This document is an Amendment of Solicitation (Standard Form 30) for the Gifford Pinchot Repairs 2020, Phase 1 project, issued by the Department of Transportation's Federal Highway Administration. Amendment A002, dated 09/23/2025, modifies the original solicitation No. 69056724B000011 with updates to two specific subsections: 108.03 Determination and Extension of Contract Time and 109.06 Pricing of Adjustments.
The amendment primarily focuses on revising contract time extension provisions, particularly for quantity variations and weather-related delays. Key changes include clarifying conditions for contract time adjustments, specifying that no time extensions will be granted for stop orders except under unusual weather conditions, and establishing procedures for contractors to request time extensions when estimated quantities vary significantly. The amendment also updates invoice submission and payment processing requirements, including specific deadlines for invoices submitted between September and July, and establishes guidelines for equitable contract price adjustments when unit-priced item quantities deviate more than 15 percent from estimated amounts.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A002 09/23/2025 N/A
WA ERFO FS GIFPN603 2020-1(1),
Gifford Pinchot Repairs 2020, Phase 1
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056724B000011
9B. DATED (SEE ITEM 11)
08/28/2025
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
WA ERFO FS GIFPN603 2020-1(1), Gifford Pinchot Repairs 2020, Phase 1
See page 2
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A002, dated 09/23/2025 Project No.: WA ERFO FS GIFFPN603 2020-1(1)
Solicitation No. 69056724B000011 Project Name: Gifford Pinchot Repairs 2020, Phase 1
REVISIONS ARE AS FOLLOWS:
SPECIAL CONTRACT REQUIREMENTS
Pages E-20, Subsection 108.03 Determination and Extension of Contract Time. Updates reference in paragraph (c).
Pages E-24, Subsection 109.06 Pricing of Adjustments. Updates to paragraph (c), Variation in Estimated Quantity.
ENCLOSURES
Pages:
E-20
E-24
E-20 DIVISION 100
Special Contract Requirements
Revised by Amendment A001
Project: WA ERFO FS GIFPN603 2020-1(1), Gifford Pinchot Repairs 2020, Phase 1
Section 108. — PROSECUTION AND PROGRESS
11/01/24– FP-14
108.01 Commencement, Prosecution, and Completion of Work. Delete the first sentence and amend as follows:
Delete the text of the second paragraph and substitute the following:
A preconstruction conference will be held after the contract is awarded and before beginning work.
A baseline schedule submittal meeting is also required according to Subsection 155.10. The schedule manager, project manager, and project superintendent are required to attend the preconstruction conference and the schedule submittal meeting unless otherwise approved by the
CO.
Do not begin on-site ground disturbing activities or Section 151 mobilization within the construction limits prior to approval of the baseline schedule submittal. Only construction surveying and staking, temporary traffic control, weed treatment, and work under Section 637 is allowed before approval of the baseline schedule submittal.
Add the following:
Furnish at least a 48-hour advanced notice before changing the current work schedule. Work schedule changes that include additional shifts require a 14-day advanced notice.
Perform work under this contract by limiting work as provided for in Sections 105, 107, 156, and
157.
108.01A Labor. (Added Subsection).
Follow the requirements of FAR Clause 52.222-6 Construction Wage Rate Requirements.
Adjacent or virtually adjacent work sites, as used in FAR Clause 52.222-6, are defined to be work sites within ½ mile of the project. Application of Construction Wage Rate Requirements (Davis-
Bacon Act) for work sites beyond ½ mile of the project will be determined by the CO.
108.03 Determination and Extension of Contract Time. Delete the first sentence and add the following to paragraph (c):
No adjustment in contract time or amount will be made for stop orders issued under
Subsection 108.05(a) or (b), except an adjustment in contract time, as provided by FAR
Clause 52.249-10 Default (Fixed-Price Construction), may be made when the Contractor is able to demonstrate that the weather was unusually severe based on the most recent 10 years of historical data.
If a quantity variation described in Subsection 109.06(e c) results in an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the CO within 10 days from the beginning of the delay, or within such further
Revised by Amendment A002 rebekah.webb Cross-Out
E-24 DIVISION 100
Special Contract Requirements
Revised by Amendment A001
Project: WA ERFO FS GIFPN603 2020-1(1), Gifford Pinchot Repairs 2020, Phase 1 records that relate to the ownership and operating costs for each piece of equipment.
When actual costs cannot be determined, use the rates shown in the U.S. Army Corps of Engineers Construction Equipment Ownership and Operating Expense Schedule
(CEOOES) for the region where costs are incurred. Adjust the rates for used equipment and for other variable parameters used in the schedules. Provide the CO with a completed WFLHD Form 103, proposed CEOOES rates for each piece of equipment with supporting calculations, and any other necessary documentation about the equipment to calculate allowable ownership and operating costs using CEOOES.
An electronic version of the WFLHD Form 103 form is available at:
https://highways.dot.gov/federal-lands/construction/forms-wfl.
For equipment that is not planned to be used at the time of the preconstruction conference, but is later used on the project, provide required information and data prior to mobilizing the equipment to the project.
Add the following:
(d c) Variation in Estimated Quantity. If the quantity of a unit-priced item is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price will be made upon demand of either party. The equitable adjustment will be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity
109.08 Progress Payments. Amend as follows:
Delete paragraph (b) and substitute the following:
(b) Closing date and invoice submittal date. The closing date for progress payments will be designated by the CO. Include work performed after the closing date in the following month's invoice. For work performed between September and July of any year, submit invoices to the designated billing office by the 7th day after the closing date. Invoices received by the designated billing office after the 16th day following the closing date, for work included in the
September through July invoices, will not be accepted for payment processing that month. For work included in the August invoice, submit the invoice to the designated billing office by the
5th day after the closing date. Invoices received by the designated billing office after the 5th day following the closing date, for work included in the August invoice, will not be accepted for payment processing that month. Include late, unprocessed invoice submittals in the following month’s invoice.
Delete paragraph (e) and substitute the following:
(e) Processing progress payment requests. No payment will be made for work unless field note documentation for the work was provided by the closing date.
(1) Work performed between September and July.
(a) Invoices received by the 7th day following the closing date.
Revised by Amendment A002 https://highways.dot.gov/federal-lands/construction/forms-wfl rebekah.webb Cross-Out