A003 Revised Solicitation 47PM0123R0022 2023 07 13.pdf

PDF 269 KB Posted

Attached to
Elevator Modernization Project, Robert F. Kennedy Federal Building, Washington, DC
Solicitation number
47PM0123R0022
Issued by

About this file

This is a solicitation for a design-build contract to modernize elevators in the Robert F. Kennedy Federal Building in Washington, DC. The General Services Administration is seeking proposals to design and construct 32 elevators, including 30 public elevators and 2 private elevators. Services required include professional architectural, engineering, construction management, inspection, testing, and commissioning services. The North American Industry Classification System code for this work is 236220. The small business size standard is $45 million in average annual receipts. The site visit date is to be determined. Proposals are due by July 17, 2023 at 4:00 PM Eastern Time. The selection process will follow FAR Part 15 procedures. The solicitation and any amendments will be posted to the System for Award Management website. Interested firms must register in SAM, which they can do at www.sam.gov. No telephone inquiries will be accepted - all communication must be in writing.

View the file

Other files

File Type Posted
A0005 Solicitation 47PM0123R0022 RFI Clarification 2023 07 25.pdf PDF
A0005 Solicitation 47PM0123R0022 SF30 2023 07 25.pdf PDF
A004 Solicitation 47PM0123R0022 DOJ RFK Elevators Bid Sheet Rev 2023 07 19.xlsx XLSX spreadsheet
A004 Solicitation 47PM0123R0022 SF30 2023 07 19.pdf PDF
A004 Solicitation 47PM0123R0022 FY23 Division One Section List and Links.xlsx XLSX spreadsheet
A0004 Solicitation No. 47PM0123R0022 RFI and Clarifications 2023 07 19 .pdf PDF
A0003 Solicitation 47PM0123R0022 SF30 2023 07 13.pdf PDF
A0003 Solicitation 47PM0123R0022 Evaluation Factors 2023 07 13.pdf PDF
A0003 Solicitation 47PM0123R0022 Pre-Proposal Meeting Site Visit Slide Deck 6-29-2023.pdf PDF
A0003 Solicitation 47PM0123R0022 Bid Sheet.xlsx XLSX spreadsheet
A0003 Solicitation 47PM0123R0022 RFI 2023 07 13.pdf PDF
A0003 Solicitation 47PM0123R0022 Sign In Sheet 2023 06 29 (2).pdf PDF
Amendment 0002 Wage DC20220002 20230602.pdf PDF
Amendment 0002 Revised Solicitation 47PM0123R0022 2023 06 23.pdf PDF
Amendment 0002 47PM0123R0022.pdf PDF
Revised Solicitation No. 47PM0123R0022 A001 2023 06 21.pdf PDF
Solicitation 47PM0123R0022 A001 RFK Evaluation Factors.pdf PDF
Solicitation 47PM0123R0022 A0001 2023 06 21.pdf PDF
C D Waste Monthly Report TEMPLATE.pdf PDF
Solicitation No. 47PM0123R0022 DB Agreement 2023 06 14.pdf PDF
Solicitation No. 47PM0123R0022 2023 06 14.pdf PDF
PBS Past Performance Form 20210524 (1).docx DOCX document
Solicitation 47PM0123R0022 SOW Design-Build 2023 06 05.pdf PDF
C D Waste Mgmt Plan TEMPLATE.pdf PDF
47PM0123R0022 SF1442 Form 2023 06 07.pdf PDF
RFK-DOJ_DC0023ZZ_Elevator_Modernization_TechStudy_2019-07-29 (1).pdf PDF
Solicitation No. 47PM0123R0022 Reps and Certs 2023 06 14.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GSA Solicitation No. 47PM0123R0022

Document: DB201A/MARCH 2023 (The Solicitation)

Design Build Contract for: Design/Build Contract for U.S. Department of Justice Robert F. Kennedy Building - Elevator Modernization Project

The Solicitation

Design Build Contract for: Design/Build Contract for U.S. Department of Justice Robert F. Kennedy Building - Elevator Modernization Project

Table of Contents

I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. FAR 52.236-27 Site Visit – Construction H. Receipt of Offers

II. Proposals A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal E. Other Information to be Submitted with Proposal F. Requirements of Joint Venture Offerors

III. General Provisions A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Affirmative Procurement Program F. Notice Concerning Preparation of Proposals G. Bond Requirements H. Contractor Performance Information I. Safeguarding and Dissemination of Controlled Unclassified Information

(CUI) Building Information

J. INFORM

K. Mega Construction Project Program

IV. FAR/GSAR Solicitation Provisions

A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR 101-29

B. FAR 52.211-3, Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Items Description

C. FAR 52.216-1 Type Of Contract D. FAR 52.222-5 Construction Wage Rate Requirements-Secondary Site of

Work E. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure

Equal Employment Opportunity for Construction F. Buy American Requirements G. Buy American Exceptions H. FAR 52.233-2 Service of Protest I. FAR 52.252-1 Solicitation Provisions Incorporated by Reference J. GSAR 552.102 Incorporating Provisions and Clauses by Reference K. GSAR 552.252-5 Authorized Deviations in Provisions (Nov

2021)(DEVIATION FAR 52.252-5)

L. Small Business Subcontracting Plan M. Project Labor Agreement N. Certified Cost or Pricing Data O. Additional Provisions

(i) GSAR 552.236-74, Evaluation of Options (Mar 2019)

(ii) GSAR Clause 552.236-77, Government’s Right to Exercise Options (Mar 2019)

V. Instructions to Offerors and Clauses A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition B. Security Requirements C. Additional Clauses

VI. Method Of Award A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness/Price Realism D. Unbalanced Price E. Total Evaluated Price F. Non-Price Factors G. Evaluation of Joint Venture Offers

I. General Information

I.A. The Solicitation and Contract

(1) This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the Solicitation Documents. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.

(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.

(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer. No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.

I.B. List of Solicitation Documents

The Solicitation Documents are comprised of:

(1) The Solicitation

(2) Offeror Representations and Certifications Form

(3) Standard Form (SF) 1442 – Solicitation Offer and Award

(4) The Agreement and Attachments to the Agreement

(5) The Statement of Work, Specifications, Drawings, and Exhibits

I.C. Authorized Representatives

The following individuals are designated as the authorized GSA representatives under this Solicitation:

Authorized Representative Information:

Contracting Officer’s Information

Name: Kelly DeShields Address: 1800 F Street, NW, Washington DC 20407

Telephone: (202) 308-9146

Authorized Representative Information:

Email: kelly.deshields@gsa.gov

Alternate POC Information

Name: Elwora Ahmed Address: 1800 F Street, NW, Washington DC 20407

Telephone: 202-255-9273

Email: Elwora.Ahmed@gsa.gov

I.D. Pre-Proposal

Date: TBD

Time: TBD U.S. Department of Justice Robert F. Kennedy Building - Elevator Modernization located at 850 Pennsylvania Ave, NW Washington, DC 20530.

I.E. Estimated Price Range

The estimated price range for the Project is more than $10,000,000.

I.F. FAR 52.228-1 Bid Guarantee (Sep 96)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids;

and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

I.G. FAR 52.236-27 Site Visit – Construction (Feb 95)

(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.

(2) Site visits will be conducted by appointment only at the times and dates specified by the point of contact shown below. To arrange for a site visit, contact:

Name: Courtney Brown Address: U.S. Department of Justice Robert F. Kennedy Building - Elevator Modernization located at 950 Pennsylvania Ave, NW Washington, DC 20530 at the Visitor Center

Telephone: 202-812-9895

Email:Courtney.brown@gsa.gov

(3) Pre-registration is required for all attendees to the pre-proposal Site Visit. The Site Visit shall be limited to not more than four (4) representatives from each Offeror. Offerors shall submit a Visit Authorization Request (VAR) identifying all attendees from their respective team. Participants must have a valid, Government issued picture identification, driver’s license preferred, to gain access for the pre-proposal Site Visit. Notification of the location of entry, where attendees are required to meet, and all other requirements for the Site Visit will be issued to the Offerors. Submit the VAR to the point of contact listed below.

Offerors shall submit names of their attendees information via email to courtney.brown@gsa.gov no later than Monday, June 26, 2023 at 4PM EST.

Name of Attendee (First, Middle, Last) Date of Birth:

Company (Name, Address, phone number) Company Designation (Sub/Prime) Attendee Email:

Solicitation Number and Project Name

Site visits will be held at the following dates and times:

Date: Thursday, June 29, 2023

Time: 9:30AM-11:30AM

RFI Due:

Date: Wednesday, July 5th, 2023

Time: NLT 4PM EST.

I.H. Receipt of Offers

(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 4:00 pm Eastern Standard Time (EST) on the following date and at the following address.

Date: Revised To Wednesday, July 26, 2023.

Address: Please submit a separate copy of technical and price proposal electronically to the Contracting Kelly DeShields at kelly.deshields@gsa.gov and the Contract Specialist Elwora “Liza” Ahmed at Elwora.ahmed@gsa.gov

(2) Offers sent by commercial package delivery and hand delivery shall be deemed received as of the date and time of delivery to the office designated for receipt of offers.

(3) Offers sent by United States Mail shall be deemed timely if delivered to the address of the government installation designated for receipt of offers on or before the date established for receipt of offers.

II. Proposals

II.A. Proposal Contents

Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:

1. Price Proposal

2. Technical Proposal

3. Representations and Certifications

4. Standard Form 24, Bid Bond

5. Subcontracting Plan

6. GSA Form 527 – Contractor’s Qualification and Financial Information

7. Proprietary Information Agreement(s)

8. Other Documents as Required

II.B. Proposal Format

Technical and Price Proposals shall be submitted electronically, via email, to the Contract Specialist and the Contracting Officer.

All offers shall include a detailed cost breakdown on the attached BID SPREADSHEET.

II.C. Price Proposal

(1) Contents

The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for each price element shown on the pricing form included in Section II of the Agreement. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.

(2) Qualifications, Exclusions and Conditions

If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further consideration.

(3) Additional Proposal Requirements

Price proposal shall be submitted on the BID SPREADSHEET provided.

Offers not submitted on this form will be considered non-responsive.

Offers that do not include complete responses to all technical evaluation factors will be deemed non-responsive.

II.D. Technical Proposal

The Technical Proposal shall include the information requested below for the non-price factors described in Section VI.

Technical proposals will be evaluated independently of the price proposal.

Lowest Price Technically Acceptable

1. The Government will make award to the responsible Offeror whose proposal conforms to the solicitation and is the lowest priced technically acceptable offer. All technical factors are of equal weight and will be evaluated on a “go,” “no-go” basis.

The lowest priced proposal receiving a “go” for all technical factors will receive the award.

2. The Government will evaluate technical proposals to determine if an offer meets the minimum technically acceptable requirements. Failure to meet a technical requirement may result in an offer being determined technically unacceptable. A technically unacceptable rating for any one factor makes the entire proposal unacceptable.

3. The Government will evaluate the three (3) lowest price proposals first for technical acceptability. If they are considered technical acceptable, award will be made to the lowest price technically acceptable offeror. If the 3 lowest price proposals are determined to be unacceptable, the Government will review the next 3 lowest price proposals. The evaluation process shall continue until the Government determines a lowest price technically acceptable offeror.

The following non-price factors will be evaluated for acceptability:

Consensus - Each evaluator will independently evaluate all the technical aspects of the proposal(s). After the individual evaluators have separately evaluated the proposal(s), including preparation of their narrative explanations, the panel, under the leadership of the chairman, will meet and formulate its collective conclusions. Go/No-go determinations will be accompanied by a detailed explanation.

Factor 1 - Experience on Similar Projects:

Evaluation Criteria:

This factor evaluates the extent of the Offeror’s past experience as a firm in providing similar construction services to determine the firm’s experience in completing the tasks detailed in the performance work statement.

Acceptability Standard:

The Offeror must demonstrate objective standard as a General Construction (GC) Contractor responsible for the construction of at least three (3) similar projects substantially completed within the last eight (8) years. A “similar project” is defined as a project that is comparable in nature, type, and complexity as defined by all of the following characteristics:

Project involved renovation or the modernization of the design and construction of at least 10 elevators.

Project was performed in an occupied office building.

Project involved all of the following disciplines - elevators (machine room and associated equipment: Fire/Life Safety, Mechanical and Electrical);

The total project construction cost at award of the construction contract(s) was not less than $8 million.

Submittal Requirement:

List three (3) construction projects that your firm has successfully completed over the last 8 years from the date of issuance of this solicitation. All 3 projects must, at a minimum, contain the following:

Project title and contract number Offeror’s role in the contract (prime or subcontractor); if subcontractor, list name, address, and phone number of prime contractor (Reference) Name of person representing the customer who is familiar with the project and their current phone number Project description and place of performance Contract period Project of minimum 10 elevators for design and construction services Description of work done directly by offeror Description of work done by subcontractor(s), if applicable (subcontracting plan) Original construction award amount Actual completion amount

If the project is presented for Joint Venture offerors, the proposal must indicate which participating member of the Joint Venture performed the services demonstrated. Maximum page count is 10 pages.

Factor 2 - Past Performance of Offeror

Evaluation Criteria: This factor evaluates the past performance of the Offeror to determine responsibility.

Acceptability Standard:

The Offeror’s past performance record demonstrates satisfactory performance on at least three (3) similar projects substantially completed within the last five (5) years. Any proposal which does not demonstrate satisfactory performance on at least three (3) similar projects substantially completed within the last five (5) years will not be considered technically acceptable.

Submittal Requirements:

The Offeror must provide a GC Reference Form for each reference (a person or persons who may be contacted regarding the quality of the Offeror’s past performance).

List three (3) construction projects that your firm has successfully completed over the last 8 years from the date of issuance of this solicitation. All 3 projects must, at a minimum, contain the following: Project title and contract number Offeror’s role in the contract (prime or subcontractor); if subcontractor, list name, address, and phone number of prime contractor

(Reference) Name of person representing the customer who is familiar with the project and their current phone number

Project description and place of performance Contract period Project of minimum 10 elevators for design and construction services Description of work done directly by offeror Description of work done by subcontractor(s), if applicable (subcontracting plan) Original construction award amount Actual completion amount

The Offeror must provide a GC Reference Form for each reference (a person or persons who may be contacted regarding the quality of the Offeror’s past performance).

This factor considers the past performance of the Offeror. For each project submitted under Factor 1, the Offeror shall submit no more than two Past Performance Questionnaires (PPQ) (Attachment 1) filled out by owner references with knowledge of the Offeror’s performance of the associated design build contract.

The Government requests that the offeror’s reference complete the PPQ and submit it directly back to the contract specialist along with the technical proposal. Questionnaires may also be submitted by references directly to the Government via email to Contracting Specialist. Offerors are entirely responsible for ensuring that PPQs are submitted by the due date and time for receipt of proposals.

The government reserves the right to verify any and all information on this form.

Acceptability Standard (Go): The Offeror will be deemed technically acceptable if ALL of the minimum acceptable criteria are clearly met by the proposal.

NOTE: Once the proposal(s) has/have been determined to be “technically acceptable,” the award will then be based on cost.

Offerors without a record of relevant past performance may not be evaluated favorably or unfavorably on past performance (i.e. they will receive a “neutral” rating)

To be rated “acceptable” for a project, all PPQ questions calling for an adjectival rating must be rated as satisfactory, very good, exceptional or not applicable and the reference must also answer “yes” to question 9.

Offerors are reminded that the completed Past Performance Questionnaires are confidential and are considered to contain procurement sensitive information (until determined otherwise).

The Government reserves the right to use other government data available in its assessment of the offeror. The quality of the reference information supplied will be considered. In accordance with FAR 15.306, the offeror will be given the opportunity to respond to adverse past performance information.

II.E. Other Information to Submit with Proposal

(1) Representations and Certifications

Offerors are reminded their SAM registration status must be “Active” at the time their offer is submitted to be considered for award (see FAR 52.204-7). Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for Award Management.

Offerors shall also submit with their proposal, the Annual Representations and Certifications (FAR 52.204-8),

(2) Qualifications of Offerors

Offerors submitting a proposal in response to this Solicitation shall submit with their proposal evidence of their financial responsibility and capacity to perform the Contract.

Offerors shall submit this information on GSA Form 527 – Contractor’s Qualifications and Financial Information. Where applicable, point of contact, including names and telephone numbers, are required for all contracts listed.

II.F. Requirements of Joint Venture Offerors

(1) All offers submitted by joint ventures must include a copy of an executed joint venture agreement (with original signatures) which fully discloses the legal identity of each member of the joint venture, the relationship between the members, the form of ownership of each member, and any limitations on liability or authority for each member.

(2) An authorized representative of each member of the joint venture must sign the SF 1442 accompanying an offer regardless of any agency relationship established between the members.

(3) In the case of corporations that are joint venture members, the corporation secretary must certify that the corporation is authorized to participate in the joint venture, either by so certifying in the joint venture agreement, or by submitting a separate certification to the Government. The joint venture must also provide a certificate that identifies a principal representative of the joint venture with full authority to bind the joint venture.

(4) Representations and certifications, financial information, and past performance information must be submitted for each member of the joint venture.

III. General Provisions

III.A. Availability of Funds

Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.

III.B. Requests for Clarification or Interpretation

The Government will attempt to answer all requests for clarifications or interpretations of the Solicitation Documents prior to the date set for receipt of offers.

III.C. Notice to Small Business Firms

A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (Small Business Administration). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.

III.D. Information Concerning the Disclosure of Solicitation Results

This acquisition is being conducted under the provisions of FAR Part 15 as a negotiated procurement. In accordance with FAR 3.104 and FAR 15.207, after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will be made available until after award except as provided by FAR 15.503.

III.E. Affirmative Procurement Program

GSA has implemented an Affirmative Procurement Program (APP) intended to maximize the use of recovered materials, environmentally preferable, and bio-based products. Offerors should familiarize themselves with the requirements for using and reporting on the use of such materials in performance as set forth in the Agreement.

Refer to Clause FAR 52.223-10 encouraging vendors to practice waste reduction.

III.F. Notice Concerning Preparation of Proposals

Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract, as contemplated by the Solicitation, in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.

III.G. Bond Requirements

If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond and payment bond as specified in the Agreement. Offerors who utilize individual sureties should note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR 52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Pledge of Assets.

III.H. Contractor Performance Information

(1) Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process. CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is Contractor Performance Assessment

Completed CPARS evaluations may then be used by the Federal acquisition community for use in making source selection decisions. CPARS assists acquisition officials by serving as the single source for contractor past performance data.

(2) CPARS Registration: Each award requiring an evaluation must be registered in CPARS. The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an e-mail that contains user account information, as well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.

(3) Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the CPARS training site (CPARS Training) and updated as needed.

(4) Contractor Representative (CR) Role: All evaluations will be sent to the Contractor Representative (CR) named on your award. The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.

Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.

GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.

Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.

III.I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information

Certain information contained in the Solicitation Documents may have been designated as Controlled Unclassified Information (CUI) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.

III.J. INFORM

A.

Not applicable (GSAM § 515.3702-2(a)(2))

III.K. Mega Construction Project Program

The Department of Labor’s Office of Federal Contract Compliance Programs (OFCCP) Mega Construction Project (Megaproject) Program fosters equal opportunity in the construction trades workforce of federal contractors and subcontractors on large federal construction projects.

When OFCCP designates a construction project as a Megaproject, OFCCP offers contractors and subcontractors extensive compliance assistance, conducts compliance evaluations, and fosters collaboration across the public and private sectors. From the earliest stages of a designated Megaproject, OFCCP engages a wide range of stakeholders in the community to remove hiring barriers and promote consideration of a diverse pool of qualified workers for jobs in the trades.

If this project is selected by OFCCP, the contractor will be required to participate in the Mega Construction Project Program and comply with the requirements enforced by

OFCCP.

To learn more about OFCCP’s Mega Construction Project Program, please see https://www.dol.gov/agencies/ofccp/construction/mega-program.

IV. FAR/GSAR Solicitation Provisions

IV.A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 (AUG 98)

(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to—

GSA Federal Supply Service Specifications Section, Suite 8100 470 East L’Enfant Plaza, SW Washington, DC 20407

Telephone (202) 619-8925 Facsimile (202) 619-8978

(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.

IV.B. FAR 52.211-3 Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions (JUN 1988)

(Applicable to solicitations that cite specifications not listed in the Index and are not furnished with the solicitation)

(a) The specifications cited in this solicitation may be obtained from: GSA Specifications Unit at (202) 755-0325. MIL Specifications may be obtained by calling

(215) 697-2179.

(b) The request should identify the solicitation number and the specification required by date, title, and number as cited in the solicitation.

IV.C. FAR 52.216-1 Type of Contract (APR 84)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

IV.D. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (MAY 14)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.

IV.E. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999)

(Applicable to solicitations resulting in construction contracts in excess of $10,000.)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

[CO Note: Locality goals can be found at Participation Goals ]

Goals for Minority Participation for Each Trade

Goals for Female Participation for Each Trade

28% 6.9%

These goals are applicable to all of the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade.

The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is:

IV.F. Buy American Requirements

Under $7,032,000 Between $7,032,000 and less than $12,001,460

$12,001,460 or more

Solicitation Provision

FAR 52.225-10 FAR 52.225-12

Alternate II

FAR 52.225-12

FAR 52.225-10 Notice of Buy American Requirement-Construction Materials (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the

Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested-

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

FAR 52.225-12 Notice of Buy American Requirement-Construction Materials Under Trade Agreements (MAY 2014) Alternate II (JUNE 2009)

(a) Definitions. "Bahrainian, Mexican, or Omani construction material," "Commercially available off-the-shelf (COTS) item," "construction material," "designated country construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials Under Trade Agreements" (Federal Acquisition Regulation (FAR) clause 52.225-11).

(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material, except foreign construction material from a designated country other than Bahrain, Mexico, or Oman that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material. An offer based on use of the foreign construction material for which an exception was requested-

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

FAR 52.225-12 Notice of Buy American Requirement-Construction Materials Under Trade Agreements (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "designated country construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials Under Trade Agreements" (Federal Acquisition Regulation (FAR) clause 52.225-11).

(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of the foreign construction material for which an exception was requested-

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

IV.G. Buy American Exceptions

For Buy American exceptions, if any, see the applicable Buy American clause in Section IV of the Agreement

IV.H. FAR 52.233-2 Service of Protest (SEP 06)

(a) Protests, as defined in section 31.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from the Contracting Officer at the address provided in the provision “Receipt of Offers” in Section I (General Information).

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

IV.I. FAR 52.252-1 Solicitation Provisions Incorporated by Reference

(FEB 98)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this address:

Federal Acquisition Regulation

NUMBER TITLE DATE

52.204-22 Alternative Line Item Proposal JAN 17

52.214-34 Submission of Offers in the English Language

APR 91

52.215-16 Facilities Capital Cost of Money JUN 03 52.219-4 Notice of Price Evaluation

Preference for HUBZone Small Business Concerns

OCT 22

NUMBER TITLE DATE

52.236-28 Preparation of Proposals -

Construction

OCT 97

IV.J. GSAR Clause 552.102 Incorporating Provisions and Clauses

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.

IV.K. GSAR 552.252-5 Authorized Deviations in Provisions (Nov 2021)(DEVIATION

FAR 52.252-5)

(a) Deviations to FAR provisions. This solicitation identifies any authorized deviation to a Federal Acquisition Regulation (FAR) (48 CFR chapter 1) provision by—

(1) The addition of “(DEVIATION)” after the date of the FAR provision when an authorized deviation to a FAR provision is being used, and

(2) The addition of “(DEVIATION FAR (provision number))” after the date of the GSAR provision when a GSAR provision is being used in lieu of a FAR provision.

(b) Deviations to GSAR provisions. This solicitation identifies any authorized deviation to a General Services Administration Acquisition Regulation (GSAR) (48 CFR chapter 5) provision by the addition of “(DEVIATION)” after the date of the provision.

(c) “Substantially the same as” provisions. Changes in wording of provisions prescribed for use on a “substantially the same as” basis are not considered deviations.

IV.L. Small Business Subcontracting Plan

A Small Business Subcontracting Plan, as required under FAR 52.219-9, is /is not required to be submitted with offers.

IV.M. Project Labor Agreement (PLA)

(1) This Project Labor Agreement section only applies to proposals submitted subject to the PLA requirements of this solicitation.

(2) FAR 52.222-33 Notice of Requirement for Project Labor Agreement (May 2010) Alternate 1 (DEVIATION July 2011)

(a) Definitions. “Labor organization” and “project labor agreement,” as used in this provision, are defined in the clause of this solicitation entitled Project Labor Agreement.

(b) The apparent successful offeror shall negotiate a project labor agreement with all labor organizations having jurisdiction over the trades involved in the construction of the project. The project labor agreement must be signed by all such labor organizations and cover the entirety of the construction work to be performed during the term of the resulting construction contract.

(c) Consistent with applicable law, the project labor agreement reached pursuant to this provision shall—

(1) Bind the offeror and all subcontractors engaged in construction on the construction project to comply with the project labor agreement;

(2) Allow the offeror and all subcontractors to compete for contracts and subcontracts without regard to whether they are otherwise parties to collective bargaining agreements;

(3) Contain guarantees against strikes, lockouts, and similar job disruptions;

(4) Set forth effective, prompt, and mutually binding procedures for resolving labor disputes arising during the term of the project labor agreement;

(5) Provide other mechanisms for labor-management cooperation on matters of mutual interest and concern, including productivity, quality of work, safety, and health; and

(6) Fully conform to all statutes, regulations, Executive orders, and agency requirements.

(d) Any project labor agreement reached pursuant to this provision does not change the terms of this contract or provide for any price adjustment by the Government.

(e) The apparent successful offeror shall submit to the Contracting Officer a copy of the project labor agreement prior to contract award.

(3) The requirements of 52.222-33 Alt I are supplemented as follows:

(a) The project labor agreement reached pursuant to FAR 52.222-33 Alt I shall supersede the terms of any other collective bargaining agreement that conflict with the terms of such project labor agreement.

(b) Within 30 days following receipt of written notification to the apparent successful offeror by the Contracting Officer, the apparent successful offeror shall furnish the Contracting Officer with a copy of an executed project labor agreement that meets the requirements of this Section. If, for any reason, the apparent successful offeror fails to furnish such project labor agreement within the time stated above, the Government may, in its sole discretion, eliminate the proposal from consideration and select the next apparent successful offeror.

IV.N. Requiring Certified Cost or Pricing Data [15.403-4]

N/A

IV.O. Additional Provisions

(i) GSAR 552.236-74, Evaluation of Options (Mar 2019) [

(ii) GSAR Clause 552.236-77, Government’s Right to Exercise Options (Mar

2019)

V. Instructions and Clauses

V.A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition (NOV 2021)

(a) Definitions. As used in this provision-

Discussions are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.

In writing, "writing," or "written" means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.