Q&A_02-01-19.pdf

PDF 57 KB Posted

Attached to
MT DOT 569 (3), North of Moose Creek North
Solicitation number
69056718B000024
Issued by

View the file

Other files

File Type Posted
Bid_Opening_Summary.pdf PDF
A003.pdf PDF
A002.pdf PDF
Q&A_02-22-19.pdf PDF
Q&A_02-19-19.pdf PDF
Q&A_02-14-19.pdf PDF
Amendment_A001.pdf PDF
Q&A_02-11-19.pdf PDF
Q&A_02-07-19.pdf PDF
Q&A_01-28-19.pdf PDF
Waterway_Hydraulics_Memo.pdf PDF
Plan_Sheets_(R).pdf PDF
mt-56903_XS_MAIN01(r2).pdf PDF
MT_North_of_Moose_Creek_North_Pave_Memo_FINAL.pdf PDF
mt-56903_XS_DETOUR01.pdf PDF
SWPPP_MT_DOT_569(3)_North_of_Moose_Creek_North.pdf PDF
California_Creek_Bridge_Inspection_Report.pdf PDF
California_Creek_As-built.pdf PDF
Attachment_2-_Site_Photographs.pdf PDF
2016-04-25_Proj_002-490L_Bridge_Lead_Paint_Testing_Report_w_Attachments.pdf PDF
2016-04-25_Proj_002-490_Bridge_Asbestos_Inspection_Report_wAtts.pdf PDF
North_of_moose_controlsheet.xlsx XLSX spreadsheet
Attachment_2_-_LBP_Sample_Lab_Report.pdf PDF
GM_31-17_North_Moose_Creek_Preliminary_Foundation_Recommendations__FINAL_1.pdf PDF
GR_23-18_MT_DOT_569(3)_Final_Geotechnical_Report.pdf PDF
GM18-18_Final_Bridge_Foundation_Recommendations_August_2018.pdf PDF
GM19-17_North_Moose_Creek_Subsurface_Investigation_and_Prelim_Recomm_FINAL.pdf PDF
California_Creek_Preliminary_Bridge_TS&L_Report.pdf PDF
Attachment_1_-_Asbestos_Lab_Reports.pdf PDF
mt-56903_Earthwork_MAIN01.pdf PDF
Plan_Request_Form.pdf PDF
IFB_Moose_Creek.pdf PDF
Attachment_1-_Site_Photographs_Lead.pdf PDF
mt-56903_Earthwork_DETOUR01.pdf PDF
Prelim_Letter_Moose_Creek_North.pdf PDF
PROJECT_DESCRIPTION_Moose_Creek.pdf PDF
Preliminary_Plans.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MT DOT 569 (3)

North of Moose Creek North

# General Technical Question Answer Date

1 X Is there a ceiling for the number of days retained by the contractor if finished earlier than the days bid?

No days are retained by the contractor if the project is finished earliar than days bid.

In other words, no payment incentives are provided for the project to be completed prior to the day established in Part B of the bid schedule.

1/25/19

2 X

On E‐15 of the specs SCR 107.12 states the need to provide a Professional Archaeologist meeting the Secretary of Interior Standard’s to conduct monitoring at six locations on the project. Is there an approved list of Archaeologist’s available you would provide for bidding?

No. Bid accordingly. 1/28/19

3 X

According to the Offer Submittal Checklist, the Subcontracting Plan is required with the Offer Submission. On page A‐6, Subcontracting Plan, it states “Do not submit this form with your bid”.

Please clarify if the Subcontracting Plan as provided in A‐6a thru A‐6f is required to be submitted with the Offer.

Do not submit the subcontracting plan with your bid.