This is a Quality Assurance Surveillance Plan (QASP) for the Graduate Research, Education and Technology (GREAT) Support contract at the Air Force Institute of Technology (AFIT). The contract period of performance is March 1, 2025 through February 28, 2030, with GSA's Assisted Acquisition Services Division serving as the contracting organization supporting AFIT.

The QASP establishes performance monitoring methods and standards for contractor services including administrative, programmatic and technical assistance for AFIT's educational and research activities. Key performance areas include project management, process documentation, security incident reporting, monthly status reports and invoicing, mandatory training compliance, and personnel retention (maximum 15% annual turnover allowed). The contractor must provide support for graduate/continuing education courses and research efforts in areas like high-power lasers, optics, remote sensing, cyberspace, hypersonics, nuclear, quantum computing, and space technologies. Performance monitoring uses a combination of customer input, monthly reviews, and status report assessments, with most performance standards requiring no more than 2 violations per month to meet acceptable quality levels. Wesley Mason is identified as the Contracting Officer and Brandy Pickens as the GSA Program Manager.

View the file

Other files for this federal contract opportunity

Other files attached to Graduate Research, Education and Technology (GREAT) Support, newest first.
File Type Posted
47QFLA24R0013 Amend 6_GREAT Support RFP Appendix 1_Solicitation Sections K-M_2024 12 30.docx DOCX document
47QFLA24R0013 Amend 5_GREAT Support RFP Appendix 1_Solicitation Sections K-M_2024 12 30.docx DOCX document
47QFLA24R0013 Amend 3_RFP Attachment 8_GREAT Support Question Answer_Govt Response_2024 12 13.xlsx XLSX spreadsheet
47QFLA24R0013 Amend 2_GREAT Support RFP Appendix 1_Solicitation Sections K-M_2024 12 09.docx DOCX document
47QFLA24R0013 Amend 2_GREAT Support PWS_Solicitation Sections A-J_2024 12 09.docx DOCX document
47QFLA24R0013_RFP Attachment 8_GREAT Support Questions_Govt Responses_2024 12 09.xlsx XLSX spreadsheet
47QFLA24R0013 Amd 1_RFP Attachment 8_GREAT Support Question_Answer Template_2024 12 03 Govt Responses.xlsx XLSX spreadsheet
47QFLA24R0013_GREAT Support PWS_Solicitation Sections A-J_2024 11 14.docx DOCX document
47QFLA24R0013_RFP Attachment 3_GREAT Support Non-Disclosure Agreement Certification__2024 10 24.docx DOCX document
47QFLA24R0013_RFP Attachment 9_GREAT Support Travel Expense Sheet Template_2024 10 31.xlsx XLSX spreadsheet
47QFLA24R0013_RFP Attachment 10_GREAT Support SCRM Questionaire_2024 10 31.xlsx XLSX spreadsheet
47QFLA24R0013_GREAT Support RFP Appendix 1_Solicitation Sections K-M_2024 11 14.docx DOCX document
47QFLA24R0013_RFP Attachment 1_GREAT Support Pricing Sheet_2024 10 22.xlsx XLSX spreadsheet
47QFLA24R0013_RFP Attachment 4_GREAT Support Consent to Purchase CTP Template_2024 10 24.xlsx XLSX spreadsheet
47QFLA24R0013_RFP Attachment 5_GREAT Support Key Personnel Qualification Worksheet _ 2024 11 13.docx DOCX document
47QFLA24R0013_RFP Attachment 6_ GREAT Support OCI Statement Template_2024 10 26.docx DOCX document
47QFLA24R0013_RFP Attachment 8_GREAT Support Question_Answer Template_2024 10 31.xlsx XLSX spreadsheet
47QFLA24R0013_RFP Attachment 2_GREAT Support DRAFT DD254 w SCI Add_2024 09 23.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)

Solicitation PIID: 47QFLA24R0013 Award PIID: TBD for Graduate Research, Education and Technology (GREAT) Support in support of Air Force Institute of Technology (AFIT)

Customer Support Center: Air Force, Navy, Space Force (AFNSF) Business Unit Contractor Name: TBD Contract Period of Performance (PoP): 1 Mar 25-28 Feb 30 Effective Date of QASP: TBD

Table of Contents

1.0 General Instructions............................................................................................................pg 3

2.0 Purpose................................................................................................................................pg 3

2.1 Performance Management Approach.....................................................................pg 4
2.1.1 Performance Management Strategy.........................................................pg 4
2.2 Scope of this QASP...................................................................................................pg 5
2.2.1 Description of Contractual Effort..............................................................pg 5

3.0 Roles and Responsibilities...................................................................................................pg 6

3.1 Contracting Officer...................................................................................................pg 6
3.2 Contracting Officer's Representative.......................................................................pg 6
3.3 Client's Technical Point of Contact...........................................................................pg 7

4.0 Surveillance Procedures......................................................................................................pg 7

4.1 The Performance Requirements Summary..............................................................pg 7
4.2 The Quality Assurance Monitoring Form...............................................................pg 11
4.3 The Client Complaint Investigation Form...............................................................pg 11
4.4 The Quarterly COR Report.....................................................................................pg 11

5.0 Attachments......................................................................................................................pg 12

5.1 Memorandum for Documenting Surveillance........................................................pg 12
5.2 Quality Assurance Monitoring Form......................................................................pg 13
5.3 Client Complaint Investigation Form......................................................................pg 14
5.4 Corrective Action Plan Template............................................................................pg 16

1.0 - General Instructions This Quality Assurance Surveillance Plan (QASP) establishes the process for surveillance of contract performance in support of Air Force Institute of Technology's requirement for services, as detailed in the Performance Work Statement (PWS) for Graduate Research, Education and Technology (GREAT) Support.

This QASP has been completed in partial fulfillment of requirements established under Federal Acquisition Regulation (FAR) Part 46. It details the surveillance roles and responsibilities of the contract administration team and describes the specific contract elements subject to surveillance. Further, this QASP establishes the methods of surveillance to be employed, as well as the frequency and timing of that surveillance. The documentation produced through implementation of this QASP will serve to inform the Quarterly Contracting Officer’s Representative (COR) Report in accordance with the Federal Acquisition Service (FAS) Policy and Procedure (PAP) Memo 2020-03, and as implemented via the associated ASSIST Quarterly COR Report module, as well as the applicable Contractor Performance Assessment Report (CPAR). This QASP is filed under Tab 47, Surveillance, of the Electronic Contract File (ECF), and the surveillance documents produced in accordance with this QASP are filed as described in the applicable sections below. In short, this QASP establishes what must be surveilled, how it must be surveilled, and when surveillance must occur. Note: The format of the Quarterly COR Report is provided for via a template that is separate from this document.

This QASP is effective as of the date on the cover and supersedes all previous versions. In the instance of a conflict between this QASP and the associated contract, the contract shall prevail.

2.0 - Purpose The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards or quality levels identified in the PWS, and for ensuring that the Government pays only for the level of services received.

This QASP defines the roles and responsibilities of all members of the Integrated Project Team (IPT), identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes Quality Assurance (QA) documentation requirements, describes the analysis of QA monitoring results, and provides a Performance Requirements Summary (PRS).

The contractor is responsible for implementing and delivering performance that meets contract standards using its Quality Control Plan (QCP). The QASP provides the structure for the Government’s surveillance of the contractor’s performance and their QCP to assure they meet contract standards. It is the Government’s responsibility to be objective, fair, and consistent in evaluating contractor performance.

The QASP is not part of the contract, and it is not intended to duplicate the contractor’s QCP. This QASP is a living document. Flexibility in the QASP is required to allow for an increase or decrease in the level of surveillance necessary based on contractor performance.

2.1 – Performance Management Approach The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by the General Services Administration (GSA) to monitor and manage the contractor’s performance to ensure the expected outcomes or performance objectives communicated in the PWS are achieved. Performance management rests on developing a capability to review and analyze information generated through performance assessment. The ability to make decisions based on the analysis of performance data is the cornerstone of performance management; this analysis yields information that indicates whether expected outcomes for the project are being achieved by the contractor.

Performance management represents a significant shift from the more traditional QA concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent versus scrutiny of compliance with the processes used to achieve the outcome. A performance-based approach facilitates the contractor providing an innovative solution within the stated constraints that gives the Government the opportunity to receive outstanding results. A “results” focus provides the contractor flexibility to continuously improve and innovate over the course of the contract as long as the critical outcomes expected are being achieved and/or the desired performance levels are being met.

2.1.1 – Performance Management Strategy The contractor shall be responsible for the quality of all work performed. The contractor measures that quality through the contractor’s own Quality Control (QC) program. QC is applicable to all work performed under the contract and accordingly, for any contract featuring a prime contractor/subcontractor arrangement, the prime contractor’s QC program must also address how it will ensure the quality of all work that its subcontractors perform. The contractor’s QCP shall set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. The contractor shall develop and implement a performance management system with processes to assess and report its performance to the designated Government representative. This QASP enables the Government to take advantage of the contractor’s QC program.

Government representative(s) will monitor performance and review performance reports furnished by the contractor to determine how the contractor is performing against communicated performance objectives. The Government will utilize performance data generated through surveillance in accordance with this QASP to manage contractual performance. Specifically, the Government will complete regular evaluations of contractor performance in accordance with the PRS. The Government will document those evaluations using the Quality Assurance Monitoring Form (QAMF) and the aforementioned Quarterly COR Report. These evaluations will inform the contractor’s rating in the applicable CPAR. Additionally, regular evaluations may lead to action by the Contracting Officer (CO), including, but not limited to, demands for Corrective Action Reports by the contractor, the issuance of Cure Notices, or the issuance of Show Cause letters. In summary, the surveillance completed and documented through implementation of this QASP will have real and meaningful impact upon the performance of the contract.

2.2 - Scope of this QASP This section of the QASP describes the contractual effort to which the QASP applies. Additionally, this section addresses any applicable and special concerns, to include surveillance and corrective action.

2.2.1 – Description of the Contractual Effort Background: AFIT requires on-site support to help faculty and staff execute its academic missions/ The contractor shall be responsible for providing administrative, programmatic and technical assistance to educational and research activities. The contractor shall provide support for the development and delivery of graduate and continuing education courses. The contract shall assist with on-going graduate-level research efforts, with emphasis in high-power lasers, optics, remote sensing, cyberspace modeling & simulation, advanced navigation, hypersonic, nuclear, quantum computing, fast-lasers, and space-related technologies. Additionally, the contractor shall assist in organizing, administering, and promoting AFIT programs.

Scope: The scope of this effort is to continue support services for AFIT’s educational and research missions. The contractor will provide all necessary non-personal labor and services to complete tasks specified in support of the AFIT Research Centers and Departments’ workload. These tasks may include direct or indirect support of office operations, as well as programs and projects supporting education and research users. The contractor will manage and organize resources and personnel needed to efficiently and effectively meet the objectives of each task and explore new approaches, as applicable, within the performance of these tasks.

The contractor shall assign sufficient resources and trained personnel to accomplish the tasks and meet program/project milestones and schedules. The contractor will assign a person to identify and assign contractor personnel (or a team of personnel), possessing the necessary experience, skills, and security clearances, in appropriate contractor labor categories, to support the various efforts/tasks outlined in this PWS. Tasks shall be accomplished in an effective, efficient, and timely manner. The contractor shall be capable of providing and performing the whole spectrum of support.

Objective: The primary objective of this TO is to provide qualified personnel to support numerous AFIT customers conducting technical research and developing/delivering specialized educational programs. The contract personnel will be responsive to their AFIT customers in accomplishing the varied tasks outline in this PWS.

3.0 - Roles and Responsibilities This section of the QASP specifies the roles and responsibilities of the applicable individuals regarding contract surveillance.

3.1 - Contracting Officer (CO) The CO is responsible for monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by the COR and the contractor. The CO will typically designate one full-time COR as the Government authority for performance management. The number of additional representatives serving as technical inspectors depends on the complexity of the services measured, as well as the contractor’s performance, and said individuals must be identified and designated by the CO.

Assigned CO: Wesley "Wes" Mason Organization or Agency: Assisted Acquisition Services Division, APEX 2 Email: Wesley.mason@gsa.gov Phone: (850) 398-7466

3.2 - Contracting Officer’s Representative (COR) The COR is designated in writing by the CO to act as their authorized representative to assist in administering a contract. COR limitations are contained in the written appointment letter. The COR is responsible for technical administration of the project and ensures proper Government surveillance of the contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf. Any changes that the contractor deems may affect contract price, terms, or conditions shall be referred to the CO for action. The COR will have the responsibility for completing QAMFs used to document the inspection and evaluation of the contractor’s work performance. Additionally, the COR is responsible for completing the Quarterly COR Report per the established template and ensuring that completed reports are filed in Tab 47 of the ECF. Government surveillance may occur under the inspection of services clause for any service relating to the contract.

Assigned GSA PM: Brandy Pickens Organization or Agency: Assisted Acquisition Services Division, AFNSF Email: brandy.pickens@gsa.gov Phone: (813) 624-0143

3.3 Client’s Technical Point of Contact (TPOC)

The CO may designate a TPOC for the technical administration of the contract. As a representative of the requiring activity, the TPOC may perform or assist in monitoring and assessing the contractor’s performance under the requirements of the PWS); inspecting and recommending acceptance of deliverables; reviewing invoices and recommending approval of payments; providing guidance and clarification of technical requirements, security-related issues, and Information Technology (IT) access.

The TPOC is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf which will:

· Cause the contractor to perform work outside the scope of the contract.

· Constitute a change as defined in FAR 52.243-1.

· Cause an increase or decrease in the price of the contract.

· Alter the period of performance or delivery dates.

· Change any of the other express terms or conditions of the contract.

Assigned Client’s TPOC: TBD Organization or Agency: Air Force Institute of Technology Email: TBD Phone: TBD

4.0 - Surveillance Procedure

4.1 - The Performance Requirements Summary (PRS) The PRS is the “heart” of quality surveillance. The tasks, performance standards, and Acceptable Quality Levels (AQLs) in the matrix below are established in the contract PWS. The method of surveillance and frequency of surveillance are established by this QASP, and CPAR factors applicable to each task are annotated in this QASP PRS. These parameters have been chosen to ensure that contract surveillance supports and documents contractor performance.

The following provides a description of each column of the QASP PRS matrix.

· Task: The tasks established in this QASP PRS are derived from those established in the contract PWS. The task provides a description of the work to be surveilled, as well as a PWS citation that associates the task with specific requirements.

· Performance Standard: Performance standards established in the QASP PRS are derived from those established in the contract PWS. The performance standard describes the expected level of performance associated with a task.

· Acceptable Quality Level (AQL): AQLs established in the QASP PRS are derived from those established in the contract PWS. The AQL provides a specific metric to allow the Government to determine whether contractor performance regarding a task is acceptable. For the purposes of this QASP, meeting the AQL for a task is commensurate with Satisfactory performance. Failure to meet an AQL constitutes Marginal or Unsatisfactory performance, depending upon the degree to which the AQL has been breached. Exceeding the AQL may constitute Very Good or Exceptional performance, but only if the Government realizes specific benefits, such as a higher quality deliverable or a reduction in contract cost. The IPT should exercise care when determining the AQL, and should avoid establishing perfection as the standard except in the rare instance when perfection is required.

· Method: This QASP PRS establishes the method of surveillance for each task in the PRS matrix. The appropriate method is one that successfully compares the observed performance with both the performance standard and the AQL. Typical methods include 100 percent inspection, random sampling, periodic sampling/inspection, and customer/client feedback. However, the method selected is not necessarily limited to these options. Rather, the method selected may be tailored to a task to successfully determine whether observed performance meets the established standard and AQL. A best practice is to establish in the description of the method the individual(s) responsible for the surveillance (the “who”) as well as “how” surveillance will be accomplished. The contract COR will utilize the QAMF, Section 4.2, established in this QASP to document completion of surveillance in accordance with the method described.

· Frequency: This QASP PRS establishes the frequency of surveillance for each task in the PRS matrix. The frequency of surveillance must be tailored with respect to the task, performance standard, AQL, and method. The contract COR will utilize the QAMF to document the date on which surveillance occurred to demonstrate compliance with the frequencies established in this QASP PRS. For example, a monthly status report to be surveilled via 100 percent inspection must be completed monthly.

· Applicable CPAR Factor(s): This QASP PRS associates each surveillance activity with an applicable CPAR factor. Regular assessment of contractor performance using the CPAR Factors established in FAR 42.1503(h)(4) (e.g., Exceptional, Very Good) will support CPARs completed either annually, or at the conclusion of performance. IPTs should consult FAR 42.1503(h)(4) when determining which CPAR factors are applicable to a particular task and the associated surveillance.

Figure 1: The QASP PRS Matrix

Performance Requirement
Task
Performance Standard
Acceptable Quality Level (AQL)
Method of Performance Assessment
General
C.3.1 - C.3.9
▪ 100% of documentation and services shall be completed and submitted IAW the requirements established within the requirement documents (PWS \ work definition \ task directive \ task assignment form, etc.) and shall be compliant with all applicable governing regulations, policies, directives and guidance.
No more than 2 violations per month.
Customer Input

▪ 100% of documentation and services shall be completed (including required updates) and submitted NLT the established date for completion/receipt as identified in the requirement documents.

Project Management
C.3.1
▪ 100% of presentations and communications shall be coordinated as required and shall be clear, effective, concise, and organized.
No more than 2 violations per month.
Customer Input, MSR Review

▪ 100% of shall be tailored specifically for team needs and shall result in the team’s ability and empowerment to achieve documented action items and milestones.

▪ Project Managers shall respond to 100% of questions and requests with applicable responses/references.

▪ 100% of documentation and services (including updates) shall be completed and submitted NLT the established date for completion/receipt as identified in the requirement documents.

▪ 100% of documentation and services (including updates) shall be completed and submitted IAW the requirements established within the requirement documents.

Process, Development and Documentation Activities
C.3.2, C.3.3, C.3.4, C.3.6, and C.3.7
▪ 100% of all process, development and documentation activities shall be conducted in accordance with governmental & organizational standards, policies, directives, standard operating procedures, work instructions, processes & guidance.
No more than 2 violations per month.
Customer Input
Documentation Updates and Storage/Repository
C.3.3
▪ Electronic versions of all documentation in the required format shall be posted/stored within the mutually established timeframe in the required artifact repository/tool location and shall be available for Government review at all times as required.
No more than 2 violations per month.
Customer Input
Achieving Actions
C.3.4, C.3.6, C.3.7
▪ 100% attendance and active participation in all events as required.
No more than 2 violations per month.
Customer Input

▪ 100% of presentations and communications shall be coordinated as required and shall be clear, effective, concise, and organized.

▪ Support for all PWS tasks shall enhance the team’s ability and empowerment to achieve documented action items and milestones.

Project Planning and Management
C.3.4, C.3.5, C.3.6, C.3.7
▪ The contractor shall develop, document, and maintain project plans 100% compliant with federal governing regulations, policies, directives, guidance and industry practice.
No more than 2 violations per month.
Customer Input, MSR Review

▪ 100% of project plans shall include the identification of applicable responsibilities, timelines, deliverables, risks, milestones and other elements as required.

▪ 100% of plan schedules and activities shall be coordinated with all required participants.

▪ All issues impacting project schedules shall be communicated to government staff within one business day after determination of impact.

▪ 100% of project plans shall be updated weekly.

Inquiry Response
C.3.1 - C.3.9
▪ Respond to all customer inquiries NLT 24 hours after inquiry receipt.
No more than 2 violations per month.
Customer Input, MSR Review
Security Incident Notification and Resolution
H.10 - H.12
▪ 100% of security incidents shall be reported within one hour of detection to the AFIT COR.
No allowable violations per month.
Customer Input, MSR Review
Monthly Status Report
C.13.0
▪ 100% complete with all required appendices.
No more than 1 violation per month.
Customer Input, Monthly TPOC Review

▪ 100% accurate.

▪ Submitted no later than (NLT) 15th calendar day of month following the reporting period and submitted concurrent with the monthly invoice.

Monthly Invoice
G.2.0
▪ 100% complete with all required supplemental information.
No more than 2 violations the first 2 months. No allowable violations for the remainder of the contract/order.
Customer Input

▪ 100% accurate.

▪ Submitted no later than (NLT) 15th calendar day of month following the reporting period and submitted concurrent with the monthly status report.

Mandatory Government Training Compliance
C.3.1 - C.3.9, H.10.2, H.15
▪ 100% of required training (for all contractor personnel performed under the GREAT Support requirement, including all CLINs) shall be completed and submitted NLT the established date for training completion as mandated by the Government.
No violations per month.
Customer Input, MSR Review
Personnel Availability
C.3.1 - C.3.9
▪ 100% contractor personnel availability during required daily core hours (with the exception of coordinated absences).
Vacancies are filled within 10 days of personnel departures
Customer Input, MSR Review

▪ The contractor is responsible for resource substitution/coverage when a coordinated absence is greater than five consecutive workdays.

Personnel Retention
C.3.1 - C.3.9
▪ 100% compliance with staffing requirements identified in PWS.
No greater than 15% turnover of personnel per annual period of performance. If contractor fails to retain qualified personnel as stated, no higher than a "Marginal" rating under CPARS Management unless the contracting officer determines the documented circumstances justify a different rating.
Customer Input, MSR Review

4.2 - The Quality Assurance Monitoring Form (QAMF) The Government will use the surveillance methods cited in the PRS to determine whether the performance standards and AQLs have been met by the contractor. The COR will document the Government’s quality assurance surveillance using the monitoring form using Attachment 3, QAMF Template. If the contractor has not met the AQLs, the contractor may be required to develop a Corrective Action Plan (Attachment 5) to show how and by what date it will bring performance up to the required levels.

The COR will upload a copy of the completed QAMF to the ECF as frequently as needed to comply with the PRS. Completed QAMFs will be uploaded to ECF Tab 47, Surveillance.

4.3 - The Client Complaint Investigation Form Performance management drives the contractor to be customer-focused through initially and internally reviewing the quality of performance. When a customer complaint arises, a customer may use the Client Complaint Investigation Form (Attachment 4). Valid customer complaints must clearly set forth the detailed nature of the complaint, must be in writing and signed, and must be forwarded to the COR. The COR will investigate the complaint, using the Client Complaint Investigation Form and will inform the contractor of the complaint. If corrective actions have been taken or are planned, the COR may document in the Contract Corrective Action Plan (Attachment 5).

4.4 - The Quarterly COR Report A Quarterly COR report must be completed in accordance with FAS PAP 2020-03, and the controlling COR SOP. CORs should refer to the AAS Template for the quarterly COR report, which is provided for by way of a separate document. Regular completion of the QAMF will support completion of the Quarterly COR Report and inform its contents.

Timing for completion and filing of the Quarterly COR Report is dependent upon the award date of the applicable contract or order. As this contract was awarded on (insert date), Quarterly COR Reports associated with this QASP will be completed by the final days of (insert the names of the applicable months).

Each Quarterly COR Report will be completed in accordance with the instructions provided in this with FAS PAP 2020-03 and filed under Tab 47, Surveillance, of the ECF.

5.0 - Attachments

5.1 - Attachment 1, Template Memorandum for Documenting Surveillance at Contract Level

MEMORANDUM TO FILE

File completed memorandum in Tab 47 of each applicable order.

DATE:Insert Date
FROM:Insert Name, Contracting Officer’s Representative (COR), Insert Customer Support Center/COR Organization
SUBJECT:Surveillance for Orders under (Insert Award PIID) Performed at Contract Level

· This memorandum documents the performance of contract surveillance at the contract level for the subject contract. See the Quality Assurance Surveillance Plan (QASP) filed in Tab 47 of the contract level Electronic Contract File (ECF) for details.

· Surveillance products (e.g., deliverables, inspection reports) pertaining to contract surveillance are documented in accordance with the contract level QASP.

Insert Name Date

COR

(Insert organization)

5.2 - Attachment 2, QAMF Template

QUALITY ASSURANCE MONITORING FORM

Quality Assurance Monitoring Form

Contract Number:
INSERT CONTRACT NUMBER
Contract/Task Order Number:
INSERT CONTRACT/TASK ORDER NUMBER OR N/A
Contractor:
INSERT CONTRACTOR NAME
COR:
INSERT COR
Surveillance Period:
INSERT DATES
TASK
PWS

CITATION

PERFORMANCE STANDARD
ACCEPTABLE QUALITY LEVEL (AQL)
METHOD OF SURVEILLANCE
FREQUENCY
DATE OF MONITORING
CONTRACTOR MET AQL
SUPPORTING NARRATIVE
Insert ALL Tasks from PRS matrix in Section 4.1
Insert PWS citation
Insert Performance Standard from PRS matrix in Section 4.1
Insert AQL from PRS matrix in Section 4.1
Insert Method of Surveillance from PRS matrix in Section 4.1
Insert Frequency from PRS matrix in Section 4.1
Insert the date(s) monitoring occurred or N/A if monitoring was not required for this task during the surveillance period.
Select Yes, No, or N/A if monitoring was not required for this task during the surveillance period.
Provide a narrative of contractor performance or N/A. Include specific examples or analysis if the AQL was not met. Reference any other supporting documentation and its location in the contract file, if applicable. Narrative should provide ratings for the applicable CPAR factors.

5.3 - Attachment 3, Client Complaint Investigation Form Template

CLIENT COMPLAINT INVESTIGATION FORM

Service: (Insert a brief description of the service that is being reviewed)

Surveillance Period: (Insert date/time of the surveillance period) Month XX, 20XX through Month XX, 20XX Date/Time that Complaint was Received: (Insert date/time) Month XX, 20XX at 11:00 am Eastern Time (ET) (modify based on actual time that complaint was received) Source of Complaint: (Insert information regarding the source of the complaint) Name: _____________________________________________________ Organization or Agency: _______________________________________ Email Address: ______________________________________________ Phone Number: ______________________________________________

Nature of Complaint: (Insert a description of the nature of the complaint)

Result of the Investigation: (Insert a summary of the results of the complaint investigation)

Date/Time that Contractor was Informed of Complaint: (Insert date/time) Month XX, 20XX at 11:00 am ET (modify based on actual time that service provider was informed) Prepared by: ______________________________ Date: _______________ Received by: ______________________________ Date: ________________

5.4 - Attachment 4, Corrective Action Plan Template Contract Corrective Action Plan

· Administrative Information Contract Number/Task Order Number:

Report Number:

Issue to (Contractor, Name, Title):

Issue by (COR):

Date of Issue:

Area of Concern (PWS Section, PRS #):

Suspense Date:

· Description of Area of Concern (Describe in Detail and Ref. PWS (choose one) Section)

Finding 1 Impact Finding 2 Impact

· Contractor Response Insert a written Corrective Action Plan that details the corrective action of the Areas of Concern cited. Include the cause and actions taken to prevent recurrence by Suspense Date.

· Government Response and Actions Taken COR Response to Contractor Corrective Action Plan and Action Taken to Prevent Recurrence - Indicate Acceptance, Partial Acceptance, Rejection with Rationale.

Insert CO Action: (If applicable, reduced payment, cure notice, show cause, other)

· Closeout

Name, Title
Signature
Date

Contractor Notified

Client Representative

COR/CO

RFP 47QFLA24R0013