KB Posted

Attached to
SFFC Admin Building HVAC
Solicitation number
S-29100-00013280
Issued by
Tillamook County, Oregon

About this file

This document is a State of Oregon Public Improvement Agreement between the Department of Corrections and Copper Mechanical LLC for the OSP Admin Building HVAC project, with a contract number of #6991. The project involves HVAC work at the administration building, with a base bid of $190,300.00. The project start date is 10 days after the Notice to Proceed, with substantial completion scheduled for 09/01/25 and final completion set for 10/01/25. The contract includes various exhibits and attachments such as pricing submittal forms, bond forms, general conditions, specifications, plans, and bidder qualification requirements.

The contract includes liquidated damages of $400.00 per calendar day for failing to meet substantial or final completion dates. The contractor, Copper Mechanical LLC, is located in Ridgefield, Washington, with a Construction Contractors Board (CCB) number of 244752 valid until 2/28/2027. The contract emphasizes non-discrimination policies in line with House Bill 3060 and requires compliance with workforce and outreach requirements under Oregon Revised Statute 279C.533. The contract documents constitute the entire agreement between the parties, with no additional verbal or written understandings permitted outside of the signed contract.

View the file

Other files

File Type Posted
13280 Background.pdf PDF
13280 Plan Holder List.pdf PDF
Check Off sheet ITB~1.pdf PDF
13280 ITB_GTC_SGC_SPECS.pdf PDF
13280 Plans.pdf PDF
13280 SFFC Admin Building HVAC SOW.pdf PDF
13280 Bid Tab.pdf PDF
Beans Black~1.docx DOCX document
13280 ADDENDA 1.pdf PDF
6991 NOITA.pdf PDF
ITB~11.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Level 3 - Restricted a

Base Bid: $190,300.00; (As Detailed in Exhibit 1, Pricing Submittal Form)

STATE OF OREGON PUBLIC IMPROVEMENT AGREEMENT

for OSP

Admin Building HVAC Contract Number: #6991

This Agreement for the SFFC Admin Building HVAC (the "Agreement"), made by and between the State of Oregon, acting by and through the Department of Corrections, hereinafter called OWNER, and Copper Mechanical LLC. hereinafter called the CONTRACTOR (collectively the “Parties”), is effective on the date this Agreement has been signed by all the Parties and all required State of Oregon governmental approvals have been obtained. Unless otherwise defined in the Invitation to Bid or in this Agreement, the capitalized terms used herein are defined in Section A.1 of the State of Oregon General Conditions for Public Improvement Contracts.

WITNESSETH:

1. Contract Price, Contract Documents and Work.

The CONTRACTOR, in consideration of the sum of $190,300.00 (the "Contract Price"), to be paid to the CONTRACTOR by OWNER in the manner and at the time hereinafter provided, and subject to the terms and conditions provided for in the Invitation to Bid, this Public Improvement Agreement and other Contract Documents, all of which are incorporated herein by reference, hereby agrees to perform all Work described and reasonably inferred from the Contract Documents.

The Contract Price includes the following items:

CONTRACTOR shall perform the Work for the Contract Price pursuant to Invitation to Bid No. S‐29100‐0012569 d all Addenda thereto) and the following Exhibits and Attachments which are incorporated herein by this reference, whether or not physically attached to this Agreement:

EXHIBIT 1 PRICING SUBMITTAL FORM

EXHIBIT 2 [RESERVED]

EXHIBIT 3 PAYMENT BOND FORM

EXHIBIT 4 PERFORMANCE BOND FORM

EXHIBIT 5 [RESERVED]

EXHIBIT 6 GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS

EXHIBIT 7 SUPPLEMENTAL GENERAL CONDITIONS

ATTACHMENT B SPECIFICATIONS

ATTACHMENT C PLANS

ATTACHMENT D GENERAL REQUIREMENTS BIDDER'S QUALIFICATIONS

ATTACHMENT E SECURITY FORM (LEDS)

2. Representatives.

Unless otherwise specified in the Contract Documents, the OWNER designates Pete Belisle as its Authorized Representative in the administration of this Contract. The above‐named individual shall be the initial point of contact for matters related to performance, payment, authorization, and to carry out the responsibilities of the OWNER. CONTRACTOR has named Andrew Lee as its Authorized Representative to act on its behalf.

3. Contract Dates.

PROJECT START DATE:

SUBSTANTIAL COMPLETION:

FINAL COMPLETION:

10 Days After Notice to Proceed 09/01/25

10/01/25

3.a Project substantial and final completion dates represent the BASE BID timelines only. Bid alternates, if selected, may allow additional substantial and final completion time as indicated on each respective bid alternate line item on Exhibit 1; Pricing Submittal Form.

4. Liquidated Damages.

Liquidated damages of $400.00 will apply to the contract resulting from this ITB. Failure to substantially complete the Project by the date of Substantial Completion, as specified in the Contract, will result in damage to the State of Oregon.

Moreover, failure to fully complete the Project by the date of Final Completion, as specified in the Contract, will also result in damage to the State of Oregon. Since actual damage will be difficult to determine, it is agreed that the Contractor shall pay to the State of Oregon, not as a penalty but as the State of Oregon, not as a penalty but as liquidated damages, $400.00 per calendar day elapsed in excess of the Substantial Completion date stated in Section 3 of this Agreement. Moreover, it is agreed that the Contractor shall pay to the State of Oregon, not as a penalty but as liquidated damages, $400.00 per calendar day elapsed in excess of the Final Completion date stated in Section 3 of this Agreement.

5. Certification ‐ Non‐Discrimination Contractor certifies, in accordance with House Bill 3060 (2017 Oregon Laws, chapter 212)(“HB 3060”), that it has in place a policy and practice of preventing sexual harassment, sexual assault, and discrimination against employees who are members of a "protected class," as that term is defined by subsection 2(1)(b) of HB 3060. As a material term and condition of this Agreement, Contractor must maintain, throughout the duration of this Agreement, a policy and practice that complies with HB 3060, including, but not limited to, giving employees written notice of the Contractor’s policy and practice.

6. Workforce and Outreach Requirements (ORS 279C.533) Contractor agrees to be bound by and comply with all applicable workforce and outreach requirements provided under ORS 279C.533 as prescribed in the Contract Documents (see Exhibit 7).

7. Integration THE CONTRACT DOCUMENTS CONSTITUTE THE ENTIRE AGREEMENT BETWEEN THE PARTIES. NO WAIVER, CONSENT, MODIFICATION OR CHANGE OF TERMS OF THIS CONTRACT SHALL BIND EITHER PARTY UNLESS IN WRITING AND SIGNED BY BOTH PARTIES. SUCH WAIVER, CONSENT, MODIFICATION OR CHANGE, IF MADE, SHALL BE EFFECTIVE ONLY IN THE SPECIFIC INSTANCE AND FOR THE SPECIFIC PURPOSE GIVEN. THERE ARE NO OTHER UNDERSTANDINGS, AGREEMENTS, OR

REPRESENTATIONS, ORAL OR WRITTEN, NOT SPECIFIED HEREIN REGARDING THIS CONTRACT.

CONTRACTOR, BY THE SIGNATURE BELOW OF ITS AUTHORIZED REPRESENTATIVE, HEREBY

ACKNOWLEDGES THAT IT HAS READ THIS CONTRACT, UNDERSTANDS IT, AND AGREES TO BE BOUND

BY ITS TERMS AND CONDITIONS.

In witness whereof, the STATE OF OREGON, acting by and through the Department of Corrections executes this Agreement and the CONTRACTOR does execute the same as of the day and year of this Agreement first above written.

CONTRACTOR DATA:

CONTRACTOR NAME: Copper Mechanical LLC

CONTRACTOR ADDRESS: 6024 N 10th St

CONTRACTOR ADDRESS: Ridgefield, WA 98642

CONTRACTOR EMAIL ADDRESS: andrew@coppermechanical.com

CONTRACTOR'S CCB#: 244752

Expiration Date: 2/28/2027

SECRETARY OF STATE REGISTRATION: 2069763-91

CONTRACTOR'S SIGNATURE: Date

Reviewed by Facilities Administrator: Date

Date State of Oregon by and through its DEPARTMENT OF CORRECTIONS

STATE OF OREGON PUBLIC IMPROVEMENT AGREEMENT
WITNESSETH:
1. Contract Price, Contract Documents and Work.
2. Representatives.
3. Contract Dates.
4. Liquidated Damages.
$400.00
5. Certification ‐ Non‐Discrimination
6. Workforce and Outreach Requirements (ORS 279C.533)
7. Integration THE CONTRACT DOCUMENTS CONSTITUTE THE ENTIRE AGREEMENT BETWEEN THE PARTIES. NO WAIVER, CONSENT, MODIFICATION OR CHANGE OF TERMS OF THIS CONTRACT SHALL BIND EITHER PARTY UNLESS IN WRITING AND SIGNED BY BOTH PARTIES. SUCH WAIVER, CONSENT,...
3608521583
2025-06-11T14:06:45-0700
Copper Mech Office
Andrew Lee
I attest to the accuracy and integrity of this document
2025-06-18T10:37:21-0700
Steve Walborn
2025-06-20T07:52:51-0700
Dustin Sculatti