About this file

This notice announces a solicitation for construction manager as constructor services for the alteration of the Tomochichi Federal Building and U.S. Courthouse in Savannah, Georgia. The project involves renovations, repairs, and upgrades to building systems for the 125,668 gross square foot historic courthouse, including three courtrooms. The estimated construction cost range is $50-60 million. The construction manager as constructor will provide preconstruction and construction phase services, working with the selected architect-engineer firm and construction manager as agent. The base contract will be awarded on a firm-fixed price basis. The solicitation will be issued on August 28, 2020 and offers will be due on September 28, 2020. A pre-proposal conference will be held on September 9, 2020. The solicitation will be available electronically through beta.SAM.gov. The applicable NAICS code is 236220 with a small business size standard of $39.5 million.

View the file

Other files

File Type Posted
Tomochichi CMc Questions and Answers (120-182) - 10.21.20 Final.pdf PDF
47PF0020R0071 Amendment 004.pdf PDF
47PF0020R0071 Amendment_003.pdf PDF
Tomochichi CMc Pricing Sheet (Attachment to SF1442) - Final R2.pdf PDF
Tomochichi CMc Preproposal Meeting Minutes 10.06.2020 - Final.pdf PDF
Tomochichi CMc Questions and Answers 10.15.2020.pdf PDF
SF1442-14b R1.pdf PDF
47PF0020R0071 Amendment 001.pdf PDF
47PF0020R0071 Amendment 002.pdf PDF
Tomochichi CMc Pricing Sheet (Attachment to SF1442) - Final R1.pdf PDF
GSA TOMO SCHEDULE 20_1005 CMc Collapsed.pdf PDF
Tomochichi CMc Questions and Answers 10.07.2020.pdf PDF
Site Visit Request Form -Tomochichi CMc -Final.pdf PDF
Tomochichi CMc - Preproposal Contractor Attendance 10.06.2020.pdf PDF
Tomochichi CMc Pre-proposal Agenda - Final 10.06.20.pdf PDF
Tomochichi CMc Pricing Sheet (Attachment to SF1442) - Final.pdf PDF
SF24-16d.pdf PDF
Model_Subcontracting_Plan_Updated Apr 2020.pdf PDF
Tomo CMc Pre-Proposal RSVP Form - Final.pdf PDF
Tomo CMc PPQ.pdf PDF
CIO_IT_Security_09-48.pdf PDF
CIO 12-2018_ IT Policy Requirements Guide_0.pdf PDF
CMc Reps and Certs 09.22.20 Tomo.pdf PDF
SF1442-14b.pdf PDF
PBS_3490.3_CIU.pdf PDF
Davis Bacon GA20190117.pdf PDF
018111a KSP Construction Product Tracking Form.pdf PDF
GSA527-15e.pdf PDF
CMc Solicitation 09.22.20 Tomo.pdf PDF
CMcSOW Final.docx.pdf PDF
CMc Agreement 09.22.20 Tomo.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GSA Division 01 Guide Specifications

For

Construction Manager as Constructor (CMC) Contract

PROJECT IDENTIFICATION

Project Name: Alteration of the Tomochichi Federal Building and Courthouse

Project Number: TBD

Region: Region 4

Building Name: Tomochichi CTHS

Building Address: 125 Bull Street, Savannah Georgia

Spec Writer: Sam Harris Date: 18 AUG 2020

Alteration of the Tomochichi Federal Building and Courthouse Savannah, Georgia.

TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

Contents

TABLE OF CONTENTS

SECTION 011000 – SUMMARY

SECTION 011400-WORK RESTRICTIONS

SECTION 012100 – ALLOWANCES

SECTION 012500-SUBSTITUTION PROCEDURES

SECTION 012600-CONTRACT MODIFICATION PROCEDURES

SECTION 012900-PAYMENT PROCEDURES

SECTION 013000 – gBUILD

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

SECTION 013103 – BIM EXECUTION PLANNING

SECTION 013110 - CRITICAL PATH METHOD SCHEDULING

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

SECTION 013220 - PHOTOGRAPHIC DOCUMENTATION

SECTION 013300 - SUBMITTAL PROCEDURES

SECTION 014000 - QUALITY ASSURANCE & CONTROL REQUIREMENTS

SECTION 014025 – QUALITY CONTROL TESTING FOR AIR BARRIER SYSTEMS

SECTION 015639 - TREE AND PLANT PROTECTION

SECTION 015950 - SAFETY AND HEALTH

SECTION 016000 - PRODUCT REQUIREMENTS

SECTION 017000 - EXECUTION REQUIREMENTS

SECTION 017310 - CUTTING AND PATCHING

SECTION 017320 - SELECTIVE DEMOLITION

SECTION 017350 - FIRE PREVENTION PRECAUTIONS FOR HOT WORK

SECTION 017419 - CONSTRUCTION NONHAZARDOUS WASTE MANAGEMENT AND DISPOSAL .. 89

SECTION 017700 - CLOSEOUT PROCEDURES

SECTION 017810 - PROJECT RECORD DOCUMENTS

SECTION 017822 - OPERATION AND MAINTENANCE DOCUMENTATION

SECTION 018111 - SUSTAINABLE DESIGN REQUIREMENTS

SECTION 018113 - Green Purchasing Plan Requirements

SECTION 018200 - DEMONSTRATION AND TRAINING

SECTION 019113 - FACILITY COMMISSIONING

SECTION 011000 – SUMMARY

PART 1 - GENERAL

1.1 PROJECT INFORMATION

A. Project Name and Location:

Renovation of Tomochichi Federal Courthouse

125 Bull St. Savannah, GA 31401

B. Project Summary Description:

The Scope of work is addressed in the attached Narrative and drawings. Many of the deficiencies identified in the existing building, such as the lack of accessibility, code-compliant egress and secure circulation among other security concerns, along with the poor condition of the building systems, will be addressed by the renovations.

C. Architect: The term Architect refers to the project designer. The Architect's status relative to the construction will be stated in writing by the Contracting Officer prior to the pre-construction conference. The project is designed by: Liollio, Hartman-Cox Architects JV

D. Project Delivery Method: Construction Manager as Contractor (CMc)

E. Jacobs Technologies Inc.

F. See GSA’s Partnering with the Public Building Service Policy dated March 5, 2014.

G. Jacobs Technologies Inc.

H. Construction Manager as Constructor (CMc): TBD

1. Construction Manager as Constructor (CMc) has been engaged for this Project to serve as Project's constructor. In Divisions 01 through 49 Sections, the term "Construction Manager (CMc)" or "CMc" denotes the Construction Manager as Constructor, and the terms "Construction Manager (CMc)" and "Contractor" are synonymous.

I. The Contracting Officer for the project is: Helen Dimonte.

1.2 WORK SEQUENCE

A. The work shall be conducted in phases in the building As determined by the CMc. Prior to the Notice to Proceed (NTP) for the Construction Phase of the project, the building shall be vacant.

1.3 WORK BY OTHER CONTRACTORS

A. The Contractor shall cooperate with other contractors performing related work, including providing labor, materials and other costs necessary to satisfactorily coordinate the Contract work with work performed under other contracts.

1.4 SCHEDULE OF GOVERNMENT-FURNISHED PROPERTY

A. The project may include Government furnished property to be installed by the Contractor. The contractor shall advise GSA at least 30 days in advance of when the property should be delivered.

1.5 MISCELLANEOUS PROVISIONS

A. Work in existing facilities shall correspond in all respects with the existing conditions to which it connects, or to similar existing conditions, in materials, workmanship and finish.

B. Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of Work under the Contract.

Work out of alignment where exposed by removal of existing work shall be called to the attention of GSA. Necessary corrective work shall be as directed.

1. Replacements of existing conditions that are removed shall match similar existing conditions.

2. Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting Officer.

3. Conditions remaining in place, which are damaged or defaced during the Work, shall be restored to the condition existing at time of award of Contract.

4. Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.

C. Existing structures will remain in place unless indicated otherwise.

D. Existing utility services and equipment will remain in place as indicated in the drawings and specifications.

E. The Contractor will be required to engage and provide Telephone Service into the building and provide for the required analog telephone lines to required devices. The Contractor base bid on providing nine (9) analog lines.

F. Removed items indicated to remain the property of the Government shall be stored on site where directed by the Contracting Officer.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 011000

SECTION 011400-WORK RESTRICTIONS

PART 1 -GENERAL

1.1CONTRACTOR USE OF PREMISES

A. Conduct a pre-construction survey to review and document the existing conditions surrounding the project premises prior to the beginning of any construction activity.

B. During the construction period, the Contractor shall have full use of the designated premises for construction operations, including full use of the indicated work site, limited only by the Government's right to perform work or retain other contractors to perform work on portions of the project.

1.2 GOVERNMENT OCCUPANCY

A. The Government reserves the right to occupy, place, and install equipment in completed areas of the building prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. The Government's installation of equipment and partial occupancy shall not constitute acceptance of the total Work.

1. Prior to partial Government occupancy, mechanical and electrical systems for the space shall be fully operational, and required inspections and tests shall be successfully completed. Upon occupancy, the

Government will operate and maintain mechanical and electrical systems serving the occupied portions of the building.

2. Upon occupancy, the Government will assume responsibility for maintenance and custodial service for the occupied portions of the building.

PART 2 -PRODUCTS (Not Applicable)

PART 3 -EXECUTION (Not Applicable)

END OF SECTION 01140

SECTION 012100 – ALLOWANCES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. The RFP and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Sections, apply to this Section.

B. Reference RFP Section B—5.1, page I-b-3

1.2 SUMMARY

A. Certain materials, equipment or other work are specified in the Contract Documents by allowance to defer selection of actual materials, equipment or other work to a later date when additional information is available for evaluation.

B. An allowance amount is stated as a lump sum, or is stated as a unit price for an indicated quantity with the unit price multiplied by the indicated quantity establishing a lump sum.

C. An allowance amount shall be included in the contract price, and the contract price will be adjusted by change order for the difference between the allowance amount and the actual approved amount for the work.

D. For an allowance stated as a unit price, the actual quantity and calculation of the actual amount shall be approved by the Contracting Officer (“CO”) after completion and acceptance of the allowance work, based on the following information when applicable:

1. Invoices or delivery slips.

2. Credit from manufacturer or supplier for unused material.

3. In-place measurements provided by the Construction Manager as Contractor (“CMC”) Contractor, the allowance subcontractor and the CO, either individually or collectively.

4. Other relevant data.

1.3 PROCEDURES

A. At the earliest practical date after award of the Contract, the CMC Contractor shall notify the CO of the date when the final selection must be completed for material, equipment or other work described by an allowance, to avoid delaying the total project Work.

B. When notified by the CO of the selection of the specific material, equipment or other work, the CMC Contractor shall secure competitive bids for the work of the allowance.

1. Bids shall be based on drawings, specifications and other information provided by the CO.

2. The CMC Contractor and the CO shall set an agreed date and time for receipt of bids.

3. Each bid shall be addressed and delivered to the CMC Contractor in a sealed envelope.

4. Bids received by the CMC Contractor by the date and time for receipt of bids shall be opened at that time and the CMC Contractor shall forward one copy of each bid along with a certified statement that each was received in a sealed envelope prior to the time for receipt of bids to the CO.

5. Any bid received by the CMC Contractor after the time for receipt of bids shall not be opened, but shall be time-stamped on the envelope and forwarded to the CO in the original sealed envelope.

C. The CMC Contractor shall award the subcontract for the allowance work in the bid amount to the bidder acceptable to both the Contractor and the CO.

1.4 ALLOWANCE FOR PURCHASE

A. An allowance for the purchase of material or equipment shall cover only the cost of the material or equipment delivered to the site, less applicable trade discounts.

B. The CMC Contractor's costs for unloading and handling at the site, labor and other installation costs, overhead, profit and other expenses contemplated for the total allowance work shall be included in the contract price but not in the allowance amount.

1.5 ALLOWANCE FOR FULL WORK

A. An allowance for the described full work shall cover all costs contemplated for the work, except the CMC Contractor's overhead, profit and related expenses for coordination with the subcontractor.

B. The CMC Contractor's overhead, profit and related expenses for coordination with the subcontractor shall be included in the contract price but not in the allowance amount.

C. Unless the description of an allowance specifically limits the amount to the purchase of material or equipment, the allowance shall include the full work.

1.6 SUBMITTALS

A. Submit subcontract bids for allowance work, as specified, for the CO's selection and approval.

B. When requested by the CO, submit invoices or delivery slips, credit slips, measurements and other data showing actual quantities in fulfillment of allowance work.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Promptly upon delivery, examine materials and equipment covered by an allowance for damage or defects.

B. Replace damaged or defective materials and equipment with specified products without damage or defects.

3.2 PREPARATION

A. Coordinate materials, equipment and their installation for the allowance work with related material, equipment and installations for complete integration and interfacing of the allowance and related work.

3.3 SCHEDULE OF ALLOWANCES

A. Allowance No. 1: Include an allowance of $40,000 for interior and exterior signage as part of project funding IAW GSA-PBS P-100. The cost of construction and installation, including all direct, indirect, overhead, fees, commission, contractor related bonds and other costs that generally make up the cost of the Work is included in the CMC contract amount as stated in 1.5 ALLOWANCE FOR FULL WORK above.

B. Allowance No. 2: Include an allowance of $80,000 for the cost of providing audio visual As related to the Courts infrastructure. The cost of construction, including all direct, indirect, overhead, fees, commission, contractor related bonds and other costs that generally make up the cost of the Work is included in the CMC Contractor’s contract amount as stated in 1.5 ALLOWANCE FOR FULL WORK above.

C. Allowance No. 3: Include an allowance of $500,000 for interior and exterior demolition as part of project funding for hazardous material abatement. The cost of construction including all direct, indirect, overhead, fees, commission, contractor related bonds and other costs that generally make up the cost of the Work is included in the CMC contract amount as stated in 1.5 ALLOWANCE FOR FULL WORK above.

D. Allowance No. 4: Include an allowance of $100,000 for or cementitious fireproofing of existing building components to Type IIA protected construction IAW the International Building Code. The cost of construction including all direct, indirect, overhead, fees, commission, contractor related bonds and other costs that generally make up the cost of the Work is included in the CMC contract amount as stated in 1.5 ALLOWANCE FOR FULL WORK above.

END OF SECTION 01210

SECTION 012500-SUBSTITUTION PROCEDURES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Sections:

1. Division 01 Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

2. Divisions 02 through 49 Sections for specific requirements and limitations for substitutions.

1.3 DEFINITIONS

A. Substitutions: Proposed changes to the Contract Documents by the Contractor for products, materials, equipment, and methods of construction.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner

1.4 SUBMITTALS:

A. Substitution Requests: Per Submittal Procedures Section 013300 submit electronic copies through ePM of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: CSI Form 13.1A or approved equal

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.

b. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by the Government and separate contractors that will be necessary to accommodate proposed substitution.

Detailed comparison of significant qualities of proposed substitution with those of the Work specified.

Include annotated copy of applicable specification section.

Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, energy and resource

SUBSTITUTION PROCEDURES performance goals, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects with project name, location and contact information of owner and architect/engineer of record.

h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for project, when applicable for the proposed substitution.

j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work. If specified product or method of construction cannot be provided within the

Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery. Provide a schedule fragnet with a time impact analysis to allow the Government to consider the proposed substitution.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

m. The Contracting Officer may require the Contractor to a contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. The Contracting Officer or Contracting Officer’s Representative (CO) or (COR)

Action: If necessary, the Contracting Officer or COR will request additional information or documentation for evaluation within 7 days of receipt of a request for substitution. CO or COR will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later. The Contractor shall be entitled to receive notice of action on submittals within a reasonable time, given the volume or complexity of the submittals and the criticality of the affected activities to Substantial Completion as may be indicated in the Project

Schedule. The Contractor shall not be entitled to receive notice of action on submittals containing variations from Contract requirements in less than twenty working days.

a. Forms of Acceptance: Change Order, Construction Change Directive, or the Contracting Officer

(CO)'s Supplemental Instructions for minor changes in the Work.

b. Failure by the government to respond does not constitute acceptance of the proposed substitution.

1.5 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.

1.6PROCEDURES

A. Coordination: Modify or adjust affected work as necessary to integrate work of the approved substitutions.

PART 2 -PRODUCTS

2.1SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change, but not later than15 days prior to time required for preparation and review of related submittals.

1. Conditions: The Contracting Officer (CO)will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, the Contracting Officer

(CO)will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. If requested substitution involves schedule impact Contractor has identified time impact and a mitigation plan.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: The Contracting Officer (CO) will consider requests for substitution if received within 60 days after Notice to Proceed for construction. Requests received after that time may be considered or rejected at discretion of the Contracting Officer (CO) or the Contracting Officer

Representative (COR).

1. Conditions: The Contracting Officer will consider Contractor's request for substitution when the following conditions are satisfied.

a. Requested substitution offers the Government a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional obligations the Government incurs.

b. Requested substitution does not require extensive revisions to the Contract Documents.

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Substitution request is fully documented and properly submitted. If requested substitution involves schedule impact Contractor has identified time impact and a mitigation plan.

e. Requested substitution has received necessary approvals of authorities having jurisdiction.

f. Requested substitution is compatible with other portions of the Work.

g. Requested substitution has been coordinated with other portions of the Work.

h. Requested substitution provides specified warranty.

i. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

END OF SECTION 012500

SECTION 012600-CONTRACT MODIFICATION PROCEDURES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing Contract modifications.

B. Related Sections:

1. Division 016000 Section "Product Requirements" for administrative procedures for handling requests for substitutions made after Contract award.

2. Section 012500 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.

1.3 PROPOSAL REQUESTS

1. Proposal Requests issued by GSA are not instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request or 20 calendar days, when not otherwise specified, after receipt of Proposal Request, submit a proposal estimating cost adjustments to the Contract Sum and the

Contract Time necessary to execute the change to the Contracting Officer [CO].

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship.

Use available total float before requesting an extension of the Contract Time.

B. Comply with requirements in Division 01 section 013110CPM Scheduling.Contractor-Initiated

Proposals: If Contractor encounters any condition that may give rise to a modification to the Contract, Contractor shall submit a request for a change to GSA.

1. Include a statement outlining reasons for the change and the effect of the change on the Work.

Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship.

Use available total float before requesting an extension of the Contract Time.

6. Comply with requirements in Division 01 section 013110 CPM Scheduling Comply with requirements in

Division01 Section "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

1.4 CHANGE ORDER PROCEDURES

A. Upon acceptance GSA will issue a contract modification on standard form 30 (SF30).

PART 2 -PRODUCTS (Not Applicable)

END OF SECTION 012600

SECTION 012900-PAYMENT PROCEDURES

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process

Requests for Payment.

1.2 DEFINITIONS

A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Requests for Payment. The

Agreement (aka contract templates) provides further details.

B. Request for Payment: Contractor invoice and request for progress payment with substantiating information consistent with approved schedule of values.

1.3 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's

Construction schedule. Submit completed Schedule of Values no later than [14] calendar days prior to scheduled date of initial Requests for Payment.

B. Schedules for Phased Work: Where the work is separated into phases, provide Schedules showing values correlated with each phase using the standard format referenced below.

C. Format and Content: Contractor shall be responsible to complete the GSA Schedule of Values

Workbook and compile the values into electronic Project Management (ePM) System. Contractor will enter values into workbook prior to ePM input and provide associated electronic baseline copy to contracting officer for record. Contractor will follow guidelines in the Schedule of Values workbook to support ePM upload.

1. Identification: Complete the following Project Identification fields in the Schedule of Values:

a. Project Name

b. Project Number

c. Base Contract Numbered. Modification Number

e. GSA Project Manager

f. Contractor's Name and contact information

g. Date of submittal

2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of

Requests for Payment and progress reports.

a. Work activity – (by division or specific work activity)

b. Dollar value of each specific work activity –both with an amount in dollars and whole cents, and as a percentage of the Contract Sum to nearest one-hundredth percent. Adjust the amounts to total to the

Contract Sum and the percentages to total 100 percent.

c. Labor.

d. Materials

e. Equipment

f. Each item in the schedule of valuesand Requests for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item. (i.e. no stand alone item for OH, and P)

g. Modifications that affect value.

h. Update affected work branches and subordinate line items and

i. resubmit the schedule of values before the next Request for Payment when Modifications result in a change in the Contract Sum

j. Line item for mobilization and de-mobilization

k. Line item for close out (% to be negotiated with GSA COR)

3. Options: Provide a separate Schedule of Values for each exercised Option.

4. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

5. Provide a separate line item in the schedule of values for each part of the Work where Requests for

Payment may include materials or equipment purchased or fabricated and stored, but not yet installed. a.

Differentiate between items stored on-site and items stored off-site. If required, include evidence of insurance.

6. Each item in the Schedule of Values and Requests for Payment shall be complete. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at the government's option.

7. Revise and update workbook in ePM with all items affecting scope, schedule or cost and resubmit within 14 calendar days as coordinated with project manager or contracting officer. Contractor shall provide a final as-built schedule at project completion. Update affected work branches and subordinate line items and resubmit the schedule of values before the next Request for Payment when Modifications result in a change in the Contract Sum

1.4 REQUESTS FOR PAYMENT

A. Requirements for Requests for Payment are in Section III, Terms and Conditions of the Agreement.

B. Each Request for Payment following the initial Request for Payment shall be consistent with previous

Requests.

1. Initial Request for Payment, Request for Payment at time of Substantial Completion, and final Request for Payment involve additional requirements.

C. Payment Request Times: Submit on a timetable to be mutually agreed-upon by GSA and the CMC

Contractor after award

1. Enter in ePM along with construction progress report sevendays prior to due date for review by GSA.

Provide documentation evidencing the cost of work performed to be included in the Request for Payment.

Resolve questions resulting from GSA review of draft Request for Payment and construction progress report prior to submitting Request for Payment.

D. Request Preparation: All payments must be executed by a person authorized to legally bind the

Contractor.

1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.

2. Include amounts for work completed following effective date of previous Request for Payment, whether or not payment has been received. Include only amounts for work completed as of effective date of current Request for Payment.

3. Include amounts of Modifications issued before last day of construction period covered by Request.

E. Stored Materials: Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, and consent of surety to payment, for stored materials.

2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation.

3. Provide summary documentation for stored materials indicating the following:

a. Value of materials previously stored and remaining stored as of effective date of previous Request for

Payment.

b. Value of previously stored materials put in place after effective date of previous Request for Payment and on or before effective date of current Request for Payment.

c. Value of materials stored since effective date of previous Request for Payment and remaining stored as of effective date of current Request for Payment.

F. Initial Request for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Request for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule per Agreement (startup if not final).

4. Products list (preliminary if not final).

5. Sustainable design submittal for project materials cost data.

6. Sustainable design action plans.

7. Schedule of unit prices.

8. Submittal schedule (preliminary if not final).

9. List of Contractor's staff assignments.

10. List of Contractor's principal consultants.

11. Copies of building permits.

12. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

13. Initial progress report.

14. Report of preconstruction conference.

G. Request for Payment at Substantial Completion: After GSA issues the Notice of Substantial

Completion, submit a Request for Payment less previous payments made for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This Request shall reflect Notices of Substantial Completion issued previously for GSA occupancy of designated portions of the Work.

H. Final Payment Request: The Agreement provides further details

PART 2 -PRODUCTS (Not Applicable)

END OF SECTION 012900

SECTION 013000 – gBUILD (GREEN BUILDING UPGRADE INFORMATION

LIFECYCLE DATABASE)

PART 1 - GENERAL

1.1 PURPOSE

A. The Contractor shall use GSA’s web-based Green Building Upgrade Information Lifecycle Database

(gBUILD) system, a custom database primarily used for tracking sustainable design elements and goals within Capital Projects. The system may also be used by Small Projects if required by the PBS Office of

Facilities Management and Services Programs.

1.2 DEFINITION

A. gBUILD is a web-based project information system that collect project sustainability information such as scope details and anticipated savings from project teams, and aggregates it for GSA’s Public Buildings

Service. gBUILD’s project creation and document storage is integrated with ePM to avoid duplicative entry. gBUILD gathers information about project scope and technologies, performance goals, anticipated

LEED ratings, compliance with the Guiding Principles for New Construction and Major Renovations, commissioning, and innovative designs. The system is GSA’s system of record for reporting on the capital construction and modernization program by scope, for predicting projects’ cumulative contribution toward agency-wide sustainability goals, and for ensuring compliance with certain environmental laws and executive orders.

1.3 PROJECT COLLABOARTION AND DOCUMENTATION

A. General

1. The Contractor shall effectively manage assigned project records within gBUILD, including maintaining adequate staffing levels and ensuring that personnel attend the mandatory GSA-provided training sessions.

2. The Contractor shall use gBUILD to report and update project information at critical design and construction milestones throughout the project. Required information includes: project narratives; scope details; anticipated energy, water, and solid waste diversion performance; technologies; compliance status with GSA's Minimum Performance Criteria; supporting calculations and documentation. The

Contractor shall respond to quarterly data calls from GSA, and establish a main gBUILD point of contact accountable for keeping project records current. Classified material is not permitted to be stored in this system.

3. The Contractor shall use the workflow processes contained within gBUILD to submit and receive approval for the contents of forms including Scope reportable detail on each system or feature being installed or upgraded, Key Performance Measures anticipated energy and water performance, plus actual construction and demolition waste diversion figures, and Compliance. The compliance tab contains

GSA’s Minimum Performance Criteria, which are a checklist of 39 items that track project compliance with the Guiding Principles for New Construction and Major Modernization, as mandated by Executive Order

13514.

4. The Contractor shall monitor and review gBUILD monthly, to ensure the Contractor data is current through completion of the Close-out Phase of Construction.

B. Contents of gBUILD

1. The Contractor shall use gBUILD as the electronic system of record for project sustainability information and supporting documentation. Minimum Requirements:

a. Project Basics: N/A

b. Financials: N/A

c. not used

d. Scope: Report all applicable scope items

e. Performance Projections: Indicate if EUAS represents accurate baseline information; Select the method by which energy savings will be reported

f. LEED: Anticipated LEED certification level, LEED rating system, LEED version number

g. Energy Star:

h. Waste Management: Waste diversion target, Total C&D waste (tonnage), Total C&D waste diverted (tonnage)

i. Compliance: Provide current MPC Status, upload submission requirements and related documents

j. Building Closeout: Commissioning information, Compliance and Requirements checklist

2. Submittal Requirements:

A. MPC 1-Integrated HPGB Design Plan:

a. Integrated design team disciplines/frequency

b. Integrated design team disciplines

c. List of integrated team meetings

d. Basis of design and latest review drawings or specifications

e. Integrated design narratives

f. Building operations narrative B. MPC 2-Commissioning-Independent Agent:

a. Commissioning agent

b. Commissioning agent contract

c. Date commissioning agent hired

d. Commissioning design review/plan C. MPC 3-Commissioning: N/A D. MPC 4-Energy Efficiency: Reduce Fossil-Fuels and Energy Usage:

a. Target finder report and input/outputs

b. ASHRAE 90.1 2007 baseline building calculations

c. Building as designed % reduction ASHRAE 90.1 2007 calculations

d. Energy model or energy study E. MPC 5-Measurement and Verification:

a. Advanced meters narrative

b. Advanced meters sub-metering description F. MPC 6-Energy Efficiency: Energy Start and FEMP: N/A G. MPC 7-On-Site Renewable Energy, Solar for Hot Water

a. Solar hot water narrative

b. Solar hot water production target

c. Lifecycle cost figures

d. Solar hot water calculations

e. Solar hot water life cycle cost analysis H. MPC 8-Renewable Energy: Photovoltaic, Wind, Geothermal, Solar Thermal, Passive Solar Design, Cogeneration and Biomass

a. Renewable energy narrative

b. Renewable energy LCC figures

c. Renewable energy calculations

d. Renewable energy life cycle cost analysis I. MPC 9-Asses Solar Heat Gain

a. Solar heat gain J. MPC 10-Complete Envelope Design

a. Envelope design narrative

b. Envelope design K. MPC 11-Glazing

a. Glazing systems narrative L. MPC 12-Cooling and Heating Plants

a. Cooling and heating plants narrative

b. Cooling and heating plants LCC figures

c. Cooling and heating plants support calculations

d. Cooling and heating plants life cycle cost analysis M. MPC 13-Benchmarking: N/A N. MPC 14-HVAC Use: N/A O. MPC 15-Indoor Water

a. Indoor potable water scope ID and narrative

b. Indoor potable water LCC figures

c. Indoor potable water calculations

d. Indoor potable water life cycle cost analysis

e. Indoor water reduction plumbing/fixture schedule P. MPC 16-Outdoor Water

a. Outdoor potable water narrative

b. Outdoor potable water LCC figures

c. Outdoor potable water irrigation calculations

d. Outdoor potable water life cycle cost analysis Q. MPC 17-Measurement of Water Use

a. Rainwater capture narrative

b. Rainwater capture LCC figures

c. Rainwater capture life cycle cost analysis R. MPC 18-Process Water

a. Cooling tower potable water use narrative

b. Cooling tower potable water LCC figures

c. Cooling tower potable water use calculations

d. Cooling tower potable water use life cycle cost analysis S. MPC 19-Outdoor Water

a. Square footage of ground area disturbed T. MPC 20-Water Efficient Products: N/A U. MPC 21-Water Efficient Products: N/A V. MPC 22-Water Meter

a. Meter cooling tower scope W. MPC 23-Lighting Controls

a. Lighting controls narrative

b. Lighting controls LCC figures

c. Lighting control energy analysis X. MPC 24-Daylight: N/A Y. MPC 25-Occupancy Sensors Factor: N/A Z. MPC 26-Daylight Sensors: N/A AA. MPC 27-Environmental Tobbacco Smoke Control: N/A BB. MPC 28-Ventilation and Thermal Comfort: N/A CC. MPC 29-Moisture Control

a. Moisture control narrative DD. MPC 30-Ventilation and Thermal Comfort

a. Ventilation narrative

b. Pressurization narrative EE. MPC 31-Low Emitting Materials

a. Low emitting materials narrative

b. Low emitting materials checklist FF. MPC 32-Indoor Air Quality: N/A GG. MPC 33-Indoor Air Quality: N/A HH. MPC 34-Environmentally Preferable Products

a. Environmentally preferable products narrative II. MPC 35-Recycled Content: N/A JJ. MPC 36-Biobased Content:N/A KK. MPC 37-Waste and Materials Management:

a. Waste and materials management plan LL. MPC 38-Ozone Depleting Compounds: N/A MM. MPC 39-Transportation: N/A

1.4 EQUIPMENT AND TRAINING

A. Equipment

1. GSA will not furnish any equipment related to accessing gBUILD. gBUILD is webaccessible, and can therefore be accessed via any computer with an Internet connection.

B. Training

1. GSA will provide live online training via WebEx via to familiarize team members with the gBUILD system. The GSA Project Manager will determine which team members should attend training and what roles they will be set up within the system based on their project responsibilities.

C. Support

1. GSA will provide gBUILD system administration and end user support for the duration of the project.

1.5 PERSONNEL REQUIREMENTS

A. A NACI (National Agency Check with Inquiries) background check and investigation or higher (e.g. an HSPD-12 security clearance) is required to access gBUILD. Project Team members without at least a NACI check will need to work with the GSA Project Manager to initiate the clearance process. Once the individual’s HSPD-12 clearance is confirmed, a gBUILD username and password will be provided.

1.6 DATA OWNERSHIP

A. GSA shall retain ownership of all data entered into the system and shall administer and distribute all information contained therein.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 013000

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 – GENERAL

1.1 SUMMARY

A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:

1. General project coordination.

2. Coordination drawings.

3. Requests for Information (RFIs)

4. Conservation.

5. Administrative and supervisory personnel.

6. Conferences and meetings.

7. Utility service interruptions.

8. Cleaning and protection.

1.2 GENERAL PROJECT COORDINATION

A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation. Keep pipes, ducts, conduit, and the like as close as possible to ceiling slab, walls, and columns to take up a minimum amount of space. Locate pipes, ducts, and equipment so that they do not interfere with the intended use of eyebolts and other lifting devices.

Assure all controls can be reached and operated.

1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the Work depends on installation of other components before or after that part.

2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.

B. Notification: Prepare and distribute memoranda to each party involved, outlining special procedures required for coordination. Include notices, reports and meeting minutes as part of the memoranda.

C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work. Administrative procedures include but are not limited to the following:

1. Preparation of schedules.

2. Installation and removal of temporary facilities.

3. Delivery and processing of submittals.

4. Progress meetings.

5. Project closeout activities.

6. Startup and adjustment of systems.

1.3 COORDINATION DRAWINGS

A. Prepare coordination drawings where coordination is needed for installation of products and materials fabricated by separate entities, and prepare coordination drawings where limited space availability necessitates maximum use of the space for efficient installation of different components.

1. Show the relationship of components shown on separate shop drawings. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems

2. Indicate required installation sequences.

3. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

4. Show location and size of access doors.

5. Provide vertical and horizontal dimensions necessary to locate each component and avoid conflicts within the space.

6. Comply with shop drawing requirements for sheet size and submittal methods specified in Division 1 Section "Submittal Procedures."

B. Refer to Divisions 23, and 26 Plumbing, Heating Ventilating and Air Conditioning, and Electrical for specific coordination drawing requirements for mechanical and electrical installations.

C. Provide coordination drawings for equipment and system installations in mechanical and electrical rooms and spaces where two or more entities will provide the work and separate shop drawings are insufficient to show coordination.

D. Work installed prior to approval of coordination drawings shall be at the Contractor’s risk. Subsequent relocations required to avoid interferences shall be made without additional expense to the Government.

In case interference develops, the Government will decide which work shall be relocated, regardless of which was installed first.

E. Digital Data Files of Coordination Drawings: Prepare coordination digital data files in accordance with the following requirements:

1. File Preparation Format: Same digital data software program, version, and operating system as the original Drawings.

2. File Submittal Format: Same digital data software program, version, and operating system as the original Drawings and Portable Document Format (PDF).

3. GSA will furnish Contractor one set of digital data files of the Drawings for use in preparing coordination digital data files.

a. GSA makes no representations as to the accuracy or completeness of digital data files as they relate to the Drawings.

b. Execute a data licensing agreement in a form acceptable to the GSA, if required for Project.

1.4 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return RFIs submitted to Architect by other entities controlled by Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Architect.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: Form acceptable to Architect.

1. Attachments shall be electronic files in Adobe Acrobat PDF format.

D. Architect's Action: Architect will review each RFI, determine action required, and respond. Allow 10 working days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day.

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt of additional information.

3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect in writing within 10 days of receipt of the RFI response

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Use software log that is part of Project Web site.

F. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within 7 days if Contractor disagrees with response.

1. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate.

1.5 CONSERVATION