Questions and Answers 10 27 2026 ND NP THRO 202(1) Buck Hill Road.pdf

PDF 139 KB Posted

Attached to
ND NP THRO 204(1) Buck Hill Road
Solicitation number
6982AF25B000004
Issued by

About this file

This is a Questions and Answers document for federal contract opportunity 6982AF25B000004, ND NP THRO 204(1) Buck Hill Road, dated October 27, 2026. The document addresses 23 questions received between September 21 and October 22, 2026, regarding a landslide stabilization project at Buck Hill Road in Theodore Roosevelt National Park. Key clarifications include: contractors must bid the project as specified in the plans, with value-engineered alternatives permitted only after award; no pre-bid events are scheduled, but the project location is accessible; the period of performance is detailed in SCR Section 108.01; Amendment 001 clarifies specifications for Fusion Welded HDPE pipe regarding IPS or DIPS sizing; and the Superintendent cannot serve as the Quality Control Manager, per FP-14 Section 153.02(1). Additional details address permitting requirements (Sections 107 and 157), temporary traffic control and work limitations (Sections 108 and 156), construction water source provisions (Sections 105 and 158), staking data points and requirements (Section 152), tax exemption status under FAR Clause 52.229-3, field office requirements (Section 637), and pay factor acceptance criteria (Section 106). The document confirms that culvert C04 at STA 118+97 Rt. must be removed as noted in the plans; clarifies that the Quality Control Manager and Tester must be separate individuals; and specifies that if a government laboratory option is exercised, its location will be jointly determined between the Government and Contractor after Notice to Proceed issuance.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6982AF25B000004

ND NP THRO 204(1) Buck Hill Road

Questions & Answers 10/27/26 Page | 1

Questions Answers

Received September 21, 2026 1Q. In response to the Buck Hill Road landslide stabilization scope that is currently in pre-solicitation, would the Owner be interested in a value engineered solution alternative to stabilize the landslide? The current description details a large excavate/replace operation, and we could likely minimize disturbance in the National Park with a soil nail stabilization option.

Please let me know if we can discuss.

1A. The Contractor needs to bid the plans as

is. The successful Contractor can submit a VE proposal for evaluation after award.

Received October 6, 2026 2Q. Is there any type of prebid event planned? 2A. No pre-bid events are planned.

3Q. Is the project location available for viewing?

3A. The project location is accessible.

4Q. Are there any requirements to get into the park to view the project?

4A. Contact Theodore Roosevelt National Park directly via email at Philip_McCall@nps.gov for any requirements. The NPS cannot answer any questions concerning the project. All questions must be emailed to CFLContracts@dot.gov in accordance with the solicitation.

Received October 14, 2026 5Q. What is the period of performance for this project?

5A. Please see SCR Section 108.01 Commencement, Prosecution and Completion of Work starting on page E-13.

Received October 21, 2026 6Q. Will NDDOT Specifications be acceptable for the permanent sign installation and materials?

6A. Please bid the project as is.

7Q. Will NDDOT Specifications be acceptable for the temporary traffic control signs instead of mounting signs on wood posts?

7A. Please bid the project as is.

Received October 22, 2026 8Q. The spec doesn’t specify IPS or DIPS for the Fusion Welded HDPE pipe.

8A. Please see Amendment 001.

mailto:CFLContracts@dot.gov

Questions & Answers

Page | 2

Please advise which size you are looking for when you have a chance.

9Q, Can one person "triple hat" as Superintendent, SSHO and QC Manager?

9A. The Superintendent cannot serve as the QC Manager. Refer to 153.02(1) of the FP-14 for QC Manager requirements.

10Q. Please provide the site visit attendee sign in sheet.

10A. Pre-Bid Site Visit attendees has been posted on SAM.gov

11Q. Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?

11A. A construction water source is not identified in the contract. Please refer to Sections 105 and 158 for water source requirements.

12Q. Does this project require phasing?

12A. Refer to Section 108 and 156 of the SCRs for limitations on work and temporary traffic control requirements. Refer to section 204 of the SCRs for subexcavation plan requirements.

13Q. Is this project tax exempt? 13A. See Revolutionary FAR Overhaul (RFO) Clause 52.229-3 Federal, State, and Local Taxes

14Q. When do you anticipate on site work starting?

14A. Refer to subsection 108.01 for initial site work requirements.

15Q. Is permitting required? 15A. Yes. Please refer to Sections 107 and 157 of for permit requirements.

16Q. Please provide staking data points for the project.

16A. Please refer to SCR Subsections 102.02A and 152 for physical data provided on SAM.gov.

17Q. Are red, yellow, and blue tops required? 17A. Please refer to Section 152 for staking requirements.

18Q. Which pay item(s) are measured for payment using Pay Factors on this project?

18A. Please refer to Section 106 and the “Acceptance” Subsections for each pay item in the FP-14 and the SCRs for sampling, testing, and acceptance requirements.

19Q. Can we shut down the roadway for the entire construction period or must we maintain one lane of traffic?

19A. Please refer to Sections 108 and 156 of the SCRs for limitations on work and temporary traffic control requirements.

20Q. Can you confirm what we are supposed to do with existing culvert C04? The hydraulics report recommends cleaning C04 in place because it may provide additional drainage, but the bid schedule has 8 EA for removal of pipe culvert. Please confirm if C04 is included in the 8 EA removal or if it is to remain in place and be cleaned.

20A. Remove this culvert as noted in the Plans at STA 118+97 Rt.

Questions & Answers

Page | 3

21Q. If the option is exercised where will the government furnish lab be located?

21A. If the option is exercised, the location will be determined jointly between the Government and the Contractor after NTP is issued.

22Q. Is there power and water connections near the field office location?

22A. Refer to Section 637 of the SCRs for field office requirements.

23Q. Does the QCM and Tester have to be 2 separate individuals?

23A. Yes. Please refer to Section 153.02(1) of the FP-14 for QCM requirements.

File details come from the government source that posted it. Updated .