QA_09-12-2025.pdf
PDF 99 KB Posted
- Solicitation number
- 69056724B000011
About this file
This document is a Questions and Answers (Q&A) file for the Gifford Pinchot Repairs 2020, Phase 1 project, identified by Project No. WA ERFO FS GIFPN603 2020-1(1). The Q&A table contains two entries addressing technical inquiries about the project. The first question asks about locating project plans and specifications, which are directed to be found on SAM.gov at a specific URL. The second question seeks clarification on specific technical details for Line Item A0640, Pay item 60601-0000 Spillway Assembly, particularly regarding pipe length and elbow angles. The response directs the inquirer to a Physical Data document (waef-gifpn2020-1-1_XS_culverts.pdf) posted under "Attachments" on SAM.gov. Both questions were submitted and answered in September 2025, with responses providing specific guidance on where to find the requested information.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. WA ERFO FS GIFPN603 2020-1(1), Project Gifford Pinchot Repairs 2020, Phase 1
# General Technical Question Answer Date
1 X
Do you know where we can find the plans and specifications for the Gifford Pinchot Repairs
2020 Phase 1 project?
This information is posted to SAM.gov:
https://sam.gov/workspace/contract/opp/
6e7db19217954d6b893b465ac489dabb/vie w.
9/11/25
2 X
Line Item A0640 Pay item 60601-0000 Spillway
Assembly doesn’t define the length of the Half
Round 36” pipe, or the angle for the elbows as shown in the Standard detail.
Please see the Physical Data document, wa-ef-gifpn2020-1-1_XS_culverts.pdf, posted under “Attachments” for this solicitation on SAM.gov.
9/12/25
Check General or Technical