This document contains a solicitation for construction manager as constructor (CMc) services for the alteration of the Tomochichi Federal Building and U.S. Courthouse in Savannah, Georgia. The General Services Administration (GSA) is seeking a CMc to provide all management, supervision, labor, equipment and supplies necessary for the project. The estimated total construction costs range from $50 to $60 million, with construction anticipated to begin in January 2021 and last approximately 2.5 years. The scope of work involves repair, renovation, rehabilitation, preservation, and alteration of the historic courthouse building and systems upgrades. The base contract will be a firm-fixed-price design-phase services contract, with option periods to include construction services to be awarded as a guaranteed maximum price contract. Proposals are due by September 28, 2020. To be eligible for award, offerors must be registered in the System for Award Management.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Manager as Constructor (CMc) Contract for the Alteration of the Tomochichi Federal Building and U.S. Courthouse, 125 Bull Street, Savannah, Georgia, 31401. Solicitation # 47PF0020R0071.
Tomochichi CMc Pricing Sheet (Attachment to SF1442) Revision 1
CLIN ITEM PRICE
1 Base - Design Phase Services (Firm Fixed Price) $
2 Option 1 - Estimated Cost of Work (ECW) $
3 Option 1 - CMc Contingency Allowance (CCA) Percentage _3_ %
4 Option 1 - CCA (2 x3) $
5 Option 1 - Fee Percentage (Overhead + Profit) __ %
6 Option 1 - Fee (2 x 5) $
7 Option 1 - Guaranteed Maximum Price (GMP) for Construction Services (2+4+6)
8 Total Evaluated Price (1+7) $
9 Overhead Rate for Contract Changes %
10 Profit Rate for Contract Changes
Note: can not exceed 10%
11 Markups on Subcontractors for Contract Changes =
½ X (9+10)
Note: can not exceed 10%
Note: For CLIN 9, 10 and 11, see the chart on the next page for further explanation
552.243-71 EQUITABLE ADJUSTMENTS CLAUSE
Markups Prime Sub Tier 1 Sub Tier 2 Sub Tier 3
Overhead
Negotiated, and may be subject to audit and adjustment. Only applied to Primes self performed work
At 50% of OH And Profit negotiated with Prime, but not to exceed 10% combined Only allowed on subs direct cost. Not allowed on subs profit and
OH
At 50% of OH And Profit negotiated with Prime, but not to exceed 10% combined Only allowed on subs direct cost. Not allowed on subs profit and
OH
Not Allowed
Profit
Negotiated, but not to exceed 10%, Applied only to Prime's self performed DC + Prime's OH Not Allowed
Bond & Insurance - if a direct cost of prime and not part of OH
Calculated after OH and Profit are applied, if premium computed based on Total Contract Value. But cannot be applied if they are already included in the OH rate.
Notes, per the Equitable Adjustments Clause 552.243-71:
1. The Prime and its subcontractors shall not be allowed OH and profit on the OH or profit received by a subcontractor
2. The Prime can only apply OH rate to self performed work