QA_07-18-24.pdf
PDF 94 KB Posted
- Solicitation number
- 69056724B000012
About this file
This document contains a set of Questions and Answers related to the Swiftcurrent Spur Road Rehabilitation project, Federal Contract Opportunity 9a9956f6dcef4d06b852a0206d159d52. The key details are:
The project, MT NP GLAC 14(6), involves the rehabilitation of the Swiftcurrent Spur Road. The solicitation is issued by the Department of Transportation Federal Highway Administration. The Questions and Answers provide clarification on the size and source of boulders (barrier rock) to be used in the project. Specifically, the plan sheets indicate the typical dimensions for the boulders, and the contract specifications state there is no supplemental park source for the boulders - the contractor is responsible for procuring them.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No.: MT NP GLAC 14(6), Project : Swiftcurrent Spur Road Rehabilitation
# General Technical Question Answer Date
1 X SCR 705.08 gives a general description of the shape of the boulders needed but does not give a size. How big do the boulders need to be?
See plan sheet C.1 for typical boulder (barrier rock) dimensions.
7/18/24
2 X Is there a source within the Park for these boulders? See SCR’s subsections 203.03 Salvaging Material, 251.06A Boulders, and SCR 705.08
Boulders (Barrier Rock). There is no supplemental park source for boulders. 7/18/24