This document contains questions and answers regarding a solicitation for the CO FTNP MEVE 100(1), Cliff Palace and Mesa Top Loop Road project. The project is located in Mesa Verde National Park and involves reconstructing approximately 9 miles of roadway along the Cliff Palace and Mesa Top loops to improve safety and road conditions. The work includes Schedule A for reconstruction of the 4.7 mile Cliff Palace loop, Option W for the 4.23 mile Mesa Top loop, as well as other options for an entrance roundabout, culvert work, and rockfall repair. The solicitation is a full and open competition estimated to cost between $10-14 million. The Federal Highway Administration is the contracting agency, with work expected to begin in March 2021.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for
CO FTNP MEVE 100(1), Cliff Palace & Mesa Top Loop Roads
December 3, 2020
Questions Answers
1 For line items A0880 60704-0000
CLEANING CULVERT IN PLACE 12
EACH and W0880 60704-0000
CLEANING CULVERT IN PLACE 8
EACH, there are 5 TBD locations in
Tabulation of Quantities Schedule A and
5 TBD locations in Option W; could you please specify an assumed dimension width and length for bidding purposes?
An average 24” diameter and an average length of 40ft
2 For line items A0880 60704-0000
CLEANING CULVERT IN PLACE 12
EACH and W0880 60704-0000
CLEANING CULVERT IN PLACE 8
EACH, do you want debris captured or left in place of exit? If captured, where would you like it disposed on site?
Dispose of material as per FP14 Section 607.02
3 In the plans Sheets D16, D22, and D25, regarding the callouts for coordinating with stone masons, is NPS providing traffic control for this as part of the scheduled traffic control GC is providing or will NPS provide separate from contract?
Per project specification the contractor will remove stones and label them for the NPS masonry staff to replace. This coordination will between conducted by FHWA CFL Project Engineer and the contractor to schedule items of work. The completion of the masonry work will be done during the loop closure for each loop.
4 With potential delays and increasing restrictions due to Covid-19 and Colorado
December weather, could electronic submissions of the proposal please be considered.
No, paper bids must be submitted. However, electronic bid modifications will be accepted.
5 To install the Riprap per the cross sections and typical section(s) on sheets G2-
G3, excavation and backfill will be required. Please confirm the excavated quantities will be paid under 20401-0000
Roadway Excavation.
No payment will be made for earthwork required to install riprap aprons. See FP-14 Section 251.
6 Can electronic CAD files be provided to facilitate takeoffs? Specifically, existing
& final ground (DTMs or contours), alignment and other line work would be very helpful.
No, electronic CAD files will not be provided.
7 On Sheet E15 of the IFB (Pg. 118), the third paragraph states “Ground disturbance activities may begin on March
1, 2020 for schedule A”. We presume that this date should be March 1, 2021, but please clarify.
Correct, the date should be March 1, 2021. Amendment A001 will correct this.
8 On Sheet E30 of the IFB (Pg. 133), Part
203.03(a)((Removal of Headwal)(Salvage
Historic)) states “Store stones at location provided by the NPS, near the culvert location”. Please quantify the term “near”
(i.e. within 10-feet of culvert, 50-feet?
etc.).
Assume average of within 50’ for bidding purposes
9 Is there are designated staging area for the
Option “Y” work?
No staging areas other than those shown in the plans
10 Given that there is no site visit scheduled for this project and given the increasing
COVID-19 restrictions, can the Owner provide plan and profile details for the pipework associated with Option “Y”?
No. The site may be accessed by the general public for purposes of investigating the project location. The contractor may view culvert location by walking to the culvert location. No access will be allowed by vehicles.
11 Can a virtual pre-bid meeting be held for this project?
No, there are no plans for a virtual pre-bid meeting to be held with proposed contractors.
12 Regarding the Option “Y” pipework, does the size of the existing culvert pipe(s) scheduled to be removed match the size of the new pipe scheduled to be installed?
Yes, except for Site 1 which is replacing a 96” with two 48” diameter culverts.
13 Regarding the Option “Y” pipework, please quantify how much silt and/or debris exists within the existing pipe (i.e.
25% full, 50% full, etc.).
The option Y pipework are still in operation and passing flow currently from the inlet to the outlet.
14 Regarding the “Manhole Adjustments” bid Item (Pay Item 60405-0000), no rim elevations are provided for either the existing or the planned Manholes. Please quantity an estimated range in the adjustment (i.e. + 0.1’, 0.5’, etc.)
This is a mill and repave project with minor changes noted in the plans. Field adjustments will be required by the contractor to set manhole rim elevations to the proposed pavement elevation.
15 The specifications for section 302 in solicitation 6982AF20B000036 and FP-14 do not specify which grading designation from table 703-3 should be used for Pay
Item 30202-2000 Roadway Aggregate, Method 2. Please clarify which grading designation should be used for supplemental roadway aggregate, method
2.
Section 302 references Subsection 703.06 Crushed Aggregate. This Subsection allows for aggregate conforming to federal or state specifications.
16 Please confirm type of fence to be removed and reset in bid schedule X?
Will fence require new materials to reset?
See the above picture. No new materials are required to reset.
17 Regarding W1120 62302-1000 SPECIAL
LABOR, HIRED TECHNICAL
SERVICES 20 HOUR, could you tell us where to find specifics on the definition of this line item or provide one?
See Special contract requirements section 623 and FP -14 623 General Labor
18 Due to COVID-19 Global Pandemic will the U.S. Department of Transportation, Federal Highway Administration, Central
Federal Lands Highway Division consider electronic bid submittal?
See question #4
19 Is there a designated staging area for bid schedule Option X? Park Entrance
Roundabout.
The contractor will use existing pullouts and distrubed gravel around this intersection. The maintenance area adjacent to entersection may be used for equipment without tracks for weekend storage. No materail will be stored in Maintenance area.
December 9, 2020
20 Where are the Government supplied boulders located?
The supply of boulders is in the Staging yard and the project will utilize the boulders that will be generate from the slope scaling.
21 Is there a detail available for the “SOIL
EROSION CONTROL, STABILIZED
CONSTRUCTION EXIT”?
No detail is available. Use best management practices.
22 For schedule Y:
Where is the access for the work on schedule Y? Yesterday I tried to access from the area shown on the plans and came to a locked gate about half way to the first culvert where you leave park land and enter BLM land.
Will there be any improvements to the road prior to start of construction? Attached are two pictures of the first portion of the road before the locked gate. The road is narrow and very steep in areas. With the concrete headwalls on the culverts my concern is the area is not
The site can be accessed on foot because of the limitation with staffing at the Park the gate will remain closed during bidding. The site will be opened for construction of Option Y work.
No roadway improvements will be done on this roadway besides the plan drainage improvements.
No plans to improve the roadway before the project begins.
The roadway is used to transport cattle by semi transport in the spring and winter each year. The construction would be completed under 30 minutes delays and the contractor will be able to occupy the entire roadway.
accessible to a concrete mixer truck.
23 The spec states that clearing and grubbing must be done by March 1st. It is difficult to predict how much snow we will get this year but there is a real possibility for significant snow accumulation in
February for clearing and grubbing activities. Should snow removal be included or will contract time be adjusted?
The clearing and Grubbing are mainly due to the migratory birds. The project will identify only falling the few trees and grubbing the trees. So, the falling the tree is the only item that needs to be completed by March 1st.
Snow removal will be part of the work when the contractor starts to occupy the road.
24 Spec Section 623.06 states “Measurement will begin from the time a Qualified
Scaler crew is equipped and begins to climb the slope until they have descended the slope”.
Yes, this statement is correct.
25 It appears that multiple scaling sites lack adequate trees or rock to provide natural anchors for the scalers to tie off. In this case the scalers will need to drill adequate anchors using pneumatic hand drills. Will the drilling of these anchors be paid for under Pay Item Number 63202-0100, Special Labor, Slope Scaling?
Yes, this would be covered under the scaling hours for the crew.
26 Sheet T9 note 2 says “ aggregate base under curb and curb and gutter, is paid under Roadway Aggregate, Method
2. Quantities are included in surfacing summaries.” Sheet T10 note 1 says “ no payment will be made for aggregate base, #4 rebar, and isolation joint sealer required for construction of sidewalk.” Please confirm that the aggregate base under curb and curb and gutter is paid under roadway aggregate method 2 but the aggregate base course
The aggregate base under curb and curb and gutter is paid under Roadway Aggregate, Method 2 and is included in the surfacing summaries quantities.
under sidewalk should be inclusive to the sidewalk item.
27 For the A1260 63316-1000 REMOVE
AND RESET SIGN 7 EACH, W1280
63316-1000 REMOVE AND RESET
SIGN 2 EACH, X0700 61920-2000
REMOVE AND RESET GATE 1 EACH,
and X0980 63316-1000 REMOVE AND
RESET SIGN 3 EACH line items, do you want these to be painted as well?
We do not anticipate existing signs and gate need to be painted.
28 Regarding the (Bid Item Alternative:
Government Furnished Lab) line items, will the government or the Contractor be expected to pay for related water and power?
Yes, the contractor will be responsible for lab location rental, and all necessary utilities.
29 Would a 30" Stop sign require a 4" x 4" post or a 4" x 6" post? If the answer is 4" x 6" post which face is the sign mounted to?
A 4” x 4” wood post
30 For the benches, such as on Sheet D4, will they be placed inside the concrete sidewalk bump-out, or against the outside edge of the concrete?
They will be placed inside the concrete sidewalk bump-out.
December 11, 2020
31 Pertaining to Option Y: Sheet T5 provides bedding and backfill details for metal and plastic pipes beneath roadways, but with the service road being native material, do the culverts need to be backfilled with imported fill, or is native suitable? If imported fill is required, which backfill detail should be applied?
See FP14 Section 704 for culvert bedding and backfill requirements. If the native material meets requirements, then native material may be used. Use the appropriate detail for the site conditions.
Site conditions are unknown, however since we are replacing existing culverts it is assumed that
‘Above Natural Ground’ or ‘On Natural Ground’ would apply.
32 Will the on-site representative require an office trailer and or office space?
The on-site representative for the government FHWA CFL Project Engineer (PE) will not require an office or office space from the proposed contractor.
33 Is a test strip required for HMA paving?
Which phases will it be required?
Yes, a test strip is required for HMA paving per specification. The test strip will be conducted on the Schedule A at a location chosen by the proposed contractor.
34 Are any bore logs available?
No bore logs are available for the project.
On sheet A15 for the parking areas it calls for “10” removal of existing material
(paid as FDR and Roadway Excavation)”.
Is the intent to pulverize (FDR) the top 6 inches, set aside the 6 inches of FDR material, remove and dispose of the bottom 4 inches of sub-grade material, and replace the set aside 6 inches of FDR material?
Yes, that is correct. The 4” of removed material paid under 20401-000 Roadway Excavation and the quantity is included in the Grading Summary and contributes to the paid waste item. The set aside 6 inches of FDR material will be supplemented by Roadway Aggregate, Method 2 as shown in Surfacing Summaries.
35 Will Advance Signing be required if the contractor closes Cliff Palace Road for the duration of Schedule A work? Will any
Temporary Traffic Control be required inside of the road closure?
Yes, advance signing will be required for road closure. No traffic control will be required inside of the road closure.
36 Will Advanced Signing be required for the closure of Mesa Top Road? How will any signs be paid for during the performance of Option W? The Summary of Quantities for Option W does not have a bid item for TTC, Construction Sign.
Will any TTC be required inside of the road closure since the road will be closed to the public?
Yes, advance signing will be required for road closure. It is assumed that signs used for construction of Schedule A will be reused for Option W. No traffic control will be required inside of the road closure.
37 For Option X should we bid all TTC bid items, barricades, cones, Portable
Changeable Message Signs, construction signs, and flaggers under the one bid item
Yes, the lump sum TTC pay item for Option X provides payment for all TTC items. TTC items required will depend on the order of operations determined by the contractor.
listed in the Summary of Quantities for
Option X? Can you tell me which devices you will require for Option X?
38 For the three designated storage/laydown areas, do any of these have power presently?
No, the storage/laydown areas don’t have power currently.
39 Can you confirm the sidewalks are not sealed?
Yes, concrete sidewalks are sealed with clear curing compound. No additional sealers are required after the curing compound is applied.