4. SPECIFICATIONS-Bldg 1406 and 1017-Switching Station.pdf
PDF 29 MB Posted
- Attached to
- Repair Base Switching Station
- Solicitation number
- FA489726B0006
About this file
This is a comprehensive specification document for the repair and reconstruction of the Base Switching Station at Mountain Home Air Force Base (MHAFB) in Idaho. The project encompasses construction of a new 12.5 kV electrical switching substation (Building B1017), transition of base electrical loads from the existing facility (Building B1406) to the new station, and demolition of the old switching station. The work includes site preparation, foundations, structural steel framing, installation of medium-voltage electrical equipment rated at 12.47 kV, construction of a control building, installation of power ductbanks and conduits, and comprehensive commissioning and testing of all systems.
The specification details extensive technical requirements across multiple construction divisions including civil work, concrete, masonry, structural steel, HVAC systems, electrical distribution, telecommunications, fire protection, and building commissioning. Major deliverables required include a project schedule using Primavera P6, quality control and special inspection plans, environmental protection and stormwater management plans, operation and maintenance manuals, as-built drawings in CAD format, building commissioning reports, and comprehensive training documentation. The contract incorporates provisions for utility outage coordination, temporary environmental controls, construction waste management with a minimum 60 percent diversion requirement, and adherence to military construction standards including UFC criteria. This is a small business set-aside solicitation under Solicitation Number FA489726B0006, issued by the Department of the Air Force Air Combat Command, with specifications prepared by HDR Engineering, Inc., and includes multiple performance requirements documented through detailed submittal procedures and quality assurance protocols.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prepared By:
HDR Engineering,Inc.
412 E. Parkcenter Blvd. Suite 100
Boise, ID 83706-6659
(208) 387-7000
100% Specifications V1 Add/Alt Base Switching Station, Bldg. 1406
Contract Number: FA4897-20-D-0001
Delivery Order: FA4897-21-F-0025
Mountain Home Air Force Base, ID
25 April 2022
-25-F-0026
16 July 2025
Repair Base Switching Station
100%
21 October 2025
Repair Base Switching Station MHAFBSWITCHGEAR
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24, CHG 1: 05/25 SUMMARY OF WORK
01 11 00.10 09/18 BASE CIVIL ENGINEER UTILITY OUTAGE
PROGRAM
01 11 00.20 09/18 BASE CIVIL ENGINEER WORK CLEARANCE
REQUEST
01 14 00 11/22, CHG 5: 05/25 WORK RESTRICTIONS
01 20 00 11/20, CHG 5: 02/25 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 5: 02/25 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 08/23, CHG 1: 08/24 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 05/24, CHG 1: 05/25 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 2: 05/25 QUALITY CONTROL
01 45 35 05/24 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 MHAFB 20220614 MHAFB TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 00.10 10/18 TRANSFER AND ACCEPTANCE FORM DD1354
01 78 00.20 10/18 CONSTRUCTION DATA SHEET
01 78 23 05/23, CHG 1: 05/25 OPERATION AND MAINTENANCE DATA
01 91 00.15 05/23, CHG 3: 08/24 BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
DIVISION 03 - CONCRETE
03 30 53 05/14 MISCELLANEOUS CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 05/25 UNIT MASONRY
DIVISION 05 - METALS
05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 50 13 08/24 MISCELLANEOUS METAL FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 08/23 BOARD AND BLOCK INSULATION
07 22 00 08/23 ROOF AND DECK INSULATION
07 27 10 08/23 BUILDING AIR BARRIER SYSTEM
07 60 00 08/23, CHG 1: 05/25 FLASHING AND SHEET METAL
07 61 14.00 20 08/16, CHG 1: 08/18 STEEL STANDING SEAM ROOFING
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
PROJECT TABLE OF CONTENTS Page 1
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 51 23 08/20, CHG 1: 02/22 STEEL WINDOWS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
DIVISION 09 - FINISHES
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 51 13 08/24 LOCKERS
DIVISION 12 - FURNISHINGS
12 35 70 08/16, CHG 2: 11/18 HEALTHCARE CASEWORK
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 15 05/22, CHG 2: 08/24 COMMON PIPING FOR HVAC
23 05 93 05/25 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 08/24 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 08 00 05/23, CHG 1: 08/24 COMMISSIONING OF MECHANICAL SYSTEMS
23 09 00 08/24 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 93 11/15 SEQUENCES OF OPERATION FOR HVAC CONTROL
23 23 00 08/21 REFRIGERANT PIPING
23 30 00 02/25 HVAC AIR DISTRIBUTION
23 81 00 05/24 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.00 08/24 CYBERSECURITY FOR ELECTRICAL CONTROL
SYSTEMS (ECS) - MODERATE IMPACT
25 05 11.01 08/24 CYBERSECURITY FOR HVAC CONTROL SYSTEMS
- LOW IMPACT
25 05 11.02 08/24 CYBERSECURITY FOR FIRE AND LIFE SAFETY
(FLS) SYSTEMS - MODERATE IMPACT
DIVISION 26 - ELECTRICAL
26 05 13.00 10 11/23 MEDIUM-VOLTAGE CABLES
26 05 73 08/23 POWER SYSTEM STUDIES
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 11 14.00 10 11/21 MAIN ELECTRIC SUPPLY STATION AND
SUBSTATION
26 12 19 05/24 PAD-MOUNTED, LIQUID-FILLED,
MEDIUM-VOLTAGE TRANSFORMERS
26 20 00 05/25 INTERIOR DISTRIBUTION SYSTEM
26 41 00 08/23 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
PROJECT TABLE OF CONTENTS Page 2
27 10 00 05/25 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 08/23 EARTHWORK
31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 21 13 11/18 RADON MITIGATION
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 20 05/22 SUBBASE FOR FLEXIBLE PAVING
32 11 23 05/22 AGGREGATE BASE COURSE FOR FLEXIBLE
PAVING
32 12 13 05/24 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23.16 11/24 ROAD AND PARKING LOT PAVEMENT MARKINGS
32 31 13.53 11/21 HIGH-SECURITY FENCES (ORNAMENTAL)
DIVISION 33 - UTILITIES
33 40 00 11/21 STORMWATER UTILITIES
33 71 01 05/19, CHG 1: 11/19 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
DIVISION 34 - TRANSPORTATION
34 75 13.13 02/22 CRASH RATED ACTIVE VEHICLE BARRIERS
AND CONTROLS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 4
D I V I S I O N 0 0
PROCUREMENT AND CONTRACTING
REQUIREMENTS
Repair Base Substation, Bldg 1406 MHAFBSWITCHGEAR
SECTION 00 01 07 Page 1
SECTION 00 01 07
SEALS AND SIGNATURES
I, James Zavadil, hereby certify that the portion of this technical submission described below was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the State of Nebraska.
Sections covered by this seal:
26 20 00, 26 41 00, 26 51 00, 27 10 00
I, Jeffrey A. Lewis, hereby certify that the portion of by me or under my direct supervision and that I am a the State of Idaho.
01 91 00.15, 23 05 15, 23 05 93, 23 07 00, 23 08 00, 23 09 00, 23 09 13, 23 09 93, 23 23 00, 23 30 00, 23 81 00, 31 21 13
I, Jill Brandt, hereby certify that the portion of this technical submission described below was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the
State of Idaho.
31 00 00, 31 05 19.13, 31 11 00, 32 11 20, 32 11 23, 32 12 13, 32 12 16.16, 32 16 19, 32 17 23.16, 32 31 13.53, 33 40 00, 34 75 13.13
I, Patrick Phelan, hereby certify that the portion of by me or under my direct supervision and that I am a the State of Nebraska.
10 44 16, 28 31 76
Repair Base Substation, Bldg 1406 MHAFBSWITCHGEAR
SECTION 00 01 07 Page 2
I, Grzegorz Stelmaszek, hereby certify that the portion of this technical submission described below was prepared by me or under my direct supervision and that
I am a duly registered Professional Engineer under the laws of the State of Nebraska.
01 45 35, 03 30 53, 05 21 00, 05 30 00, 05 50 13
I, Paul Derr, hereby certify that the portion of this or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the
State of Idaho.
01 11 00, 01 14 00, 01 20 00, 01 30 00, 01 32 01.00 10, 01 33 00, 01 33 29, 01 35 26, 01 45 00, 01 50 00, 01 74 19, 01 78 00, 01 78 23
I, John Schneider, hereby certify that the portion of by me or under my direct supervision and that I am a the State of North Dakota.
02 41 00, 26 05 13.00 10, 26 05 73, 26 08 00, 26 11 14.00 10, 26 12 19, 33 71 01, 33 71 02
I, Scott Heaney, hereby certify that the portion of this or under my direct supervision and that I am a duly registered Architect under the laws of the State of
Nebraska.
Sections covered:
04 20 00, 07 21 13, 07 22 00, 07 27 10, 07 60 00, 07 61 14.00 20, 07 84 00, 07 92 00, 08 11 13, 08 51 23, 08 71 00, 09 90 00, 10 51 13, 12 35 70
-- End of Section --
D I V I S I O N 0 1
GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
02/24, CHG 1: 05/25
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes, but is not limited to the following:
1. Procurement of all equipment and materials for new 12.5 kV Base Switching Substation.
2. Construction of new 12.5 kV Base Switching Substation.
3. Demolition of existing 12.5 kV Base Switching Substation.
4. Reconnection of existing 12.5 kV Distribution Circuits.
1.1.2 Location
The work is located at the Mountain Home Air Force Base, Idaho, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.2 OCCUPANCY OF PREMISES
Existing 12.5 kV Base Switching Substation must remain operational until new 12.5 kV Base Switching Substation is constructed and power can be cut over to new substation.
1.3 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Per Section 01 11 00.10 BASE CIVIL ENGINEER UTILITY OUTAGE PROGRAM.
1.3.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 11 00 Page 1
SECTION 01 11 00 Page 2
Add/Alt Base Switching Station, B1406 MHAFBSWITCHGEAR
SECTION 01 11 00.10 PAGE 1
DEPARTMENT OF THE AIR FORCE
366TH CIVIL ENGINEER SQUADRON (ACC)
MOUNTAIN HOME AIR FORCE BASE IDAHO
8 Mar 16
MEMORANDUM FOR RECORD
FROM: 366 CES/CEO
SUBJECT: Utility Outage Program
1. Purpose. The purpose of this instruction is to establish Standard Operating Procedures
(SOPs) for coordinating outages and to outline what outages require base populace and 366 FW leadership notification.
2. Definitions:
2.1. Outage: Any planned loss of service to water, power, or inability to use a road. In some circumstances, this may also include sewer. An outage occurs when power is shut off (even if a backup generator is available), water is turned off, or a road is blocked (partially or completely.)
Emergency outages are unscheduled and therefore not included in the Utility Outage Program.
2.2. Outage Requestor (OR). IAW 366 CES OI 32-3003, Base Civil Engineer Work
Clearance Request (Dig Permit), the OR is an individual within any shop who is responsible for identifying the need for and requesting of an outage. This can include the electric shop, utilities shop, P&E shop, or a construction inspector acting on behalf of a contractor. Contractors cannot schedule outages. The OR gathers and provides the outage details to the Outage Coordinator
(OC), at least 15 business days prior to any scheduled outage’s proposed beginning. The OR then provides the OC assistance in making any briefing slides, and contacts the affected facilities/users to notify them of the outage, NLT seven business days prior to its scheduled beginning. Use the checklist at Attachment 2 to document prior coordination.
2.3. Outage Coordinator (OC). CE Customer Service is the OC and primary point of contact for the Utility Outage Program. The OC coordinates with all CE Ops Flight sections, and maintains information on any construction activity occurring in other flights. The OC is responsible for gathering all pertinent data concerning an outage, scheduling the outage, coordinating support for the outage and ensuring the Outage Requestor has notified the facilities/users affected by the outage far enough in advance to prepare. If the outage is for a facility listed in the 366 CRP Tier 1 Facilities listing (Attachment 1), the OC will put together slide(s) (example at Attachment 3) and coordinate notification with slide(s) up through 366 CES squadron-level leadership not later than 10 business days in advance. To give CES leadership adequate time to notify MSG, and to get a response if there is any issue identified, the OC will notify Public Affairs NET 7 business days in advance. Additionally, main thoroughfares, and customer service focal areas (BX, Commissary, CDC, etc.) require prior PA notification.
2.4. Outage Support. Defined as anyone providing support to an outage (generally includes
CE Ops Flight shops, but can also include the Fire Department, Medical, LRS, SFS, etc.) These
SECTION 01 11 00.10 PAGE 2
individuals/shops/agencies help make the outage go as smoothly as possible. Outage Support will provide backup generators, alternate transportation, close roads, etc. The OR must request and coordinate all required support with responsible agencies prior to the outage.
3. Process:
3.1. The OR gathers data concerning the purpose of the outage, what needs to be shut down, when the optimal time is to shut it down, where the shutdown needs to occur, and who the shutdown will affect. Consider all needs listed in Attachment 4, and coordinate with 366
CES/CEI as warranted. OR then gives completed checklist to the OC who looks at any other operations occurring at that time, and recommends any changes that need to be made in scheduling. Similar outages should be scheduled simultaneously.
3.2. The OC, with the assistance of the OR, arranges support from the necessary Outage
Support agencies.
3.3. The OR notifies the affected facilities/users of the upcoming outage. After completing this, the OR notifies the OC who was contacted in the facilities affected and provides contact information for those individuals. This information can later be used for reminders or rescheduling. The OC then contacts facility POCs one day prior to outage, as a reminder.
3.4. (Optional). The OC assembles all data concerning the outage, including who was notified, into one easy-to-read slide. The slides for the different outages are assembled into a chronological presentation broken down by week. This presentation is briefed to Ops flight leadership and Programs Flight, with all ORs present to explain their outages. Separate meetings will be given to the CES/CC, MSG/CC and FW/CC when required. As noted above, this step is not necessary, but may be required depending on the impact of the outage.
4. Contact CE Customer Service at DSN 728-2001/Comm. (208) 828-2001 with questions or concerns.
// original signed Richard Miller for//
JESUS MENDOZA, Maj, USAF
Operations Flight Commander
4 Attachments:
1. Tier 1 Facilities
2. Checklist for Utility Outage/Road Closure
3. Example of Briefing Slide
4. Environmental Considerations in Planning Outages
Uncommon Acronyms:
CRP – Contingency Response Plan
NET – Not Earlier Than
OC – Outage Coordinator
OR – Outage Requestor
SECTION 01 11 00.10 PAGE 3
Date Completed:
� REQUESTING POC/Ofc Symbol / Phone No.
� Outage/closure request for (gas, water, elec, Phantom, Gunfighter Ave, etc.)
� Reason for outage/closure (If road closure required, also state what section of road, length of closed section, etc.):
� Requested outage/closure date(s):
� Estimated Time OFF/CLOSED: Estimated time ON/OPEN:
� Estimated duration of outage/closure:
Coordinate through the following agencies (as applicable):
(The coordinating official shall print name, initial and date on the appropriate line)
� CEOIU (Water Plant) - 8-3391
� CEOIU/2 (Utilities) Water/Gas/Sewer - 8-6444
� CEOIU/3 (Fuel) - 8-6538
� CEOF (Electrical/Emergency Generators) - 8-6604
� CEIE (Installation Flight/Environmental) – 8-6666
� CE Ops Management/Customer Service - 8-2001
� CEO/CD or CC - 8-6405/6406 (Ensures Sq-Lvl leadership notified)
(CSU ensures w/ Sq Secretary that CES/CC or CD has received “all clear” from MSG before notifying PA)
� Comm Sq - 8-3295/8-5715
� Housing Office - 8-2781
� Fire Department - 8-6005 (Mandatory for street/parking closures & water outages that affect hydrant pressure and/or fire suppression capability)
� Security Forces - 8-3874
� Hospital Emergency Room - 8-7100
(Mandatory for street/parking closures)
(Mandatory for all street/parking closures)
List of Facilities / quarters affected here:
BLDG #: BLDG NAME: ORGANIZATION: PERSON COORDINATED WITH: DATE CONTACTED:
(Note for requester: after completing this form, ensure CE Customer Service receives a copy prior to turning off utility / road closure)
SECTION 01 11 00.10 PAGE 4
Ready Engineers … Ready to Go
Repair broken water pipe near Bldg 512
Buildings Affected:
1501,512,510,610
ATTACHMENT 3:
SAMPLE UTILITY OUTAGE BRIEFING SLIDE
Utility Outage
W/O XXXXX
Date: 3 Feb
1000-1200
Ready Engineers … Ready to Go
Outage identified by
Outage Requestor
Outage Coordinator/Outage Requestor arrange assistance from Outage Support Agencies
Outage Requestor notifies facilities/users and obtains facility POC’s. Information passed to Outage Coordinator
Outage Coordinator prepares slide presentation, if required for briefing.
Outage worked and
Completed
Outage Coordinator contacts facilities/users 1 day prior to outage as a reminder
Power Outage Flow Chart
Outage Requestor gathers who, what, when, where, why, and purpose. Information is given to
Outage Coordinator.
10 duty day notice
SECTION 01 11 00.10 PAGE 7
1. Planning Power Outages:
1.1 Under the 2015 Air Quality Tier I Operating Permit, many of the stationary emergency backup generators are not allowed to run for non-emergency purposes other than routine maintenance of the generators. All other stationary emergency backup generators have a limited number of hours that the engine can run each year for non-emergency purposes. Planned loss of power is considered non-emergency use, and therefore the use of the emergency backup generators needs to be coordinated with the Air Quality Program Manager to ensure compliance with the air permit.
1.2. Per IDAPA 58.01.08.552.01.07: During a power outage, the water system shall be able to meet the operating pressure requirements of Subsection 552.01.b. for a minimum of eight (8) hours at average day demand plus fire flow where provided. A minimum of eight (8) hours of fuel storage shall be located on site unless an equivalent plan is authorized by the The Idaho
Department of Environmental Quality (IDEQ).
2. Planning Water Outages.
2.1. During planned maintenance or repair situations, when water pressure within the system is expected to fall below twenty (20) psi, the water supplier must provide public notice to the affected customers prior to the planned maintenance or repair activity and shall ensure that the water is safe for consumption.
2.2. If water pressure isn't expected to fall below 20 psi, but does, notify CEI flight immediately.
CEI flight will then notify IDEQ as well as push out public notifications to the affected community within 24-hours, and disinfect the system. When sampling and corrective procedures have been conducted and after determination by the Department that the water is safe, the water supplier may re-notify the affected customers that the water is safe for consumption. The water supplier shall notify the affected customers if the water is not safe for consumption.
3. Environmental Consideration in Not Otherwise Specified Outage Category: Broken transite
(cement asbestos) pipe is also covered under the air permit. The Asbestos Contingency Plan needs to be followed in the event that transite pipe is broken during repairs. Proper disposal of transite pipe should be coordinated through the Air Quality Program Manager.
SECTION 01 11 00.10 PAGE 8
HANGAR 208 DESIGN MHAFBHANGAR208
SECTION 01 11 00.20 PAGE 1
MHAFBSWITCHGEARAdd/Alt Base Switching Station, B1406
SECTION 01 11 00.20 PAGE 2
MHAFB Repair Parking Lot for 428 FS MHAFB428FSAdd/Alt Base Switching Station, B1406 MHAFBSWITCHGEAR
SECTION 01 11 00.20 PAGE 3
SECTION 01 11 00.20 PAGE 4
SECTION 01 11 00.20 PAGE 5
SECTION 01 11 00.20 PAGE 6
SECTION 01 11 00.20 PAGE 7
MHAFB Repair Parking Lot for 428 FS MHAFB428FSMHAFB428FSAdd/Alt Base Switching Station, B1406 MHAFBSWITCHGEAR
SECTION 01 11 00.20 PAGE 8
SECTION 01 11 00.20 PAGE 9
SECTION 01 11 00.20 PAGE 10
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 5: 05/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for information only.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals List of Contact Personnel
Planned Working Hour Schedule
1.3 SPECIAL SCHEDULING REQUIREMENTS
a. The existing 12.5 kV Base Switching Substation will remain in operation during the entire construction period. Conduct operations so as to cause the least possible interference with normal operations of the activity.
b. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, including delivery vehicles, are clearly identified with their company name.
1.4.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, SECTION 01 14 00 Page 1 correct and change the information contained in previous lists.
1.4.1.2 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.4.2 Working Hours
Regular working hours will consist of an 12 hour period, between 6 a.m.
and 6 p.m., Monday through Friday, excluding Government holidays.
1.4.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in accordance with requirements of EM 385-1-1 .
1.4.4 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, and fire alarm are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.
d. Operation of Station Utilities: Do not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. Notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.4.5 Work Areas
Confine operations to areas within Contract limits indicated. Portions of the site beyond areas in which construction operations are indicated are not to be disturbed.
1.4.6 Site Inspections
Contractor shall provide reasonable access to the site and shall not prohibit nor interfere with lawfully conducted inspections or site visits by properly identified representatives of regulatory agencies or collective bargaining units.
SECTION 01 14 00 Page 2
(1) Notwithstanding the above, Contracting Officer's Representative (COR) regulation governing site security shall be observed.
(2) All site visitors shall comply with personal protections and regulations, including hard hats and safety glasses.
1.4.7 Contracting Officer's Representative
Confer with Contracting Officer's Representative and obtain full knowledge of all site rules and regulations affecting work.
(1) Conform to site rules and regulations while engaged in project construction.
(2) Site rules and regulations take precedence over others that may exist outside such jurisdiction.
(3) Employee list: The Contracting Officer's Representative may examine Contractor's list of employees, including those of his subcontractors and their agents, at any time.
(4) Vehicle use: Rigidly enforce the following:
a. Keep all vehicles, mechanized or motorized equipment locked at all times when parked and unattended on Base's premises.
b. Do not, under any circumstances, leave any vehicle unattended with motor or engine running, or with ignition key in place.
c. Parking: Permitted only in areas designated by Contracting Officer's Representative.
d. All traffic control subject to Contracting Officer's Representative approval.
1.4.8 Access and Deliveries
Contractor shall access the site by designated haul routes only. Keep driveways and entrances serving the premises clear and available to the Government at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.
1.4.9 Hauling and Haul Route Maintenance
Sweep job site and designated haul routes as required to remove all spillage, mud and soil tracked from work site or dump site and to assure no damage to Government and personal property during the performance period. Cover all loads subject to spilling such as earth fill, aggregates, Portland cement concrete materials, asphalt cement concrete materials, rubble, trash, materials taken to land fill, etc. during hauling to prevent spillage. Sweep spills immediately. Spills of hazardous materials shall be responded to in accordance with Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS. Haul routes shall be approved by the Contracting Officer's representative to minimize impact to the base.
SECTION 01 14 00 Page 3
1.4.10 Government Operations
Perform the Work so as not to interfere with the Government's operations.
1.4.11 Utility Outages and Shutdown
Utility outages and shutdowns, should they be required for the performance of the work, shall be scheduled 21 working days in advance with the Contracting Officer. Outages shall be on weekends or weekdays specified by the Contracting Officer's representative at no additional cost to the Government. Outages shall be limited to 2 hours duration. All Contractor's operations shall be controlled to prevent any unscheduled interruptions of utility services and facilities.
1.4.12 Protection of Government Property
Protect all Government property within the site in which working, except for such property as is required to be demolished. Protect property which is to be demolished until its scheduled demolition time. Protection shall include, but not be limited to, protection from construction generated dust, debris, water, and vibration.
1.4.13 Maintenance and Repair of Pavements, Drives or Turf Areas
Maintain and repair pavements, drives or turf areas utilized during construction for access roads or storage areas, to the satisfaction of the Contracting Officer. Costs associated with the above work shall be incidental to the contract. Where landscape rock areas are repaired or installed, provide weed barrier under rock to prevent weed growth. Weed barrier shall be DeWITT PRO 5 Weed Barrier, 5 oz. Woven needle-punched material, or approved equal. Make sure landscape rock is free from dirt and debris if reused, and repair all wheel ruts, etc.
1.4.14 Planned Working Hour Schedule
Contractor shall coordinate with and obtain approval of the Contracting Office for his planned working hour schedule. Contractor shall also coordinate with and obtain approval of the Contracting Officer for any required working hours that fall outside his approved planned working hours schedule.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 14 00 Page 4
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/20, CHG 5: 02/25
PART 1 GENERAL
1.1 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.1.1 Submission of Invoices
If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the Contract, provide the documents listed in above paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.
Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.
1.1.2 Final Invoice
a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 20 00 Page 1
SECTION 01 20 00 Page 2
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 5: 02/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for information only.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map
Progress and Completion Pictures
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice one set of digital photographs in the agency construction management system of record, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch with the submission in the agency construction management system of record as a digital file. Include a date designator in file names. Photographs provided are for unrestricted use by the Government.
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, SECTION 01 30 00 Page 1 during the entire period of performance under this contract. Provide other insurance coverage as required by Idaho State law.
1.6 SUPERVISION
1.6.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.6.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.6.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time or excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION CONFERENCE
After award of the contract, but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
SECTION 01 30 00 Page 2
1.7.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 30 00 Page 3
SECTION 01 30 00 Page 4
SECTION 01 32 01.00 10
PROJECT SCHEDULE
08/23, CHG 1: 08/24
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
AACE 84R-13 (2015) Planning and Accounting for Adverse Weather
AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)
ASCE 67-17 (2017) Schedule Delay Analysis
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (2017) Administration -- Project Schedules
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for information only.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G
Preliminary Project Schedule; G
Initial Project Schedule; G
Periodic Schedule Update; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The Designated Project Scheduler must have prepared and maintained at least three previous construction schedules for projects of similar size and complexity to this contract, using Primavera P6..
Representative must have a comprehensive knowledge of CPM scheduling principles and application.
SECTION 01 32 01.00 10 Page 1
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Government Default Software
The Government uses Primavera P6. Ensure exported schedule files are compatible with the version of P6 used by the Government.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system. Verify at the SEKO meeting which version of P6 is in use by the Government. Export the schedule in a version of P6 no newer than that used by the Government.
2.1.2.2 Other Than Primavera
If the Contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors, and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.1.1 Scheduling Expectations Kickoff Meeting(SEKO)
In conjunction with the post award conference or pre construction conference the Government and the Contractor will hold a separate and distinct Scheduling Expectations Kickoff Meeting(SEKO). The intent of this meeting is for the Government to review with the contractor the
SECTION 01 32 01.00 10 Page 2 requirements of the scheduling specification, communicate the Government’s expectations regarding schedule development and management, and answer any questions the Contractor may have regarding the schedule requirements.
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN. Match the progress payment "Pay Period Thru" date in RMS to the schedule data date.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Activities with a negative cost loading is not allowed. Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Cost Loading of Submittals
No costs are to be assigned to activities for the preparation, review, or approval of submittals, except as described under paragraph COST LOADING OF CLOSEOUT ACTIVITIES, paragraph AS-BUILT DRAWINGS, and paragraph O&M
MANUALS.
3.2.3 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial, or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Non-procurement activities Original Durations (OD) are not to exceed 20 workdays or 30 calendar days.
SECTION 01 32 01.00 10 Page 3
3.3.3 Procurement Activities
Include in the schedule activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Activities
Include the following activities in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission of mechanical/electrical/information systems layout drawings.
c. Submission and approval of O & M manuals.
d. Submission and approval of as-built drawings.
e. Submission and approval of DD1354 data and installed equipment lists.
f. Submission and approval of testing and air balance (TAB).
g. Submission of TAB specialist design review report.
h. Submission and approval of fire protection specialist.
i. Submission and approval of Building Commissioning Plan, Controls testing plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
These activities may include but are not limited to: air and water balancing, building commissioning -functional performance testing, controls testing, and performance verification testing. Include other systems testing, if required. Include additional commissioning requirements noted elsewhere in the Contract as required in the schedule and discuss during the SEKO meeting, noted in paragraph
SCHEDULING EXPECTATIONS KICKOFF MEETING (SEKO).
j. Contractor's pre-final inspection.
k. Correction of punch list from Contractor's pre-final inspection.
l. Government's pre-final inspection.
m. Correction of punch list from Government's pre-final inspection.
n. Final inspection.
SECTION 01 32 01.00 10 Page 4
3.3.5 Government Activities
Show in schedule, Government and other agency activities that could impact progress. These activities include, but are not limited to environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein.
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government
SECTION 01 32 01.00 10 Page 5
Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for Air Force).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
Activities cannot have more than one Work Area Code.
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Number (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
3.3.6.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.
a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.
b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
3.3.6.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.6.8 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the
SECTION 01 32 01.00 10 Page 6 approved QC plan.
Definable Feature of Work is defined in Section 01 45 00 QUALITY CONTROL.
An activity can have only one Feature of Work Code.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or affect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.3.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.3.7.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the…