10. Level 1 Executive Summary Project Schedule.pdf

PDF 132 KB Posted

Attached to
Repair Base Switching Station
Solicitation number
FA489726B0006
Issued by

About this file

This document is a project schedule for the Mountain Home Air Force Base (MHAFB) Repair Switching Station B1406 and Power Station B1017, dated December 12, 2025. The schedule presents a comprehensive timeline spanning from the second quarter of 2026 through the third quarter of 2034, encompassing design, contracting, preconstruction, and construction phases for two interconnected projects.

The Power Station Building (New Construction) project begins with design and contracting activities (Date of Estimate: 10/31/2025, Final Design Complete: 10/31/2025, Funding Phase: 12/12/2025), followed by Issue for Bidding (2/27/2027) and Bidding Phase (3/6/2027). Contract Award is scheduled for 6/19/2027, with Preconstruction activities (Shop Drawings, Submittals, etc.) commencing 7/3/2027. Construction begins 9/30/2029 and includes demolition (asphalt roadway and parking lot paving), concrete and site work, underground utilities installation (electrical and plumbing by 12/15/2029), structural framing and roofing (2/16/2030 through 8/10/2030), and interior systems installation (electrical, HVAC, plumbing, doors, windows, and electronic safety/security systems by 10/19/2030), with interior finishes and electrical transmission distribution completing 3/28/2031.

The Electrical Switch Station Building (Repair) project follows a similar timeline with Construction Commencement on 9/30/2029, including site preparation, demolition of existing infrastructure (asphalt roadway, railroad ties, fence, sidewalk, and utilities by 10/29/2029), and utility installations (communications, electrical service, roadways, sidewalks, and transmission/distribution systems from 1/12/2030 through 2/19/2030). Commissioning is scheduled for 3/28/2030, followed by demolition of the existing switch substation building (5/30/2030) and project closeout activities (Pre-Punch & Cleanup: 7/18/2030, Final Punch & Cleanup: 8/15/2030, Project Closeout: 9/8/2030, with final PROJECT COMPLETION on 9/28/2030).

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task

Mode

Design/Contracting/Preconstruction

10/31 Date of Estimate

10/31 Final Design Complete

12/12 Funding Phase

2/27 Issue for Bidding

3/6 Bidding Phase

6/19 Contract Award

7/3 Preconstruction (Shop Drawings, Submittals, Etc.)

Power Station Building (New Construction)

9/30 Construction Commencement

10/1 Demo Asphalt Roadway Paving

10/13 Demo Asphalt Parking Lot Paving

10/27 Install Concrete Footings

10/27 Install Parking Lot

10/27 Install Milled Area with Geotextile Fabric

10/27 Install Site Development (Fence, Pedestal & Equipment Rack)

10/27 Install Storm Drainage Ponds & Reservoirs

12/15 Install Underground Electrical Utilities

12/15 Install Underground Plumbing Services

1/12 Install Slab on Grade

2/16 Install Roof Structural Frame & Deck

2/16 Install Concrete Stoops

4/13 Install Vertical Enclosure

8/10 Install Roofing System

10/5 Install Interior Partitions

10/5 Install Storm Drain Piping

10/19 Install Interior Doors & Windows

10/19 Install Plumbing Services

10/19 Install HVAC System

10/19 Install Electrical System (Including Ductbanks)

10/19 Install Electronic Safety and Security

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

2026 2027 2028 2029 2030 2031 2032 2033 2034

2029 2034

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Level 1 Executive Summary Project Schedule, MHAFB - Repair Switching Station Station B1406 & Power Station B1017

12 Dec 2025

MHAFB REPAIR SWITCHING STATION B1406 &

Dec 12, 2025

ID Task

Mode

3/28 Interior Finishes

3/28 Install Site Elec Transmission and Distribution

Electrical Switch Station Building (Repair)

9/30 Construction Commencement

10/1 Site Preparation (Clearing and Earthwork)

10/8 Site Demolition (Asphalt Roadway, Railroad Ties, Fence & Sidewalk)

10/29 Site Utility Demolition (Electrical Services & Irrigation Piping System)

1/12 Install Utilities - Communications Distribution

1/12 Install Electrical Service & Distribution

1/12 Install Site Roadways

1/26 Install Site Development (Fence & Signage)

2/2 Install Sidewalks

2/9 Install Utilities - Electric Transmission & Distribution

2/19 Install Grounding System

10/5 Install Lighting Protection System

3/28 Commissioning

5/30 Demo Existing Switch Substation Building

Punchlist & Closeout

7/18 Pre-Punch & Cleanup

8/15 Final Punch & Cleanup

9/8 Project Closeout

9/28 PROJECT COMPLETION

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

2026 2027 2028 2029 2030 2031 2032 2033 2034

2029 2034

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Critical

Critical Split

Progress

Manual Progress

Mountain Home AFB - Repair Switching Station Station B1406 & Power Station B1017

100% Design Construction Schedule

12 Dec 2025

MHAFB REPAIR SWITCHING STATION B1406 &

Dec 12, 2025