This document is a Request for Information (RFI) for the MAF ATCT (Midland Air Force Air Traffic Control Tower) Modernization Project, solicitation number 697DCK-25-R-00211, issued by the U.S. Department of Transportation Federal Aviation Administration. The project involves comprehensive modernization of the air traffic control facility, including roof replacement, HVAC system upgrades, electrical system modifications, fire alarm system replacement, and lightning protection system upgrades. Key requirements include night-time work between 12:00 AM and 5:30 AM, maintaining facility operations, and adhering to strict FAA security and operational protocols.

The RFI contains 174 detailed questions and responses covering multiple aspects of the project, such as temporary equipment requirements, electrical and mechanical system specifications, site access, contractor qualifications, and performance expectations. The anticipated award date is November 2025, with a total project value estimated between $4M-$7M. Contractors must submit past performance questionnaires for projects completed within the last 10 years, provide key personnel with specific qualifications, and submit a bid guarantee/bond for 20% of the total proposed amount. The project will require coordination with FAA personnel, compliance with FAA-STD-19G standards, and careful management of the occupied facility during construction.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1

U.S. Department of Transportation Regional Acquisitions Division-AAQ550 Federal Aviation Administration Terminal Acquisitions – Atlanta Office

MAF ATCT Modernization Project

697DCK-25-R-00211

RFIs Set 1

1. Please provide sign in sheet for the site visit.

FAA Response: See Below

2. Placement of crane- may we utilize area at crane placement for staging and off-loading of materials?

FAA Response: Follow the plan in drawing number MAF-D-ATCT-G021 and Division 01 of the specification. If the following requirements are met, it may be possible to temporarily use the crane placement area to stage materials.

1. If there is enough space on the crane's cornered off area.

2. Used temporarily during roof top construction. This area is never allocated for the staging and offloading of items.

3. It does not affect the parking area of adjoining parking spaces in any manner.

4. There is approval from the facility, i.e. the COR.

3. May the -Hatch replacement and additional rung be mechanically affixed? If NO- will “hot-work” be permitted in the Control Tower main control room?

FAA Response: Mechanical attachment is likely acceptable provided it complies with structural codes. "Hot-work" in the Control Cab necessitates FAA approval, a fire watch, and a way to remove weld smoke. Moreover, FAA safety protocol must be followed for the Hot- Work. Refer to the specifications for this project for all things Hot-work.

4. Will there be requirements for “Armed Security” at construction egress gate into the facility?

FAA Response: FAA requires controlled access to the facility. Moreover, follow the direction of the specification.

5. Is the ceiling tile replacement (damaged tiles), required to match existing or is “like and kind” acceptable?

FAA Response: Replacement tiles should match existing appearance and performance, per Division 09 Acoustical Ceilings. “Like and kind” may be accepted pending FAA approval if matching units are unavailable.

6. If matching tiles are required and replacements are unavailable, will these areas require full replacement?

FAA Response: If exact matches are unavailable, localized full replacement in affected areas may be required. Include unit cost in pricing for tile/grid replacement. The FAA will review and determine based on visual continuity.

Page | 2

7. If acceptable, may the windows located @ tower floor levels have the glazing removed for debris removal and new equipment installation?

FAA Response: Temporary removal of glazing on tower floors may be permitted for equipment installation and debris removal, with FAA coordination, debris control measures and restoration to original condition required. Refer to the specification on cutting and Patching.

8. In areas where the AHU are to be replaced, will the existing obstacles and obstructions be removed by the client?

FAA Response: Unless otherwise stated, all responsibility falls on the contractor. Before taking any action on 'obstacles' or 'obstructions', the contractor must notify and obtain written consent from the COR.

9. In the server room and other sensitive areas, where work is to be performed: Will dust control and equipment protection be allowed to remain during the duration of SOW in these areas, or will it have to be installed and removed daily?

FAA Response: Yes, dust control (e.g., plastic sheeting, negative air machines) can remain in place (provided the barriers are non-intrusive) during work in sensitive areas unless otherwise directed. Reference Division 01, paragraphs on environmental protection, construction cleaning etc.

10. Will there require debris control (covered roll-offs/netting) be required during the duration of project?

FAA Response: Yes, debris containment including covered dumpsters or netting is required under Section 01 74 19 Construction Waste Management.

11. Will construction utilities (electricity, water) be furnished by client?

FAA Response: FAA Facility will provide construction utilities (electricity, water) on site and Contractor will furnish labors/materials such as power cables, temporary circuit breakers & water lines… for connection during the Construction. Refer to the specification Section 01 50 00 for detail.

12. During construction will back-up power for facility be required?

FAA Response: Back-up power for facility will be required during construction if needed.

13. Will secondary temp HVAC be required for temp HVAC?

FAA Response: Redundant units to be replaced one at a time, there shall be redundancy at all times, 1 existing + 1 temp.

14. May the SSHO/QCM be secondary role for Superintendent?

FAA Response: No. These are separate and distinct roles. As stated in Factor 3, key personnel positions must be filled by separate individuals.

15. Please indicate whether proposers are permitted to submit clarifications, explanatory notes, or minor administrative adjustments to their proposals at the time of submission, provided that such clarifications would not materially alter pricing, scope, or intent.

Page | 3

FAA Response: Yes, as long as clarifications do not materially change the pricing, scope, or technical intent. Submit as an attachment or explanatory note. Material changes require formal RFI.

16. Please confirm that the work hours for the cab and TRACON are 12:00 AM – 5:30 AM, 7 days a week.

FAA Response: Confirmed. This work window must be strictly adhered to unless otherwise authorized in writing by the FAA. Refer to section 01 10 00.

17. Please confirm that crane placement for the tower may only be done in the northwest side parking lot, and that if several parking spaces are impacted then the FAA will permit this.

FAA Response: Yes. Crane setup is permitted in the northwest lot. Impacted parking spaces must be coordinated and approved with the FAA.

18. Please confirm that the south parking area may be closed entirely for contractor use, including access via the south gate to the unnamed road that leads to Pliska Drive. Also, will this gate be required to be manned whenever left open or unlocked?

FAA Response: Yes. The south lot may be used. The gate must be secured during non-work hours, and manned if left open during operations, per FAA site security protocol and the specification requirements.

19. From time to time, will site access via the northwest gate leading out to the unnamed road be permitted?

FAA Response: Yes, limited access may be granted for deliveries or staging, with prior coordination and security approval.

20. We understand that the gravel area south of the site may also be used for contractor laydown.

Please confirm.

FAA Response: Yes, with FAA coordination. Laydown in this area must not obstruct access or operations of the facility. Refer to G021 of the plan drawing for more details.

21. Please indicate the FAA’s preferred haul route to the site from N. State Hwy 349.

FAA Response: Take Hwy 1788 south from N State Hwy 349 continue south on Hwy 1788 until you reach Airways Drive and make left turn heading East. Make right turn onto Airways Drive then left turn onto Wright Drive. Make right turn onto Windecker Street and 1st left onto N Service Rd. Make final left turn onto N Pliska Dr.

22. It was noted that the small “smoke shack” behind the facility requires some work, but exactly what and the extent of that work is unclear. Please clarify.

FAA Response: Smoke shack is required to be protected from damage during construction per sheet A034 Keynote 14. Additional work at smoke shack is not included in this project.

23. There was a man height UHF or similar type of antenna observed on the low roof portion of the facility. What is this antenna used for, and can it be moved or disconnected during re-roof of the low roof?

FAA Response: The TV antenna described can be removed, however any NAS system antennas will need to be temporarily mounted and not removed (SSC will do this work).

Page | 4

24. We understand that AHU’s 5 & 5A and connected CU’s 5 & 5A are to be removed but not replaced. Please confirm.

FAA Response: This is confirmed. Please see M014 for demolition of AHU 5, 5A, and associated CU’s.

25. During the replacement of the various roof areas, will it be acceptable to temporarily disconnect the Lightning Protection System serving the affected sections?

FAA Response: Yes, it will be acceptable if it disconnects in a few hours only. It must be reinstall immediately after it is finished (this is contingent upon acceptable weather condition).

26. Please confirm that the replacement fire alarm components are “open source” and that no proprietary fire alarm provider for the facility is required to be used.

FAA Response: This is correct.

27. Please confirm that the replacement direct digital control (DDC) components are “open source” and that no proprietary DDC provider for the facility is directed to be used.

28. Will any newly installed electronic components (e.g. fire alarm, DDC, etc.) be required to meet cybersecurity hardening requirements, such as those specified in Unified Facilities Guide Specification 25 05 11 Cybersecurity for Facility-Related Control Systems?

FAA Response: This is not required for FLS systems. Follow security guidelines based on project specifications. 25 05 11 is not in the project specs package.

29. Please confirm if Factor 3 NICET III/IV key personnel requirement may be met via the use of subcontractor, not prime contractor, personnel.

FAA Response: This is acceptable. We require NICET III/IV to sign off on documents, oversee all FLS work, and facilitate the programming of the system. They must be the ones to confirm work/programming.

30. Factor 3 – Technical Proposal, states “Offeror must provide written acknowledgement of the requirement for Project Superintendent is separate, distinct positions that require separate personnel to perform those duties.” Does this imply that simply that no Project Superintendent may wear multiple ‘hats’ and that superintendence shall be their only permitted role?

FAA Response: Yes

31. Per Factor 2: Past Performance, we need to submit a minimum of two (2) PPQs for projects within the last ten years for similar construction projects. It further provides, “Offeror’s may submit CPARS in lieu of PPQ.” Please confirm that the submission of a minimum of two (2) CPARS will satisfy the requirement of Factor 2. A.

FAA Response: Yes, two (2) Contractor Performance Assessment Reporting System (CPAR) reviews maybe be used to satisfy a Performance Questionnaire (PPQ). The CPARS must comply with paragraph VI, Proposal Criteria, Factor 2, Past Performance of the RFO.

Page | 5

32. Factor 3: Key Personnel and Team Composition requires the Offeror to be a licensed/certified sprinkler contractor and installer. Can you please update this requirement to include a licensed/certified sprinkler contractor and installer on our team as subcontractor?

FAA Response: We will not be requiring a fire sprinkler contractor for this project.

33. Please advise who is the current mechanical controls vendor.

FAA Response: Schneider Controls. Con-Tech Control Technologies INC Kelly Buchanan 432- 349-0304.

34. Please advise who is the current fire alarm vendor.

FAA Response: Johnson Controls 806-715-6819 POC: Greg Grey

35. Please advise the field of view the tower must maintain. On the site-walk, discussions of crane placement identified the potential to set up in such a way as not to obstruct direct visibility of approaching/departing aircraft or runway. This would allow work coordination to happen during non-peak flight operations.

FAA Response: Crane placement is restricted to the northwest parking lot. Crane placement must not obstruct line-of-sight to active runways, taxiways, or airspace sectors. FAA may allow limited operation during non-peak hours, but tower visibility is priority. Refer to CSPP coordination. (ref: Sheet G021).

36. Please advise if the specification is open to alternate mechanical equipment manufacturers, provided the specs can be met.

FAA Response: Yes, alternates may be proposed if they meet or exceed the specifications, are system compatible, and are submitted via Substitution Request per Division 01.

37. Please advise if the local facility has a vendor that they use to erect/service antennas.

FAA Response: We do not have a vendor for this.

38. Please confirm that the fire detection and protection does not include replacement or remodel of the fire sprinkler system.

FAA Response: There is no a fire sprinkler system in this facility. No demolition or replacement will occur.

39. Please provide the raised access floor height in rm 118-A (Comm Equipment Room)?

FAA Response: 23.5” Measured from floor to top of tile. The measurement must be taken as approximate. Contractor must field verify before material purchase and construction.

40. Please provide an abatement report.

FAA Response: Attachment in amendment 0003.

41. Can you tell me whether there is any latitude with these personnel requirements (in reference to

1.5. PERSONNEL REQUIREMENTS’)? For instance, will the project manager be required to have a degree, or can this requirement be waived with adequate experience?

FAA Response: Educational degree cannot be waived for experience.

Page | 6

42. Simplex fire alarm control and peripherals meet or exceed all spec’d products in the specifications provided. Will the substitution of Simplex 4100 ES be allowed for this project?

See Attached.

FAA Response: Once a contractor has been selected device specifications can be discussed.

43. The drawings provided with the solicitation has DRAFT watermark on them. Will the IFC or 100% drawings be provided to ensure any changes are captured prior to bidding?

FAA Response: The draft watermark was left inadvertently. The drawings attached to the solicitation are the final version.

44. Drawing A028 Note 2 states to remove door. Does this include the frame?

FAA Response: Yes, remove the frames. All openings created by this must be fire rated to match the surrounding walls.

45. Drawing A028 Note 3 states to repair current exhaust damper.

Is this damper currently functioning?

If not are we to replace damper in its entirety?

Is the current exhaust damper compatible with automatic actuators?

FAA Response: Damper testing will need to be conducted to determine if new Dampers will be required. If they are unable to be repaired or programmed anew then they will need to be replaced in its entirety. The current exhaust dampers should be compatible with automatic actuators.

46. Drawing A028 Note 4 stated to provide engineer judgement. Is it the contractors responsibility to hire an engineer for this firestopping?

FAA Response: A plan is to be submitted by the contractor and approved by the FAA personnel.

47. Drawing A028 Note 8. Please provide shelving dimensions/details being requested for this space>

FAA Response: The dimension is at the discretion of the contractor. The dimension, however, must be reviewed and approved by the COR.

48. Is 24/7 fire watch required during the fire alarm upgrade activities?

FAA Response: Fire watch will only be required if the fire alarm system is down for an extended period of time. Fire watch should not be needed as the existing system should not be removed until the new system has been tested and confirmed working.

49. Is temporary HVAC required throughout construction activities while replacing existing HVAC units?

FAA Response: Yes, refer to MAF-D-ATCT-M011.

50. Is water available to connect to temporary construction offices?

FAA Response: Yes, as per Spec 01 50 00 – Temporary Facilities and Controls, utilities will be made available. However, the contractor is responsible for temporary connections and usage metering if required

51. It was noted that a majority of existing ceiling grid has been damaged at some point. Should any damaged grid be replaced?

Page | 7

FAA Response: Where is it ‘noted’ in any of the bidding documents? If a damaged grid is discovered during construction, contact the COR for a change order.

52. Can you provide photos and dimensions of the existing roof access ladder in ATCT Cab.

FAA Response: Refer to the response below 124-125.

53. Can you provide the ceiling height in ATCT Cab?

FAA Response: 10’3”. The measurement must be taken as approximate. Contractor must field verify before material purchase and construction.

54. Can you provide the existing opening dimensions for the ladder?

FAA Response: 53.5” x 24” The measurement must be taken as approximate. Contractor must field verify before material purchase and construction.

55. If existing fire alarm pipe and wire exceed 40% conduit fill, can it be reused?

FAA Response: Yes, but the contractor is responsible for any damage or outages caused by overfilling of conduit.

56. If existing pipe is reused, does it need to be painted red as note 10 on the drawings requires all fire alarm conduit to be painted fire engine red?

FAA Response: Any pipe that has been touched/used for this project must be fire engine red.

57. Does the existing fire alarm system have to monitor the new HVAC until the new fire alarm system is accepted? If yes, is the new fire alarm contractor responsible for that work?

FAA Response: The new HVAC system must be monitored when it is put into service. If this is finished and in service before the new fire alarm system then the old system must be used.

This will be something to be discussed between the Fire alarm contractor and mechanical contractor to find the best way to make this work.

58. Is the fire alarm contractor responsible for supplying and installing position switches for the dampers or is it only to monitor the position switches that the mechanical contractor supplies and installs?

FAA Response: The fire alarm contractor is responsible for control/monitoring modules for these devices. The position switches may be present currently, but if not they will need to be provided.

59. Is the existing lightning protection system up to current code?

FAA Response: No

60. If we alter the existing lightning protection system as indicated in drawings, current code requires bringing the entire system to current code. Will this be required?

61. Is Cad Welding allowed on lightning protection system?

FAA Response: No, Cad welding is not allowed on lightning protection systems on the Base Building Roof or CAB Roof. However, Cad welding is allowed on ground for LPS.

62. Also, I noticed in the key personnel requirement it states that the offeror must be a licensed sprinkler contractor. Is this correct? To my knowledge there are no sprinklers or sprinkler

Page | 8 system in this project, only fire alarm system. See below in Blue highlight. Can you please clarify this requirement and the requirement for a NICET Category 1 Engineer?

FAA Response: There will not be a requirement for a licensed sprinkler contractor for this project.

63. REF: CAB and Sub-junction Work Hours: From previous experience productive work hours in the CAB and Sub-Junctions levels may only be only 4 hours per night with work stoppage events. Is it correct to assume that the productive work hours will be 4 – 6 hours per night, with work stoppage events during this time?

FAA Response: Yes. Section 01 10 00 (Summary of Work) notes that work in the CAB and Sub-Junction areas must be performed during night shifts and that FAA operations may limit productive work hours between 12:00AM – 5:30AM, with potential work stoppage events due to operational needs.

64. REF: Storage of existing equipment, furnishings and materials. Will the contractor be responsible for removing, storing and reinstalling existing FAA equipment, furnishing and materials on-site in Conex containers or will they have to be stored off-site?

FAA Response: Contractor is responsible for protecting and storing furnishings and equipment removed from work areas. On-site storage in lockable Conex containers is acceptable, provided space and FAA coordination are maintained. Off-site storage is not required unless coordinated. Refer to the specification for more information.

65. REF: Protect all existing fire alarm devices with covering is areas where work is to be performed with coverings. Does the contractor need to remove the protective covers at the end of each work shift and install protective covers at the beginning of each work shift? Or can the protective covers remain in place during non-work hours?

FAA Response: These must be placed at the beginning of each shift and removed at the end of each shift.

66. REF: Removal of existing ceiling tiles. If required, in the tower cab and base building, will the contractor be allowed to remove all the ceiling grid and tiles, in its entirety, then install new grid and tile? Or must we remove and replace it in sections?

FAA Response: Contractor may propose full-grid removal for efficiency, but partial/phased removal must be used where continuous occupancy or phased access is required. Submit approach and sequencing for FAA review during construction.

67. Tower cab air filtration systems. Will HEPA filter air filtration units be required for all CAB work?

(MAA)

FAA Response: Air scrubbers to mitigate dust during construction must have HEPA filters.

68. REF: Project Staffing. Will the FAA require a superintendent and QC to cover both day and night shifts?

69. REF: Date of award. Please advise on the expected award date for this project.

FAA Response: The anticipated award date is Nov 2025.

70. REF: Special requirements. Are there any special airport requirements for crane use?

FAA Response: Contractor must coordinate with airport operations for crane scheduling. FAA Form 7460 must be submitted and approved for crane operations. Contractors must comply

Page | 9 with safety zones and submit lift plans for review. Refer to section 01 10 00 of the specification.

71. Daily site and project clean-up. Can you provide the current janitorial service company that maintains the ATCT & Base building?

FAA Response: Unique Cleaners National.

72. REF: DDC / Building controls contractor.

a. Is there a preferred controls contractor currently used?

FAA Response: No preferred contractor, current controls run by Con-Tech Control Technologies INC

b. Can you provide the POC information?

FAA Response: 806-715-6819 POC: Greg Grey

73. REF: Fire Alarm contractor.

a. Who is the preferred fire alarm contractor for the facility?

FAA Response: This is up to the contractor, we have an open bid.

b. Can you provide the POC information?

FAA Response: See above.

74. REF: Quality control. Is a third party CQC firm required, even though the contractor will be providing an on-site QC Manager?

FAA Response: No, third-party CQC is not required since an on-site QC Manager is provided, per RFO Factor 3.

75. REF: On-project management. Does the Superintendent, SSHO, and QC manager need to be 3 separate individuals?

FAA Response: Superintendent, SSHO, and QC must be separate individuals with no dual roles.

76. REF: Buy American. Is this project including any Buy-American Act requirements?

FAA Response: Yes. The project is subject to Buy American provisions as defined in the SIR.

77. REF: Tax Exemption. Is this project tax exempt?

FAA Response: No, this project is not tax exempt.

78. REF: On-site trailers.

a. Confirm the number of trailers required for the FAA.

FAA Response: one (1)

b. What are the requirements for the FAA trailer / trailers?

FAA Response: Must include workspace, HVAC, power, lighting, security and connectivity. Coordinate utility hook-ups (power). Refer to the specification section 01 50 10.

79. REF: Duct work cleaning. Can the FAA provide quantities of duct work to be cleaned?

FAA Response: IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO SURVEY AND VERIFY

EXISTING CONDITIONS PRIOR TO STARTING WORK.

Page | 10

80. REF: Dwg. No. MAF-221004347-A031 - This sheet and details identify EZ Path fire stopping for cable / wire in new wall construction and not EZ Path for retrofit fire stopping.

a. Is the govt. contemplating that the existing cables / wires / conduits will be disconnected, removed, EZ Path be installed and the cables / wires / conduits will be reinstalled?

FAA Response: We require the penetrations to be fire stopped, but it is up to the contractor to decide and submit to us for approval. I would not recommend removing and reinstalling.

b. Or does the govt. wish the contractor to use EZ Path retrofit fire stopping? Which allows for the wires / cables / conduits to remain in-place.

FAA Response: We require the penetrations to be fire stopped, but it is up to the contractor to decide and submit to us for approval.

81. REF: Dwg. No. MAF-22004347-F002 - Second and Third Floor Lower Intermediate Level dwgs.

and Geneal Note 3 identifies control module for door opener (addressable control module) behind door and inside the exterior wall. Is this the correct location and not a drafting error?

FAA Response: We were planning on having door holders for these devices which can be floor/wall mounted or self-contained, but this is up to the contractor to choose. This location is just a statement that these doors will need one installed.

82. REF: The circle symbol with “M” is not identified in the Legend. Please identify this symbol.

FAA Response: “M” stands for electrical motor; on MAF-D-ATCT-M033, “M” indicates the exhaust fan motor.

83. REF: Dwg. No. MAF-22004347-F003 - Fourth and Fifth Junction Level dwgs. and Geneal Note 3 identifies control module for door opener (addressable control module) behind door and inside the exterior wall. Is this the correct location and not a drafting error?

FAA Response: We were planning on having door holders for these devices which can be floor/wall mounted or self-contained, but this is up to the contractor to choose. This location is just a statement that these doors will need one installed.

84. REF: The circle symbol with “M” is not identified in the Legend. Please identify this symbol.

FAA Response: “M” stands for electrical motor; on MAF-D-ATCT-M033, “M” indicates the exhaust fan motor.

85. REF: Dwg. No. MAF-221004347-M008. Please confirm there are no F/A devices, i.e. smoke or heat detectors on the junction level or in the Supply / Exhaust Fan enclosure.

86. REF: Dwg. No. MAF-221004347-G021 - There are no locations identified where a contractor or

FAA’s site trailers are to be located.

a. Please provide locations for the contractor and FAA’s site trailers.

FAA Response: Refer to MAF-D-ATCT-G021 for the general location (SHEET NOTES 6).

Exact locations are not pre-defined; contractor may propose trailer placement with FAA approval.

b. Where does the contractor access temporary power for the site trailers?

FAA Response: Using existing Panel MDPN or Panel ELPA2 with spare breakers available in the E/G building.

Page | 11

c. What are the requirements for the FAA’s site trailer?

FAA Response: Must include workspace, HVAC, power, lighting, security and connectivity. Coordinate utility hook-ups (power). Refer to the specification section 01 50 10.

d. Is the contractor responsible for running power, water and sewer to office trailers? If so, please provide details.

FAA Response: Yes. See the drawings and specifications for details.

e. Can the contractor use gas generators for power?

FAA Response: Gas generators may be used with noise mitigation and the approval and coordination of the facility. However, the facility prefer for the contractor to use electrical outlets outside.

f. Is the contractor responsible for weekly cleaning of the FAA’s trailer / trailers?

FAA Response: Yes. Refer to Section 01 50 00

87. REF: Dwg. No. MAF-D-ATCT-A032 & A033 - Identifies portions of the ceiling to be removed or demolished due to HVAC work. The drawing does not identify the portions of the ceilings to be removed or demolished due to 1) F /A work i.e. installation of new devices, conduits and wire, smoke dampers, duct detectors, or 2) plumbing work i.e. new roof drains and piping, 3) HVAC and VAV temporary work, 4) fire rated door / access panels work, 5) fire stopping work, and 6) roof structural support and decking work, etc. Is it the govt.’s intent for the contractor to remove suspended ceiling systems for the F / A, HVAC, plumbing, electrical, fire rated door / panel, fire stopping work, roof structural and decking work, etc.?

FAA Response: Yes. The contractor is responsible for removing and replacing suspended ceiling systems as necessary to perform all work indicated in the contract documents. All removals must be coordinated to minimize disruption, and ceiling systems shall be reinstalled to match existing per Specification and plan drawings. Any removals beyond those reasonably inferable from the contract documents shall be addressed in coordination with the FAA COR prior to execution. Refer to sheet note and legend on MAF-D-ATCT-A032

88. REF: If the contractor submits a price proposal based on the govt.’s direction of only removing and reinstalling ceiling tiles as per the dwgs. and it is determined that to perform the work the contractor must remove the ceiling grid. Will the Government issue a modification for the cost of removing the grid and installing new?

FAA Response: If field conditions require removal and replacement of the ceiling grid beyond the scope shown in the bid documents, and such work is not already indicated in the drawings or specifications, the FAA will evaluate the change. A contract modification may be issued for verified additional work in accordance with AMS 3.10.1-15, contingent on prior written approval by the FAA COR. The contractor must provide supporting documentation, including field verification, justification for removal, and cost breakdowns, before proceeding. All replacement ceiling systems must comply with Specification, and finishes must match existing or as specified in the architectural finish schedule.

89. REF: If the contractor submits a price proposal based on the Government direction of removing and reinstalling only the portions of ceiling tiles identified on the dwgs. and it is determined that to perform the work the contractor must remove more than what is identified on the dwgs. Will the Government issue a modification for the cost of removing additional ceiling tiles.

Page | 12

FAA Response: Yes. If work necessitates greater ceiling removal than shown, submit an RFI with photos and scope change. Contract modification may be issued based on review.

90. Will the Government consider revising the scope and drawings to include removing the suspended ceiling system and install new?

FAA Response: Not at this time. Contractor may propose full ceiling system replacement as a VE (value engineering) item, subject to FAA review.

91. Will the areas / rooms where work is being performed be vacant?

FAA Response: Most areas will be occupied during work.

92. What areas / rooms will be vacant and what areas / rooms will be occupied?

FAA Response: The FAA will provide a phased occupancy plan post-award. Expect night work for active operational zones

93. Will the contractor be responsible for moving, storing and moving back furniture?

FAA Response: Contractor is responsible for relocating, protecting, and restoring furnishings in work zones. Coordination with FAA required.

94. What areas / rooms will be non-standard hours / night work? (WE)

FAA Response: Cab and TRACON must be worked on between 12:00 AM and 5:30 AM.

Additional areas requiring off-hour access will be identified post-award.

95. REF: Dwg. No. MAF-D-ATCT-A034 - Demolition Sheet Note 7 states – Remove and save for reuse gutter and downspouts. If the contractor submits a price proposal based on the govt.’s direction of remove and save for reuse gutter and downspouts and it is determined that the gutter cannot be removed without damaging the gutter, thus cannot be reused. Will the govt. issue a modification for the cost of installing new gutters and downspouts?

FAA Response: Yes. If, during removal, it is determined and documented that the existing gutters and downspouts cannot be salvaged for reuse without damage, the FAA will evaluate the condition. A contract modification may be issued for the cost of new gutters and downspouts, provided:

1. The contractor notifies the FAA COR in writing prior to proceeding with replacement work.

2. The condition is documented with photos, field reports, and removal procedures attempted.

3. The replacement materials meet Specification requirements, including gauge, finish, and profile, or match existing profiles if approved by the COR.

The FAA reserves the right to direct an alternate product or installation method if it meets or exceeds performance criteria.

96. REF: Demolition Sheet Note 3 states – Existing through parapet scupper, protect from damage. If the contractor submits a price proposal based on the govt.’s direction of protecting and reusing existing scuppers and it is determined that the scuppers cannot be protected and reused due to demolition of the existing roof. Will the Government issue a modification for the cost of installing new scuppers?

FAA Response: Yes. If field conditions demonstrate that existing parapet scuppers cannot be protected and reused without compromising function, waterproofing integrity, or appearance, the FAA will review the condition. A contract modification may be issued for the installation of new scuppers, provided:

Page | 13

1. The contractor notifies the FAA COR in writing before performing any replacement work.

2. The condition is documented with photographs and a brief field report outlining why protection and reuse were not feasible.

3. New scuppers comply with Specification requirements, match the material, gauge, and finish of the existing or basis-of-design, and are installed per manufacturer’s recommendations and project details.

The FAA reserves the right to direct an alternate product or installation method if it meets or exceeds performance criteria.

97. REF: Demolition Sheet Note 17 states – Remove metal coping cap. There is only one note call-out on the dwg. Please confirm that all existing parapet walls metal coping cap on the base building will be removed.

FAA Response: All base building parapet coping is to be removed and replaced as shown in details A034–A042.

98. REF: Sheet Notes call out symbol “12” between column lines F and E, and 3.9 is point to nothing.

a. Is this a drafting error or should there be walkway pads drawn on the plan?

b. Please identify the walkway pads on the drawing.

FAA Response:

a. Keynote 12 should have been pointed to the walkway pads which are shown in the base building roof plan.

b. They are already shown in the base building roof plan through the parallel lines between units.

99. REF: Dwg. No. MAF-D-ATCT-A036, A037 & A039.

a. Is it the Government’s intent for the contractor to make all temporary and new penetrations through 1 hr. and 2 hr. walls 1 hr. and 2 hr. rated or make all temporary, new and existing penetrations 1 hr. and 2 hr. rated?

FAA Response: All penetrations through rated walls need to match the walls rating.

b. If it is the govt.’s intent to make all existing penetrations 1 hr. and 2 hr. rated. Due to the unknown amount of fire-stopping to be performed throughout the project, will the FAA provide an allowance amount for this work?

FAA Response: Areas are called out on drawings where existing are required, but new penetrations will be covered by the contractor in their submittal.

100. REF: Dwg. No. MAF-D-ATCT-A041 - Dtl. F4 and F3 identifies a steel stair from the tower level to the base building roof level. There is no detail showing how the contractor is supposed to anchor the stair to the tower wall or base building roof.

a. Are the stairs to be free standing or anchored to the tower wall?

b. Are the stairs to be free standing or anchored to the base building roof?

c. If free standing, is the contractor to provide heavy duty rubber protections pads between the stairs and roof membrane?

FAA Response:

a. It is not to be anchored to the ATCT wall since there is an expansion joint between the ATCT wall and the roof. The maximum distance allowed between the ATCT wall and the top of the platform is ½” vertically and horizontally.

Page | 14

b. It is a free-standing premanufactured platform and steps and directly placed on the roof with ballasted support components which require protection pads similar to the one provided for the portable guardrail base.

c. This is a delegated design per the specification section 05 51 19 Metal Grating Stairs.

Heavy duty rubber protection pads are required

101. REF: Dwg. No. MAF-D-ATCT-A042 Dtl. D4, please clarify if the contractor is to reuse existing parapet scuppers or install new.

FAA Response: The contractor is to install new scupper in accordance with keynote 38

102. REF: Dtl. D7, dwg. symbol call outs 20 and 19 do not point to anything. Is this a drafting error?

FAA Response: In detail D7/A042, keynote 19 should have been pointed to the roof hatch guardrail and keynote 20 should have been pointed to the self-closing safe gate. Please refer to detail A5 & A6/A-042 for the roof hatch guardrail and the self-closing safe gate.

103. REF: Dwg. No. MAF-D-ATCT-S014. Please confirm that the metal roof decking between columns grid lines A-D and 1-4 is existing unfilled metal deck.

FAA Response: The original drawings call out an existing insulated concrete fill on the deck, but during field investigations during design this was not identified when drilling through the roof membrane. The contractor should notify the COR if concrete fill is discovered upon removal of the roof membrane per General Sheet Note C.

104. REF: Dwg. No. MAF-D-ATCT-M011 - Temporary Equipment Requirements Note 3 states - A

QUALIFIED TECHNICAN MUST BE ON SITE FOR A MINIMUM OF 4 HOURS PER WEEK WHILE THE

RENTAL EQUIPMENT IS IN OPERATION TO INSPECT, CLEAN, AND MAINTAIN THE EQUIPMENT.

Please confirm that this is a requirement of the contract and the contractor shall include costs in their proposal for such.

FAA Response: This is confirmed. Comply with note 3 on sheet M011.

105. REF: Temporary Equipment Requirements Note 12 states - PROVIDE LIGHTING IN TEMPORARY

EQUIPMENT AREAS PER OSHA AND FACILITY SECURITY REQUIREMENTS. COORDINATE LIGHTING

REQUIREMENTS WITH SITE.

a. Can the govt. provide what temporary lighting requirements need to be met?

FAA Response: No, Following the FAA-STD-19G for details.

b. Where will the power for the lights be taken from?

FAA Response: Use existing outlets from FAA Facility to connect the temporary Lights via extension cords if needed (When using the lights on the Base Building or CAB Roof in the night work if local FAA required).

106. REF: Dwg. No. MAF-D-ATCT-M011. Please confirm TAHU-1, TAHU-2 and TAHU-5 do not need a back-up redundant unit.

FAA Response: Redundant units to be replaced one at a time, there shall be redundancy at all times, 1 existing + 1 temp.

107. REF: Dwg. No. MAF-D-ATCT-M011 - Shows TAHU-5 duct work entering through a window in the

Breakroom and Dwg. No. MAF-22004347-F001 shows what cabinets or countertops are where the ductwork is entering.

a. Can the govt. provide information if the contractor is going to be required to remove and reinstall cabinets or countertops?

Page | 15

FAA Response: DRAWINGS ARE DIAGRAMMATIC IN NATURE, there is enough space to route the ductwork without the need to remove/reinstall cabinets or countertops. The contractor shall avoid removing cabinets and countertops.

b. Please confirm that the temporary duct work is to be installed above the ceiling grid and does not connect into the existing duct work.

FAA Response: Temporary ductwork to be routed above ceiling and does not connect into existing ductwork. See M011 for routing information

c. Can temporary duct work be abandoned in place after use?

FAA Response: NO.

d. Can the thermostat wire be free wire ran laying on ceiling grid and not in conduit?

FAA Response: POWER WIRING AND CONTROL WIRING MUST BE INSTALLED IN RGS

CONDUIT.

108. REF: Dwg. No. MAF-D-ATCT-M012 - Secondary Requirements Note 10 states - SUBMIT FOR

APPROVAL DESIGN DRAWINGS SHOWING PROPOSED AIR CONDITIONERS AND DUCTWORK

INSTALLATION REQUIREMENTS INCLUDING FOUNDATIONS, ANCHORAGE, BRACING AND

SUPPORTS. SUBMITTALS MUST BE SIGNED AND SEALED BY A LICENSED PROFESSIONAL ENGINEER

IN THE STATE OF TEXAS. WORK ASSOCIATED WITH THE SECONDARY COOLING EQUIPMENT MUST

BE ACCOMPLISHED IN ACCORDANCE WITH PROJECT SPECIFICATIONS. WORK MUST BE

ACCOMPLISHED IN A PROFESSIONAL MANNER AND COMPLETED BY PERSONNEL EXPERIENCED IN

THAT PARTICULAR ASPECT OF INSTALLATION. Please confirm this requirement is for the 2 direct expansion ductless split systems only, and this requirement does not pertain to the replacement of AHU 2 / 3 or any other base building AHUs.

FAA Response: Note 10 on M012 applies to the temporary equipment located on the temporary equipment sheets M011 to M013.

109. REF: Secondary Requirements Note 14 states - EACH AIR CONDITIONER, FOUNDATION, ANCHORAGE AND STRUCTURAL STEEL SUPPORTS MUST BE DESIGNED TO WITHSTAND WIND AND

SEISMIC FORCES PER PROJECT SPECIFICATIONS. Please confirm this requirement is for the 2 direct expansion ductless split systems only, and this requirement does not pertain to the replacement of AHU 2 / 3 or any other base building AHUs.

FAA Response: Note 10 on M012 applies to the temporary equipment located on the temporary equipment sheets M011 to M013.

110. REF: There is not note or drawing indicating split system condensation lines. Each unit should have a condensation line daylighting or connection into a drain line.

a. Please confirm that each system requires a condensation line.

b. Please identify the line and line run.

c. Will there be a need for condensation pumps?

FAA Response: Requirements for condensate piping and condensate pumps can be found in the keynotes on M018, M020, and M021. Route condensate piping for roof mounted equipment to the closest roof drain (see sheet A038) or for interior equipment route to closest floor drain. Please refer to schedule notes M022 for condensation pump information. Review specifications for additional requirements.

111. REF: Dwg. No. MAF-D-ATCT-M018 – No equipment, piping or duct work support call outs or dtls.

Can the govt. provide AHU, CU, piping and duct work rails / curbs / supports dtls.

FAA Response: Refer to MAF-D-ATCT-A041.

112. REF: CU-5A, CU-5B and AHU-5 RS / RL piping. Dwg. does not identify piping.

Can the govt. revise drawing to show RS /RL piping from CU-5A, CU-5B to AHU-5?

Page | 16

FAA Response: Refer to MAF-D-ATCT-M009 - General Notes - Y. Coordinate final routing with the FAA COR

113. REF: Dwg. No. MAF-D-ATCT-M018 – Sheet Note 10 states - PROVIDE SINGLE PORT ETHERNET

WALL PLATE/BOX.

a. Confirm that this is cover plate and box only and does not include conduit or wire.

b. Does this box connect into existing circuit (conduit and wire)?

FAA Response:

a. Installation requires single port Ethernet wall plate, box, wiring and conduit.

b. The box/Ethernet cable must be connected to Network Switch located in TE3-5 rack in

Equipment Room 118-A. Refer to DDC System Network Architecture Diagram and Sheet Notes 1 & 3 on contract drawing MAF-D-ATCT-M039

114. REF: Dwg. No. MAF-D-ATCT-M019 – Sheet Note 13 states - PROVIDE SINGLE PORT ETHERNET

WALL PLATE/BOX.

a. Confirm that this is cover plate and box only and does not include conduit or wire.

b. Does this box connect into existing circuit (conduit and wire)?

FAA Response:

a. Installation requires single port Ethernet wall plate, box, wiring and conduit.

b. The box/Ethernet cable must be connected to Network Switch located in TE3-5 rack in

Equipment Room 118-A. Refer to DDC System Network Architecture Diagram and Sheet Notes 1 & 3 on contract drawing MAF-D-ATCT-M039

115. REF: Dwg. No. MAF-D-ATCT-M019 – Sheet Note 3 states - REF:ER TO C3/M600 FOR EQUIPMENT

RAIL DETAIL.

a. There is not C3/M600, can the govt. provide equipment rail dtl.?

FAA Response: Refer to MAF-D-ATCT-A041, MAF-D-ATCT-M023

b. Can the govt. provide AHU, CU, piping and duct work rails / curbs / supports dtls.

FAA Response: Refer to MAF-D-ATCT-A041, MAF-D-ATCT-M023

116. REF: Dwg. No. MAF-D-ATCT-M024 – Dtl. F8 note states - EQUIPMENT SUPPORT RAIL. REF TO

ARCH DWGS. Dwg. does not exist. Can the govt. provide dwg.?

FAA Response: DWG MAF-D-ATCT-A041 exists in the full package with the detail F8.

117. REF: Dtl. D8 Condensate Drain Trap Dtl. Is this dtl. for the CU roof top condensation drainpipes?

FAA Response: This is a general detail for all condensate pipe traps.

118. REF: Dwg. No. MAF-D-ATCT-E100 & E101 Demolition Sheet notes 1, 2, and 3 states – Remove associated disconnect switch, conduit and wiring back to source. Remove associated conduit and wiring back to source. Mark breaker as spare.

a. Where is “source” located and what is “source”?

FAA Response: "Source" means the electrical panel and breaker the wire is connected to.

b. After de-energizing and disconnecting conduit and wire, can wire and conduit be abandoned in-place?

FAA Response: Remove the wiring and conduit. Do not abandon in place.

119. REF: Demolition Sheet notes 1 state – Existing mechanical equipment to be replaced and re-fed.

Can the contractor reuse the existing conduit and wire for new mechanical equipment?

FAA Response: No.

Page | 17

120. Ref: Sheet M023, detail F3 shows insulated duct.

Are we installing any insulated duct and is the existing duct insulated?

FAA Response: Yes, refer to project specification section 23 31 13

121. Ref: Document J3 RFO page 5 Volume I, F. A letter from a Treasury-approved bonding company confirming bonding capacity at 100% of the propose price. The solicitation item 13B is marked that an Offer Guarantee is required. Is the offer guarantee stating that a bid bond is required for this project?

FAA Response: Yes, corrections, only 20% of the proposed price is required.

122. Ref: Document J1d EOSH Checklist page 3. Item Arc Flash Hazard is marked Yes as being required, however the Issue states, “Based on the following conditions, an Arc Flash analysis is not required:” Please confirm an Arc Flash Analysis and short circuit/arc flash hazard calculation study are required to be performed for this project.

FAA Response: Yes, AFHA & Short Circuit/Arc Flash Calculation study are required to be performed on this project.

123. Ref: Document J1d EOSH Checklist page 4. Item Safety – Confined Space is marked Yes that work will be conducted an a confined space, however, it is not marked that the work will be conducted in a Permit required confined space. Please confirm that confined space work on this project WILL NOT require a permit.

FAA Response: Yes. Confined space entry is anticipated but will not require permit-required confined space protocols. Follow standard confined space procedures per FAA safety policy and OSHA 1910.146.

124. Ref: The cab.

a. Please provide detailed photos of the existing cab roof ladder in the closed position as well as opened, at different angles.

FAA Response:

Page | 18

Page | 19

b. Please provide detailed measurements of the existing cab roof ladder in the closed position as well as interior opening dimensions, height and width dimensions of all walls, existing interior ladder height, roof hatch opening dimensions, lengths of any bracing, angle iron, etc.

FAA Response: The following measures must be taken as approximate. Contractor must field verify before material purchase and construction. Closed position 53.5”x24”, interior opening dimensions 53.5”x24”, height and width dimensions of all walls 43” from ceiling to bottom of roof, existing interior ladder height 11’3” floor to ceiling, roof hatch opening dimensions 30”x36” ID, 24” ladder frame to purling’s.

c. Please provide detailed photos and dimensions (height, width, length) of the existing roof hatch curb and lid.

FAA Response: Refer to the pictures below:

The following measures must be taken as approximate. Contractor must field verify before material purchase and construction.

Page | 20

125. Ref: Please provide multiple photos from different angles of the cab roof, roof drains, scuppers, parapet walls and terminations (t-bars), parapet wall cap, conduit on walls, and lightning protection air terminals, rods, devices, cable, etc.

FAA Response: Refer to the pictures below:

Page | 21

Page | 22

Page | 23

126. Document J1a MAF-ATCT Modernization Project Signed Drawings

a. The project drawings are stamped “DRAFT”. Will a “For Construction” set of drawings be issued for this project prior to bid?

FAA Response: The draft watermark was left inadvertently. The drawings attached to the solicitation are the final version.

b. If “For Construction” drawings are issued after award, will any changes made in the project drawings be considered for a cost and time contract modification?

FAA Response: The draft watermark was left inadvertently. The drawings attached to the solicitation are the final version.

127. Ref: Specification 01 50 00 1.3 Use Charges

a. Will separate service meters be required and installed for temporary power and water usage?

FAA Response: No, Contractor will use existing panel MDPN & panel ELPA2 in the E/G Building with spare breakers available for temporary power & use existing water outlets from Facility for water usage.

Page | 24

b. Is wi-fi service required to be provided for the FAA field office? If so, is satellite service allowed?

FAA Response: Yes. Satellite is acceptable if:

1. Cable/fiber not available.

2. Facility approves it.

3. There is no interference with NAS communication

128. Ref: See note 7 on PDF page 38 – Dwg. No. MAF-D-ATCT-M011.Are we supposed to run the temp duct and diffusers below the existing suspended ceiling?

FAA Response: Temporary ductwork to be run above ceiling, refer to M011 for temporary ductwork information.

129. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

FAA Response: Yes. As specified in the RFO and few specific sections, these roles are distinct and must be filled by separate personnel with no overlap.

130. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

FAA Response: No. Refer to paragraph VI, Proposal Criteria, Factor 4, Schedule requirement of the RFO. The period of performance will begin upon receipt of the Notice to Proceed (NTP) which occurs following the preconstruction meeting.