This document contains questions and answers from a pre-bid meeting for Federal-aid Highway Administration Solicitation Number 6982AF22B000014. The solicitation is for the CO FLAP US 36(1) project in Estes Park, Colorado, consisting of reconstructing and rehabilitating 2.3 miles of urban streets to provide a one-way two-lane couplet for traffic through town. Key project elements include construction of a new bridge at Ivy Street, retaining walls, landscaping and irrigation, sidewalks, and a new roundabout. Bidders must adhere to maintenance of traffic requirements and obtain necessary permits from the Town of Estes Park. While the notice to proceed date can be adjusted, incentive completion dates are firm. The contractor is responsible for waste disposal and obtaining any additional environmental clearances for staging areas. Specifications allow flexibility in retroreflective sign brands and stainless steel gauges used. Erosion control will follow standard practices requiring the contractor to develop plans and measures without attached drawings.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for
CO FLAP US36(1) Estes Park Loop
September 29, 2022
Questions Answers
1 Are you requiring a particular brand of RRFB, or will you allow any RRFB that meets the CDOT requirements listed in the bid document?
Any RRFB that meets CDOT requirements and the project specifications will be allowed.
2 Will all existing traffic be expected to be maintained and only slight detours allowed?
Maintenance of traffic is defined in the project Special Contract
Requirements which specifies allowable full roadway and single lane closures. US 36 and US 34 will also be required to adhere to CDOT
Region 4 Lane Closure Strategy and the associated lane closure variance procedures if any closures proposed by the contractor deviate from the project Special Contract Requirements or the strategy.
3 If the NTP date is pushed forward, does the incentive date get pushed as well?
No. The incentive date is a no excuse specification with no additional time allowed under any circumstance. Refer to section 108 in the project
Special Contract Requirements for more information.
4 For the Town of Estes Park permits, does the contractor have to obtain those?
The contractor is required to obtain a Town of Estes ROW Work Permit. A
Floodplain Development Permit is also required. See the project Special
Contract Requirements for additional information.
5 Is the project exempt from any local jurisdiction tax?
Tax exemption status varies from state to state and project to project. It is the contractor’s responsibility to determine State and local tax exemptions.
6 Is there a spot where excess material will be disposed of? Is it the contractor’s responsibility?
It is the contractor’s responsibility to dispose of any waste. A waste disposal area is not defined within the solicitation.
7 Is there a Geotech report included?
Yes, it was uploaded along with the original solicitation documents.
8 Staging areas – will they be cleared by FHWA or is it the contractor’s responsibility? Environmental clearance in terms of
NEPA?
The parcels identified for staging in the Special Contract Requirements were acquired during project development which was included in FHWA’s
NEPA process. It is the contractor’s responsibility to determine if there are any additional environmental clearances and obtain any required permits for the staging areas.
9 The notes on the bearing drawing calls for a min/max shear modulus of 85/175 psi with a hardness of 70. We can’t achieve that. Per the AASHTO design manual 70 duro falls into the 200-
300 psi range. Will 70 duro with a psi range of 200-300 be required or will an alternate be allowed?
Providing a 60 durometer shore A scale elastomer with a shear modulus between 130 to 175 psi is acceptable.
10 Will 14GA stainless steel for the slider for the bearing be acceptable?
14 GA stainless steel is acceptable.
11 I’m working on providing a bid for 6982AF22B000014 – CO
FLAP US36(1) and noticed Erosion Control is listed on the bid schedule, however it doesn’t appear to have any drawings or specifications attached anywhere in the project.
Would you be able to offer any insight?
This is current standard practice where contractor is responsible for developing SWPPP and Erosion Control Measures. See SCR Sections 107
157 in the Special Contract Requirements for additional information.