Question and Answers CA ERFO NP DEVA 2022-1(2)_10 01 2024.pdf

PDF 206 KB Posted

Attached to
CA ERFO DEVA 2022-1(2) Salt Creek Interpretive Trail Federal contract opportunity
Solicitation number
6982AF19B000019
Issued by
Department of Transportation Federal Highway Administration

About this file

This document is a set of Questions and Answers related to a federal contract opportunity for the CA ERFO DEVA 2022-1(2) Salt Creek Interpretive Trail project.

The project involves replacement and reconstruction of approximately 2,871 feet of ABA accessible raised timber boardwalk trail, removal of damaged boardwalk, reconstruction of the trailhead parking lot, and reconstruction of a 400-foot section of roadway. The work must be performed in cultural and natural resource sensitive areas with various environmental constraints, including paleontological monitoring and limitations on large equipment. Prior experience on similar projects within national parks or forests is required. Key work items include thermally modified timber decking, timber structural components, helical piles, concrete work, and removal of existing boardwalk debris. The anticipated construction period is from November 2024 to June 2025, with an estimated project value between $5,000,000 and $10,000,000. The procurement is a total small business set-aside, and is being managed by the Department of Transportation Federal Highway Administration.

View the file

Other files for this federal contract opportunity

Other files attached to CA ERFO DEVA 2022-1(2) Salt Creek Interpretive Trail, newest first.
File Type Posted
Bid Tabs CA ERFO DEVA 2022-1(2) Salt Creek Interpretive Trail.pdf PDF
CA ERFO NP DEVA 2022-1-2 Bid Opening Summary Sched A.pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_10 15 2024.pdf PDF
6982AF24B000019 A006 SF 30 CA ERFO DEVA 2022-1(2).pdf PDF
6982AF24B000019 A005 SF30 CA ERFO DEVA 2022-1(2).pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_10 08 2024.pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_10 02 2024.pdf PDF
6982AF24B000019 A004 SF30 CA ERFO DEVA 2022-1(2).pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_09 30 2024.pdf PDF
6982AF24B000019 INTERESTED VENDORS LIST 09 30 2024.pdf PDF
6982AF24B000019 A003 SF30 CA ERFO DEVA 2022-1(2).pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_09 27 2024.pdf PDF
09 24 2024 Site Visit Attendee List.pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_UPDATED 09 25 2024.pdf PDF
6982AF24B000019 A002 SF30 CA ERFO DEVA 2022-1(2).pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_09 24 2024.pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2) 09 17 2024.pdf PDF
6982AF24B000019 A001 SF30 CA ERFO NP DEVA 2022-1(2).pdf PDF
6982AF24B000019 INTERESTED VENDORS LIST 09 11 2024.pdf PDF
CA ERFO NP DEVA 2022-1(2) Salt Creek Interpretive Trail Plans.pdf PDF
CA ERFO NP DEVA 2022-1(2) Final Report_Signed.pdf PDF
6982AF24B000019 IFB CA ERFO NP DEVA 2022-1(2).pdf PDF
CA ERFO NP DEVA 2022-1(2).Salt Creek Interpretive Trail.DRAFT-FINAL Geotechnical Memorandum.July 2024.pdf PDF
6982AF24B000019 INTERESTED VENDORS LIST 09 03 2024.pdf PDF
CA ERFO NP DEVA 2022-1(2) Cross Sections.pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6982AF24B000019

CA ERFO DEVA 2022-1(2)

SALT CREEK INTREPRETIVE TRAIL

10/01/2024

Question Answer

Received September 11, 2024

1. I wanted to find out if and when a scheduled site showing will occur or has occurred for the above referenced project at Death Valley NP; the Salt Creek Trail Boardwalk?

A non-mandatory site visit is scheduled for Tuesday, September 24, 2024, from 11:00am to 2:00pm PST when NPS staff will be onsite to unlock the gate. NPS staff will not be answering bidder questions. Submit all questions to CFLContracts@dot.gov by the question due date. If planning to attend the Site Visit, please send an email to cflcontracts@dot.gov and Charles Thompson at charles_thompson@nps.gov to RSVP.

The project site is also accessible by foot (approximately five (5) miles roundtrip hike on the road) if accessing at all other times. The road is ladened with sand and difficult to pass. Arrive in the early a.m. hours when it is much cooler.

Provide Name and License Plate information to Charles Thompson at charles_thompson@nps.gov (charles_thompson@nps.gov) at least 24 hrs. prior to accessing the project site for safety concerns.

**Updated 9/25/2024**

Received September 13, 2024

2. I am not finding any details on finishing for the thermally modified wood decking.

Should this wood be coated with either a wood stabilizer or waterproofing per the same standards as regular lumber? Or should it be bare thermally modified wood?

See SCRs Subsection 716.01A.

3. I was looking to run up and take a job walk. Is there a way to open the access gate so we can drive closer, or would we need to hike all the way in?

See response to question #1 above.

Received September 16, 2024 mailto:CFLContracts@dot.gov mailto:cflcontracts@dot.gov mailto:charles_thompson@nps.gov mailto:charles_thompson@nps.gov

SALT CREEK INTREPRETIVE TRAIL

10/01/2024

4. According to Helical Specifications 582.06, “one (1) test pile is to be installed, and a static load test is to be conducted prior to the production pile installation.”

Please confirm if only one test is required before beginning the production pile installation or if there is one test per pile size required?

An amendment will be issued to clarify that one (1) test pile is required for each pile diameter.

Received September 17, 2024

5. Standard cross sections show the boardwalk centered within a 15’ wide construction limit; is it possible to adjust/ offset the construction limit to one side to possibly allow construction equipment access around helical piers in place?

As per Plan Sheet A7, Note 8 an additional 6 ft. of room to the construction limits may be requested on either side of the boardwalk.

Propose the location(s) and side of the boardwalk this space is to be requested.

6. The specification requires commercial ready mix concrete which is likely not feasible for this project due to specified delivery timeframes and location. Please provide the commercial ready mix provider identified under the project due diligence and/ or include a volumetric mix design provision within the specification.

See FP-14 Table 552-4 for remixing and discharge time limits and allowable admixtures. Hydration retarder is allowed.

7. Is there any map of paleontological sensitive areas or are we to assume that the entire project will require monitoring / protection when excavation is in progress?

See Invitation for Bid Appendix B

8. 107.15 (b) limits the GVW for equipment used within the boardwalk construction limits to 12,000 lb. Is it possible to specify a maximum ground pressure limitation as the site damage potential of a 36,000 lb GVW piece of equipment may be much less than one with 12,000 lb GVW depending on

Requirements will be revised in Amendment A002: only rubber tracked equipment, such as skid steers, mini/small excavators, mini cranes, and rubber tired equipment such as off-highway utility vehicles with trailers may be permitted within the boardwalk construction limits. Do not exceed a Ground Pressure of 5.5 psi and Gross Vehicle Weight (GVW) of 32,000

SALT CREEK INTREPRETIVE TRAIL

10/01/2024 configuration. Also, can clarification be provided on the difference between rubber track and steel track equipment under the specification limitations with consideration for the previous comment. Track equipment has much lower ground pressure than rubber tire equipment even with steel tracks.

lb for tracked equipment and GVW of 5,000 lb combined for off-highway utility vehicles and trailers.

Received September 18, 2024

9. Page E-14 Paleontological Monitor Specifications Instruct the Contractor that the Monitor has the Following Education:

“Provide a paleontological monitor who possesses a graduate degree (MS, MA, PhD) with emphasis in paleontology, in combination with one year or more of paleontological mitigation in experience in California, Nevada, or a geological province similar to the project area.”

The following Paragraph States the following :

“ If a monitor is not available for field monitoring, provide a paleontological technician who possesses a minimum of a bachelor’s degree with emphasis in paleontology, in combination with one year of experience in; laboratory preparation, curation and in field monitoring with fossil salvage and treatment.”

There is a substantial cost difference in the Different Levels of Education vs a Bachelor’s Degree.

For Bidding Purposes this specification allows contractors to not comply with sourcing the required monitor and gives an advantage to contractors not trying to Bid per the Requirements of the Contract.

Estimator requests that this specification remove the ability to use a technician and require the owner to request a credit back from Industry Standard Rates so that all proposals are weighted evenly.

Requirements will be clarified in Amendment A002.

SALT CREEK INTREPRETIVE TRAIL

10. There are 2 Bid Items for Bridge Railing :

55601-1300 Bridge Railing Timber (Curb Railing ) 55601-1300 Bridge Railing Timber (Pedestrian Railing) Is this Correct or Should there be a different FHWA Code for each one.

Pay item numbers are correct. Items have unique item codes.

11. A full geotechnical report is requested for the purpose of Helical Pile design.

See the Geotechnical Evaluations and Recommendations Technical Memo dated 7/31/2024 that was included with the Invitation for Bid and attachments included in Amendment A001.

Received September 20, 2024

12. Please clarify the boulder supply. Will the FHA / NPS be providing the boulders for our use, or will the contractor need to procure the boulders? If so, what color and type of boulders need to be provided?

The contractor will need to provide boulders. Requirements will be clarified in Amendment A002.

Received September 26, 2024

13. During a site visit, I noticed that a good portion of the roadway is covered in blown sand. The cut-to-fill tables in the plans list the excess material in the roadway prism as re-use. Are there any gradation requirements for the re-use material, or is that material pre-approved for use?

The existing sand can be incorporated into the work if it is suitable material for the specific items of work. See FP-14 definition of Suitable Material, and see Section 204 for roadway embankment requirements.

14. Traveling west from Beatty to the park entrance on N- 374/Daylight Pass Rd, there is a sign prohibiting trucks. Please confirm if trucks are not allowed on this route. Please also let us know if there are any other route

Commercial trucking is permitted on California Highway 190 through the park. The use of all other park roads by commercial trucking, when such use is in no way connected with the operation of the park area, is prohibited, however trucking is allowed on park roads (including Daylight Pass Road) when hauling materials for use on this project within the park.

SALT CREEK INTREPRETIVE TRAIL

restrictions within the park that would affect construction and material hauling vehicles.

15. Plan sheets D17-D19 (Boardwalk Removal Plan/Quantities), debris items EB 1 thru EB 6, and EB 79 are shown outside the wilderness boundary but also outside the construction limits of the parking lot/trail. Will the Contractor be allowed outside the construction limits to gather these debris with rubber tracked/tired equipment? If not, how are these debris to be removed?

Amendment A003 will clarify the requirements for removal of boardwalk debris outside the wilderness boundary and outside the boardwalk, parking lot, and roadway construction limits.

16. There is a lot of sand that has drifted over Salt Creek Road. The sand will impede the Contractor’s ability to harvest the existing berms adjacent to the roadway for use in the roadway (as depicted in the typical section for roadway reconditioning). Will this sand be removed by others prior to construction? If not, is the sand to be incorporated with the existing berm material?

There is no maintenance planned on Salt Creek Road prior to the project work. The existing sand can be incorporated into the roadway reconditioning work.

September 27, 2024

17. Please clarify if we can dispose of the unsuitable blown sand currently on the road somewhere on the site or in the park, or if it will need to be hauled off site?

See responses above to questions 13 and 16.

September 30, 2024

18. In consideration to the Government’s response to question number 6, we have reached out to every commercial ready-mix supplier we could find within a 3.5-hour radius of the project site and none will quote. Please reconsider allowing the use of volumetric mixers.

See response above to question 6.

File details come from the government source that posted it. Updated .