RFI Amendment 00003 100925.pdf
PDF 89 KB Posted
- Solicitation number
- 6973GH-25-R-00206
About this file
This Request for Information (RFI) dated 10/09/2025 with solicitation number 6973GH-25-R-00206 concerns Photovoltaic (PV) Battery Energy Storage System (BESS) units for the Federal Aviation Administration (FAA). The document addresses a vendor's inquiry about whether the Solar and BESS components of the requirement can be separated, with the FAA explicitly stating that their requirement is for a complete deployment-ready portable PV/BESS microgrid configured system solution as detailed in the Statement of Work (SOW). The FAA response clearly indicates that providing only the BESS system component would not be acceptable, emphasizing the need for an integrated solution.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI – 10/09/2025 – 6973GH-25-R-00206; PV BESS units
1. Can you please clarify whether the Solar and BESS portions of the requirement can be separated, and if it would be acceptable to provide only the BESS component.
RESPONSE - FAA’s requirement is for a deployment ready portable PV/BESS (microgrid configured) system solution as stated in the SOW. It would not be acceptable to only provide the BESS system component.
File details come from the government source that posted it. Updated .