J5b MAF Modernization_Electrical Clarifications.pdf
PDF 127 KB Posted
- Attached to
- IIJA FUNDED - MAF ATCT MODERNIZATION Federal contract opportunity
- Solicitation number
- 697DCK-25-R-00211
About this file
This document is a set of drawing clarifications for the MAF ATCT (Military Air Force Air Traffic Control Tower) Modernization project. The clarifications detail specific changes to be made across multiple electrical drawings (E107, E108, E109, E110, and MAF-22004347-E057), primarily focusing on renaming panelboard titles from "Existing Panelboard" to "Final Panelboard" for various electrical panels such as EPA, ELPA, ELPT, EPR, EPF, NPR, NLPA, NLPT, NPA, NPC, NPB, and PANEL-A. Additionally, the document includes a technical modification to the Equipment Connection Schedule for TAHU-3 and TAHU-4, changing panel breaker references, and instructions to relocate an existing breaker (NO. 39) to breaker NO. 15 in the Panel NLPT on the Junction Level.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| J5a MAF ATCT and SSC Asbestos OM Plan Aug 2024.pdf | ||
| J5c MAF ACM Removal Report 2005.pdf | ||
| 697DCK-25-R-00211 0003.pdf | ||
| J1a MAF-ATCT MODERNIZATION PROJECT SIGNED DRAWING FINAL.pdf | ||
| J5 - MAF ATCT - RFI Set 1.pdf | ||
| 697DCK-25-R-00211 0002.pdf | ||
| 697DCK-25-R-00211 0001.pdf | ||
| J4 WD TX20250261 03.14.2025.pdf | ||
| J1a MAF-ATCT MODERNIZATION PROJECT SIGNED DRAWING (1).pdf | ||
| J3. RFO - MAF ATCT Modernization - FINAL.pdf | ||
| L1. Past Performance Questionnaire.pdf | ||
| J1 Specifications for MAF ATCT Modernization Project.pdf | ||
| J1c 3900-17_MAF_ATCT_MODERNIZATION_PROJECT FLS.pdf | ||
| L2. Standardized Proposal Breakdown.xls | XLS spreadsheet | |
| 697DCK-25-R-00211.pdf | ||
| J1d EOSH Checklist MAF ATCT Modernization.pdf | ||
| J2 MAF ATCT_LPGBS Bid-Alternate_Updated 7.02.24 (1).pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAF ATCT Modernization Drawings Clarifications
1. Drawing E107:
“Existing Panelboard: EPA will change to “Final Panelboard: EPA” for the title.
2. Drawing E108:
“Existing Panelboard: ELPA will change to “Final Panelboard: ELPA” for the title.
“Existing Panelboard: ELPT will change to “Final Panelboard: ELPT” for the title.
“Existing Panelboard: ELPT-2 will change to “Final Panelboard: ELPT-2” for the title.
“Existing Panelboard: EPR will change to “Final Panelboard: EPR” for the title.
3. Drawing E109:
“Existing Panelboard: EPF will change to “Final Panelboard: EPF” for the title.
“Existing Panelboard: NPR will change to “Final Panelboard: NPR” for the title.
“Existing Panelboard: NLPA will change to “Final Panelboard: NLPA” for the title.
“Existing Panelboard: NLPT will change to “Final Panelboard: NLPT” for the title.
4. Drawing E110:
“Existing Panelboard: NPA will change to “Final Panelboard: NPA” for the title.
“Existing Panelboard: NPC will change to “Final Panelboard: NPC” for the title.
“Existing Panelboard: NPB will change to “Final Panelboard: NPB” for the title.
“Existing Panelboard: PANEL -A will change to “Final Panelboard: PANEL-A” for the title.
5. Drawing E110:
Equipment Connection Schedule:
TAHU-3 and TAHU-4 are using “Panel MDPE breakers 1,3,5 & 32,34,36” will change to “Panel MDPN breakers No. 5 & No. 2” (See drawing MAF-22004347-E056 for reference).
6. Drawing MAF-22004347-E057:
Relocate existing breaker NO. 39 to breaker NO. 15 in the Panel NLPT on the Junction Level.