MT DOT 569 (3)
North of Moose Creek North
# General Technical Question Answer Date
1 X Is there a ceiling for the number of days retained by the contractor if finished earlier than the days bid?
No days are retained by the contractor if the project is finished earliar than days bid.
In other words, no payment incentives are provided for the project to be completed prior to the day established in Part B of the bid schedule.
1/25/19
2 X
On E‐15 of the specs SCR 107.12 states the need to provide a Professional Archaeologist meeting the Secretary of Interior Standard’s to conduct monitoring at six locations on the project. Is there an approved list of Archaeologist’s available you would provide for bidding?
No. Bid accordingly. 1/28/19