This document is a Section F: Deliveries or Performance section from a federal contract for Facility Investment (Contract 1502000), specifically detailing required deliverables for a maintenance and repair contract. The deliverables table outlines seven specific reports and submissions, including Certification and Licenses, Maintenance Summary Report, Service Order Summary Report, Preventive Maintenance Program Plan, Monthly PM Work Schedule, Unaccomplished Maintenance Report, and Repair Status Report. Each deliverable has specific submission requirements, including timeframes ranging from within 15 days after award to the first work day of each month, with distribution to the Contracting Officer (KO) and Contracting Officer's Representative (COR). The frequency of submissions varies from once for initial submittal to monthly or as required, with most requiring two copies of each report.

View the file

Other files

Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1502000 – Facility Investment

SECTION F: DELIVERIES OR PERFORMANCE

DELIVERABLES

Annex/ Spec Item

Form Attachment

Number Deliverable Title Date (s) of Submission

Distribution

Frequency Original/

Copies

Number of Copies

(including original) 1502000/ 2.2.1

N/A

Certification and

Licenses Within 15 days after award or as requested by the

KO

KO/COR 1 Once for initial submittal, then as requested 1502000/ 3.0

J-150200004 Maintenance Summary Report

Within 24 hours of completion of work

KO/COR 2 As specified

1502000/ 3.1

J-150200005 Service Order Summary Report

First work day of each month KO/COR 2 Monthly

1502000/ 3.2

N/A

Preventive Maintenance Program Plan

30 calendar days after contract award

KO/COR 2 Annually

1502000/ 3.2

N/A Monthly PM Work Schedule

Five work days prior to the beginning of each month

KO/COR 2 Monthly

1502000/ 3.2

N/A Unaccomplished Maintenance

Report

First work day of each month KO/COR 2 As Required

1520000/ 3.2

N/A Repair Status

Report First work day of each month KO/COR 2 Monthly