About this file

This document is a contract amendment for a federal solicitation issued by the Department of Transportation Federal Highway Administration (FHWA). The amendment provides additional information and updates to the solicitation for the CA ERFO DEVA 2022-1(2) Salt Creek Interpretive Trail project.

The key details are:

  • The amendment posts Appendix D, which includes a Nationwide Permit (NWP) Verification Letter from the U.S. Army Corps of Engineers authorizing impacts to Salt Creek for the project. The letter outlines the specific authorized work, conditions, and timelines.
  • The solicitation is a total small business set-aside for the reconstruction and replacement of a 2,871-foot raised timber boardwalk trail, trailhead parking lot, and 400-foot section of roadway that were damaged by recent flash flood events in Death Valley National Park. The estimated price range is $5M to $10M, with an anticipated advertisement in September 2024 and construction from November 2024 to June 2025.

View the file

Other files for this federal contract opportunity

Other files attached to CA ERFO DEVA 2022-1(2) Salt Creek Interpretive Trail, newest first.
File Type Posted
Bid Tabs CA ERFO DEVA 2022-1(2) Salt Creek Interpretive Trail.pdf PDF
CA ERFO NP DEVA 2022-1-2 Bid Opening Summary Sched A.pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_10 15 2024.pdf PDF
6982AF24B000019 A005 SF30 CA ERFO DEVA 2022-1(2).pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_10 08 2024.pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_10 02 2024.pdf PDF
6982AF24B000019 A004 SF30 CA ERFO DEVA 2022-1(2).pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_10 01 2024.pdf PDF
6982AF24B000019 INTERESTED VENDORS LIST 09 30 2024.pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_09 30 2024.pdf PDF
6982AF24B000019 A003 SF30 CA ERFO DEVA 2022-1(2).pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_09 27 2024.pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_UPDATED 09 25 2024.pdf PDF
09 24 2024 Site Visit Attendee List.pdf PDF
6982AF24B000019 A002 SF30 CA ERFO DEVA 2022-1(2).pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2)_09 24 2024.pdf PDF
6982AF24B000019 A001 SF30 CA ERFO NP DEVA 2022-1(2).pdf PDF
Question and Answers CA ERFO NP DEVA 2022-1(2) 09 17 2024.pdf PDF
6982AF24B000019 INTERESTED VENDORS LIST 09 11 2024.pdf PDF
CA ERFO NP DEVA 2022-1(2) Cross Sections.pdf PDF
CA ERFO NP DEVA 2022-1(2) Salt Creek Interpretive Trail Plans.pdf PDF
CA ERFO NP DEVA 2022-1(2) Final Report_Signed.pdf PDF
6982AF24B000019 IFB CA ERFO NP DEVA 2022-1(2).pdf PDF
CA ERFO NP DEVA 2022-1(2).Salt Creek Interpretive Trail.DRAFT-FINAL Geotechnical Memorandum.July 2024.pdf PDF
6982AF24B000019 INTERESTED VENDORS LIST 09 03 2024.pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

A006

The purpose of this amendment is to the amend the IFB as follows:

1. Post Appendix D: 404 Nationwide Permit 20241011 NWP SPL-2024-164V Verification Letter NWP 45

2. Questions are no longer being accepted. Any questions submitted after the question deadline date may not be answered.

*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MY RESULT IN REJECTION OF YOUR BID. (REFER TO ITEM 11)

FEDERAL HIGHWAY ADMINISTRATION

CENTRAL FEDERAL LANDS HIGHWAY DIVISION

12300 WEST DAKOTA AVENUE, SUITE 360

LAKEWOOD, COLORADO 80228

ATTENTION: KELLY PALMER

6982AF24B000019

5. PROJECT NUMBER (If applicable)

CA ERFO DEVA 2022-1(2)

10/14/2024

09/03/2024

0*

*See Item 14

APPENDIX - D

6982AF24B000019

AMENDMENT: A006

10/14/2024

DEPARTMENT OF THE ARMY

U.S. ARMY CORPS OF ENGINEERS LOS ANGELES DISTRICT

915 WILSHIRE BOULEVARD, SUITE 930

LOS ANGELES, CALIFORNIA 90017-3489

October 11, 2024

SUBJECT: Nationwide Permit (NWP) Verification

Federal Highway Administration Central Federal Lands Highway Division Attention: Mr. Nathan Allen 12300 W. Dakota Avenue, Suite 380 Lakewood, Colorado 80228 nathan.allen@dot.gov

Dear Mr. Allen:

I am responding to your request dated July 11, 2024 for a Department of the Army (DA) permit for your proposed project, Salt Creek Interpretive Trail Boardwalk (File No.

SPL-2024-00164). The proposed project is located within Salt Creek in Death Valley National Park, Inyo County, California (Latitude 36.591663°, Longitude -116.988339°).

Because this project would result in a discharge of dredged and/or fill material into waters of the United States, a Department of the Army permit is required pursuant to Section 404 of the Clean Water Act (33 USC 1344; 33 CFR parts 323 and 330).

I have determined construction of your proposed project, if constructed as described in your application, would comply with NWP 45 Repair of Uplands Damaged by Discrete Events. Specifically, and as shown in the enclosed figures (Enclosure 1), you are authorized to:

1. Reconstruct the Salt Creek Boardwalk and parking lot, repair the entrance road, and replace the damaged vault toilet, which were damaged by flood events in August 2022 and August 2023.

2. Authorized work includes up to four temporary crossings across Salt Creek, installed using culverts and approximately 70 cubic-yards of fill material (rip rap and clean fill), that shall be removed following construction of the boardwalk and the permanent placement of approximately 130 cubic-yards of rip rap to be installed along the edge of the entrance road and parking lot.

3. Permanent impact to approximately 0.44-acre intermittent stream (Salt Creek) and temporary impact to approximately 0.15-acre intermittent stream (Salt Creek) are authorized. No impacts to wetlands are authorized.

6982AF24B000019

- 2 -

For this NWP verification letter to be valid, you must comply with all of the terms and conditions in Enclosure 1. Furthermore, you must comply with the non-discretionary Special Conditions listed below:

1. Within 30 days of completion of the authorized work, you must sign and return the enclosed Certificate of Compliance (in accordance with General Condition 30).

2. Prior to initiating construction activities in waters of the United States, the

Permittee shall clearly mark the work area limits with flagging or similar measures to ensure mechanized equipment and personnel do not enter waters of the United States outside of permitted work area. Adverse impacts to waters of the United States beyond the Corps-approved construction footprint are not authorized. Such impacts could result in permit suspension and revocation, administrative, civil or criminal penalties, and/or compensatory mitigation requirements.

3. No work may occur in waters of the United States when flows are present. Work may resume once conditions have dried sufficiently for equipment to reenter waters of the United States.

4. Material removed from waters of the United States must be placed in an upland location. Any material removed from waters of the United States that is not used to repair upland erosion must be disposed of in an upland location where it may not migrate back into waters of the United States.

5. Once work in waters of the United States is complete, the work area shall be stabilized and restored back to its original contours and elevations as much as practical.

6. Pursuant to 36 C.F.R. section 800.13, in the event of any discoveries during construction within waters within the Corps Permit Area (PM insert permit area/APE map) of either human remains, archaeological deposits, or any other type of historic property, the Permittee shall notify the Corps Regulatory Project Manager (Kerrianne Zdimal, 970-259-1764 x1) and the Corps' Regulatory Archaeology Staff (Winston Zack 505-342-3393) within 24 hours. The Permittee shall immediately suspend all work in any area(s) where potential cultural resources are discovered. The Permittee shall not resume construction in the area surrounding the potential cultural resources until the Corps Regulatory Division re-authorizes project construction, per 36 C.F.R. Section 800.13.

6982AF24B000019

- 3 -

This verification is valid through March 14, 2026. If on March 14, 2026 you have commenced or are under contract to commence the permitted activity you will have an additional twelve (12) months to complete the activity under the present NWP terms and conditions. However, if I discover noncompliance or unauthorized activities associated with the permitted activity I may request the use of discretionary authority in accordance with procedures in 33 CFR part 330.4(e) and 33 CFR part 330.5(c) or (d) to modify, suspend, or revoke this specific verification at an earlier date. Additionally, at the national level the Chief of Engineers, any time prior to March 14, 2026, may choose to modify, suspend, or revoke the nationwide use of a NWP after following procedures set forth in 33 CFR part 330.5. It is incumbent upon you to comply with all of the terms and conditions of this NWP verification and to remain informed of any change to the NWPs.

A NWP does not grant any property rights or exclusive privileges. Additionally, it does not authorize any injury to the property, rights of others, nor does it authorize interference with any existing or proposed Federal project. Furthermore, it does not obviate the need to obtain other Federal, state, or local authorizations required by law.

Thank you for participating in our regulatory program. If you have any questions, please contact Kerrianne Zdimal at (970) 259-1764 X 1 or via email at Kerri.L.Zdimal@ usace.army.mil. Please help me to evaluate and improve the regulatory experience for others by completing the customer survey form at https://regulatory.ops.usace.army.mil/ customer-service-survey/.

Sincerely, Shannon Johnson TREC Program Manager

Enclosures

CF:

Michael Reynolds, Superintendent, National Park Service, Death Valley National Park, mike_reynolds@nps.gov Regional Water Quality Control Board, Stateboard401.Stateboard401@waterboards.

ca.gov

6982AF24B000019

Federal Highway Administration, Central Federal Lands

Highway Division ±

Figure 1.

Project Location

Map prepared by: C. Balthrop Date: May 2024 Data source: ESRI World Street Map

Death Valley National Park Salt Creek Boardwalk

ERFO NP 2022-1(2)

Legend Death Valley National Park

Do cu me nt

Pa th:

N :\C

A\ erf on p2

2-1

(2) \E nv iro nm en t\M ap pin g

0 10 20 mi

Inyo County

ENCLOSURE 1

6982AF24B000019

Source: Esri, Maxar, Earthstar

Figure 8.

Impact Map

West

(12/12/23 OHWM)

Death Valley NP Salt Creek Boardwalk

ERFO NP 2022-1(2)

Federal Highway Administration, Central Federal Lands

Highway Division

Map prepared by: Casey Balthrop Date: June 2024 Data source: ESRI Aerial Imagery, Project Files

Do cu me nt

Pa th:

N :\C

A\ erf on p2

2-1

(2) \E nv iro nm en t\M ap pin g

Legend Clearing Limits Wilderness Boundary Temporary Fill Temporary Crossing Temporary Impact Permanent Impact

OHWM

Ephemeral Intermittent

0 10050 Feet

Temporary Fill <0.01 acre

Temporary Fill <0.01 acre

Temporary Equipment Access <0.01 acre

Temporary Equipment Access <0.01 acre

Temporary Equipment Access <0.01 acreTemporary Equipment Access

0.01 acre Temporary Equipment Access

0.07 acre

Temporary Fill <0.01 acre

Temporary Equipment Access

0.02 acre

Temporary Crossing Mat

0.01 acre

Temporary Fill <0.01 acre

Temporary Crossing Mat <0.01 acre

Temporary Crossing Mat

0.01 acre

6982AF24B000019

Source: Esri, Maxar, Earthstar

Figure 9.

Impact Map Center

(12/12/23 OHWM)

Death Valley NP Salt Creek Boardwalk

ERFO NP 2022-1(2)

Federal Highway Administration, Central Federal Lands

Highway Division

Map prepared by: Casey Balthrop Date: June 2024 Data source: ESRI Aerial Imagery, Project Files

Do cu me nt

Pa th:

N :\C

A\ erf on p2

2-1

(2) \E nv iro nm en t\M ap pin g

Legend Clearing Limits Road/Parking Lot Wilderness Boundary Temporary Fill Temporary Crossing Temporary Impact Permanent Impact

OHWM

Ephemeral Intermittent

0 10050 Feet

Temporary Equipment Access <0.01 acre

Temporary Equipment Access <0.01 acre

Temporary Equipment Access

0.07 acre

Temporary Fill <0.01 acre

Temporary Equipment Access

0.18 acre

Temporary Fill <0.01 acreTemporary Crossing Mat

0.01 acre

6982AF24B000019

Source: Esri, Maxar, Earthstar Geographics, and the GIS User Community

Figure 10.

Impact Map

East

(12/12/23 OHWM)

Death Valley NP Salt Creek Boardwalk

ERFO NP 2022-1(2)

Federal Highway Administration, Central Federal Lands

Highway Division

Map prepared by: Casey Balthrop Date: June 2024 Data source: ESRI Aerial Imagery, Project Files

Do cu me nt

Pa th:

N :\C

A\ erf on p2

2-1

(2) \E nv iro nm en t\M ap pin g

Legend Clearing Limits Cut Fill Limits Rock/Riprap Road/Parking Lot Wilderness Boundary Temporary Crossing Temporary Impact Permanent Impact

OHWM

Ephemeral Intermittent

0 10050 Feet

Temporary Equipment Access Accounted for in Figure 9

Temporary Equipment Access <0.01 acre (ephemeral)

Temporary Equipment Access <0.01 acre (ephemeral)

Permanent Fill

0.13 acre

Temporary Equipment Access

0.03 acre

Permanent Fill

0.25 acre (ephemeral)

Permanent Fill

0.02 acre

6982AF24B000019

LOS ANGELES DISTRICT

U.S. ARMY CORPS OF ENGINEERS

CERTIFICATE OF COMPLIANCE WITH

DEPARTMENT OF THE ARMY NATIONWIDE PERMIT

Permit Number: SPL-2024-00164

Name of Permittee: Federal Highway Administration, Central Federal Lands Highway Division, Mr. Nathan Allen

Date of Issuance: October 10, 2024

Upon completion of the activity authorized by this permit and the mitigation required by this permit, sign this certificate, and email it to Kerri.L.Zdimal@usace.army.mil or splregventura@usace.army.mil.

Please note that your permitted activity is subject to a compliance inspection by a U.S.

Army Corps of Engineers representative. If you fail to comply with this permit, you are subject to permit suspension, modification, or revocation.

Please enclose photographs showing the completed project.

I hereby certify that the authorized work and any required compensatory mitigation has been completed in accordance with the NWP authorization, including all general, regional, or activity-specific conditions. Furthermore, if credits from a mitigation bank or in-lieu fee program were used to satisfy compensatory mitigation requirements I have attached the documentation required by 33 CFR 332.3(l)(3) to confirm that the appropriate number and resource type of credits have been secured.

Signature of Permittee Date

ENCLOSURE 2

6982AF24B000019